Crescent Electric Supply Company v. Employers Mutual Casualty Company

107 N.W.2d 252, 79 S.D. 18, 1961 S.D. LEXIS 5
South Dakota Supreme Court·Decided January 27, 1961·No. File 9888·Published·Cited by 5 cases

Opinion

SMITH, P. J.

Employers Mutual Casualty Company, defendant above named, and hereinafter referred to as surety, delivered its performance bond on behalf of a subcontractor, Kruse Electric Company, to the prime contractor, Broadway Construction Company, in connection with the *19 construction of a school building at Brush, Colorado. During construction plaintiff, Crescent Electric Supply Company of Rapid City, South Dakota, supplied materials to the subcontractor. Before the work was completed under its contract, the subcontractor defaulted. This action is by Crescent Electric against the surety on the performance bond for a balance alleged to be due for materials supplied to the subcontractor which went into the described construction. Three checks of the prime contractor, payable to the subcontractor and the Crescent Electric, representing payment for materials furnished by the subcontractor, were delivered to Crescent Electric, and were applied by it on an open account of the subcontractor. The propriety of this application of those payments by Crescent Electric is the narrow issue presented by this appeal.

The subcontract and the performance bond were in the amount of $21,800. The materials furnished a>s described amounted to $14,526.67. When the first materials were furnished the subcontractor was indebted to Crescent Electric in the approximate sum of $8,654.71 on open account. The materials so furnished were charged as delivered on this 'open account. During the progress of the work other materials were furnished to the subcontractor and payments received, which had no relation or connection with the subcontract in question. These items were entered on the open account. During the work the subcontractor executed and delivered to Crescent Electric written assignments aggregating $20,000 of the amount to become due under the subcontract, which assignments, omitting the amount thereof, were in words as follows:

“This is to advise you that Kruse Electric, Electric'al Contractor, doing work on the Brush Elementary School for Broadway Construction Co., has assigned his account and all monies due him from the Broadway Construction Company for work done, or to be done on this project to Crescent Electric Supply Company, Box 1728, Rapid City, South Dakota. * * *
*20 “Therefore, any checks that you might be sending to Kruse Electric covering work done, or to be done on this project should be made out jointly to Kruse Electric and Crescent Electric Supply Company. * * *”

These assignments were executed by Kruse Electric and Crescent Supply and were delivered to the prime contractor. During the course of construction three payments aggregating $12,581.15 were made by the prime contractor by its checks made payable to1 Crescent Electric and to the subcontractor. These checks, according to the stipulation of facts “were in fact payments made by the principal contractor Broadway Construction Company for materials furnished by said John Kruse to the Brush Elementary School job * * *” and were delivered by the prime contractor directly to Crescent Electric. However, no express direction was given by anybody as to the application of these payments. Crescent Electric made application upon its open account of the subcontractor to the oldest items due thereon. In this action it alleged that there remained due to it $9,-205.72 for materials furnished to the subcontractor and used in the construction of the Brush school.

The facts were stipulated. The trial court entered judgment for plaintiff as prayed. The defendant surety has appealed, and contends that its defense of payment should have been sustained as the Crescent Electric was bound to apply the described payments upon the obligation of the subcontractor for materials which went into the Brush school building.

The application of payments as between a debtor and creditor are controlled by SDC 47.0207 reading in part as follows:

“Where a debtor, under several obligations to another, does an act by way of performance in whole or in part, which is equally applicable to two or more of such obligations, such performance must be applied as follows:
*21 “(1) If, at the time of the performance, the intention or desire of the debtor that such performance should be applied to the extinction of any particular obligation, be manifested to the creditor, it must be so applied;
“(2) If no such application be then made, the creditor, within a reasonable time after such performance, may apply it toward the extinction of any obligation, performance of which was due to him from the debtor at the time of such performance; except that if similar obligations were due to him, both individually and as a trustee, he must, unless otherwise directed by the debtor, apply the performance to the extinction of all such obligations in equal proportion; and an application once made by the creditor cannot be rescinded without the consent of the debtor;”

Predicated upon subsection (1) of SDC 47.0207 quoted supra, the defendant contends “while there was no direction in words as to the manner of the application of the payments in question, the intention or desire of the debtor and of Broadway Construction, which made the payments, that such payments should be applied to the extinction of the particular obligation, that is the obligation for materials furnished to the particular job, was, under all of the attendant circumstances, manifested to the creditor, Crescent Electric' Supply Company, Inc., and that such creditor was, therefore, required to apply such payments accordingly.”

The Crescent Electric, on the other hand, insists, that in the absence of an express direction by the prime contractor or subcontractor, it was entitled to act under SDC 47.0207(2), supra, and apply the payments as it did, and that the surety has no such interest or equity in the payments as would qualify it to ask for reapplication of those payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Crescent Electric Supply Company v. Employers Mutual Casualty Company, 107 N.W.2d 252, 79 S.D. 18, 1961 S.D. LEXIS 5 (S.D. 1961).

107 N.W.2d 252 (Crescent Electric Supply Company v. Employers Mutual Casualty Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Larson Concrete Co. v. Stroschein
353 N.W.2d 354 (South Dakota Supreme Court, 1984)
Jacobson v. United National Bank (In Re Jacobson)
5 B.R. 274 (D. South Dakota, 1980)