Crescent Corp. v. Protor & Gamble Corp.

627 F. Supp. 745, 1986 U.S. Dist. LEXIS 29555
CourtDistrict Court, N.D. Illinois
DecidedFebruary 6, 1986
Docket85 C 8930
StatusPublished
Cited by5 cases

This text of 627 F. Supp. 745 (Crescent Corp. v. Protor & Gamble Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crescent Corp. v. Protor & Gamble Corp., 627 F. Supp. 745, 1986 U.S. Dist. LEXIS 29555 (N.D. Ill. 1986).

Opinion

MEMORANDUM OPINION AND ORDER

SHADUR, District Judge.

Crescent Corporation (“Crescent”) has sued Procter & Gamble Company (“P&G”) and Huber, Hunt & Nichols, Inc. (“HH&N”) in a two-count Complaint arising out of Crescent’s engineering, design, *746 manufacture and installation of the curtain-wall for P&G’s office building in Cincinnati, Ohio, on which HH&N assertedly acted as P&G’s agent:

1. Count I seeks quantum meruit recovery from P&G for over $2 million in extra materials and services going far beyond the original contract requirements.
2. Count II seeks damages (both compensatory and punitive) against both P&G and HH&N for fraud: It alleges false representations that a change order would be executed covering the extras, in reliance on which representations Crescent went ahead with the work.

Defendants removed the case from its original forum (the Circuit Court of Kane County, Illinois) to this District Court, then moved to dismiss or alternatively to transfer this action to the Southern District of Indiana, Indianapolis Division. For the reasons stated in this memorandum opinion and order, such transfer (rather than dismissal) is granted.

Defendants’ alternative prayer for relief does not advance a 28 U.S.C. § 1404(a) motion in conventional form — the statutory successor to the forum non conveniens doctrine, allowing transfer as a matter of balancing conveniences. Defendants’ focus is rather on the forum selection clause (the “Clause”) in Article 9 of the “Subcontract Agreement CF19A” (the “Subcontract”) between HH&N as “Contractor” and Crescent as “Subcontractor”:

Any suit brought for any breach of the Subcontract and any litigation arising under the Subcontract is here agreed to be maintained in any court of competent jurisdiction in the County and State shown as Contractor’s address, Article I., Recitals, CF19A.

HH&N’s address in the cited portion of the Subcontract was shown as 2450 South Tibbs Avenue, Indianapolis, Indiana 46241.

Most of the Complaint’s allegations characterize HH&N as P&G’s “agent” (see, e.g., Complaint ¶1¶ 4, 6, 7 and 8) and hence assert the Subcontract was entered into “for and on behalf of P&G” (Complaint ¶ 12). All this is of a piece with the allegation (Complaint 116) that the earlier contract between P&G and HH&N (though it may well have been a construction contract under which P&G was designated as owner and HH&N as contractor) was an “on-going association” the Complaint refers to as the “P&G Enterprise.” Consistently with those allegations, Crescent alleges the extras that form the gravamen of the Complaint were furnished “at the special instance and request of P&G and Huber [HH&N], acting in the furtherance of the affairs of the P&G Enterprise” (Complaint 1118), and the same paragraph alleges those extras “were agreed to, approved by and accepted by P&G and Huber in the furtherance of the affairs of the P&G Enterprise, and.. .now benefit P&G and Huber and the P&G Enterprise....”

Crescent’s Count I is labeled, and is alleged in part in the form of, a quantum meruit claim — a claim based on benefits conferred by Crescent on P&G. But it cannot be gainsaid the Count I claim really asserts a “breach of the Subcontract” within the meaning of the Clause. Indeed the claim, though not articulated in a conceptually precise manner, essentially says P&G was bound by the Subcontract because HH&N entered into it for P&G’s benefit. Complaint H 19 therefore calculates and alleges the amount due in terms of Crescent having fully performed all work under the Subcontract and thus being “entitled to the full payment of all sums remaining unpaid therefor.”

In much the same way, Count II does not charge fraud in the inducement of the Subcontract (the kind of claim that ordinarily precludes a defendant from bootstrapping itself by seeking to invoke a forum selection clause in the very contract that is under attack and that would be vitiated if the fraud-in-the-inducement claim were upheld). Instead Count II actually charges defendants with having violated their contractual obligation to sign change orders for authorized extras (see Subcontract Article VI and, presumably, Subcontract Terms and Conditions Article *747 18 2 ). Whether viewed in that manner or as the kind of fraud claim Crescent asserts, Count II plainly constitutes “litigation arising under the Subcontract” for purposes of the Clause.

At least in surface terms, then, the just-completed analysis brings the Clause potentially into play as to this entire litigátion. Before this opinion turns to whether that potentiality translates into actuality, or to the impact on this lawsuit if it does, a threshold question must first be considered: the enforceability vel non of the Clause. In that respect Crescent’s President John Wegman (“Wegman”) has stated by way of affidavit that HH&N and Crescent had arrived at an oral agreement for the curtainwall long before the Subcontract was entered into (or even drafted). As Wegman’s Affidavit puts it:

9. Subsequent to the reaching of the aforesaid oral agreement, but prior to the receipt of any draft of Exhibit A [the Subcontract], and prior to the receipt of any of the contents of Attachment III to Exhibit A hereto [which includes the Clause], and specifically Exhibit C hereto, Crescent expended in excess of $500,-000 on the design, engineering, fabrication, manufacture and providing of labor and materials to the Proctor & Gamble Project.
10. It was not until the basic contract terms concerning price and scope of work had been negotiated, the aforesaid oral agreement and understanding reached with respect thereto, and Crescent had already expended the aforesaid significant sums of money in the engineering, design, and construction of the Proctor & Gamble Project, that the written contract (Exhibit A hereto) and the attachments thereto (including Attachment III and Exhibit C hereto) was given to Crescent to sign.
11. None of the contents of Attachment III to the Contract (Exhibit A hereto), and specifically none of the contents of Exhibit C hereto was the subject of any negotiation or of any discussion between any representative of Crescent and any representative of HH&N prior to the completion of the construction of the Proctor & Gamble Project.
12. None of the contents of Attachment III to the Contract (Exhibit A hereto), and specifically the contents of Exhibit C hereto, were subject to any negotiation between the parties, but all of such terms were presented to Crescent by HH&N on a take it or leave it basis. But that version has proved to be no

more than a half-truth. It turns out the Subcontract (including the Clause) was part of the “Bid Package” that had been tendered to Crescent as the predicate for its initial formulation of a bid for the curtain-wall work (Randall Ket (“Ket”) Jan. 10, 1986 Aff. ¶ 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magi Xxi, Inc. v. Stato Della Città Del Vaticano
818 F. Supp. 2d 597 (E.D. New York, 2011)
Allianz Ins. Co. of Canada v. Cho Yang Shipping Co., Ltd.
131 F. Supp. 2d 787 (E.D. Virginia, 2000)
Banco Popular De Puerto Rico v. Airborne Group PLC
882 F. Supp. 1212 (D. Puerto Rico, 1995)
First Financial Leasing Corp. v. Hartge
671 F. Supp. 538 (N.D. Illinois, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
627 F. Supp. 745, 1986 U.S. Dist. LEXIS 29555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crescent-corp-v-protor-gamble-corp-ilnd-1986.