Creedon Controls, Inc. v. Banc One Building Corp.

470 F. Supp. 2d 457, 2007 U.S. Dist. LEXIS 4432, 2007 WL 149002
CourtDistrict Court, D. Delaware
DecidedJanuary 22, 2007
DocketCIV A 05-300-JJF
StatusPublished
Cited by1 cases

This text of 470 F. Supp. 2d 457 (Creedon Controls, Inc. v. Banc One Building Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creedon Controls, Inc. v. Banc One Building Corp., 470 F. Supp. 2d 457, 2007 U.S. Dist. LEXIS 4432, 2007 WL 149002 (D. Del. 2007).

Opinion

MEMORANDUM OPINION

FARNAN, District Judge.

Pending before the Court are Defendant Banc One Building Corporation’s (“Banc One”) Motion For Summary Judgment (D.I. 115) and Defendant Forest Electric’s *459 (“Forest”) Motion For Partial Summary Judgment. (D.I. 120). For the reasons discussed, Banc One’s Motion will be granted and Forest’s Motion will be denied.

I. BACKGROUND

Banc One was tasked to construct two data centers, Core Data Center 1 and Core Data Center 2 (“CDC 1” and “CDC 2”). Banc One selected Tishman Construction of Maryland (“Tishman”) to act as the “Construction Manager,” and Banc One’s agent, for the CDC 1 and 2 project. Banc One also contracted with co-defendant Forest to serve as the “Trade Manager for Electrical Work” for the project. Tishman and Forest entered into a Trade Manager Agreement which set forth the parties’ understandings with regard to their roles and responsibilities. Forest was tasked with coordinating all electrical power and data connections work, and had the responsibility of competitively bidding and awarding this work to subcontractors.

After submitting a successful bid, Plaintiff Creedon Controls, Inc. (“Creedon”) was selected by Forest to perform part of the electrical work. Creedon contracted directly with Forest, as an electrical subcontractor. Forest supervised and coordinated Creedon’s performance throughout the project, and served as an intermediary between Creedon, Tishman, and Banc One for any changes to the scope of the project. Forest was also responsible for scheduling the work of all of its electrical subcontractors, including Creedon.

Upset with the significant delays and cost increases it was facing because of Defendants’ alleged inefficiency and improper behavior, Creedon initially filed its complaint against Defendants Banc One and Forest in Delaware Superior Court. The case was removed to this Court on May 17, 2005. Banc One and Forest filed the current Motions on July 14, 2006.

II. PARTIES’ CONTENTIONS

A. Banc One’s Motion For Summary Judgment

By its Motion, Banc One contends that the Court should grant summary judgment in its favor because no contract was ever formed between itself and Creedon. Defendant further contends that Creedon and Forest have failed to establish an agency relationship between Banc One and Forest. Therefore, Banc One contends, summary judgment must be granted because there is no relationship between Creedon and Banc One that could expose Bane One to liability.

In response, both Creedon and Forest contend that summary judgment is inappropriate because there are genuine issues of material fact in dispute as to the existence of an agency relationship between Banc One and Forest.

B. Forest’s Motion For Partial Summary Judgment

By its Motion, Forest contends that summary judgment is warranted because there is a contract between Forest and Creedon which expressly precludes any damages for delay. Forest also contends that it was merely an agent of Banc One, and therefore should not be held liable for any damages Creedon may be awarded.

In response, Creedon contends that there are genuine issues of material fact as to what contract language binds the parties and as to which party Creedon may recover from. Creedon also contends that the No-Damages-For-Delay clause is unenforceable due to Forest’s bad faith. In its response, Banc One agrees with Forest that contract language expressly precludes damages arising from Forests delays. *460 However, Banc One contends that there are no facts to support Forest’s contention that it was an agent of Banc One.

III. LEGAL STANDARD

Pursuant to Rule 56(c) of the Federal Rules of Civil Procedure, a party is entitled to summary judgment if a court determines from its examination of “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any,” that there are no genuine issues of material fact and that the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). In determining whether there are triable issues of material fact, a court must review all of the evidence and construe all inferences in the light most favorable to the non-moving party. Goodman v. Mead Johnson & Co., 534 F.2d 566, 573 (3d Cir.1976). However, a court should not make credibility determinations or weigh the evidence. Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150, 120 S.Ct. 2097, 147 L.Ed.2d 105 (2000).

To defeat a motion for summary judgment, the non-moving party must “do more than simply show that there is some metaphysical doubt as to the material facts. In the language of the Rule, the non-moving party must come forward with ‘specific facts showing that there is a genuine issue for trial.’ ” Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586-87, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (citations omitted). However, the mere existence of some evidence in support of the non-movant will not be sufficient to support a denial of a motion for summary judgment; there must be enough evidence to enable a jury to reasonably find for the non-movant on that issue. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

IV. DISCUSSION

Because the parties do not dispute that Banc One and Creedon never contracted directly with each other, the Court must consider whether there is sufficient evidence to enable a jury to find that Forest was acting as Banc One’s agent. If there is not, the Court must grant Defendant’s Motion, because Creedon will have failed to show any basis under which Banc One might be liable to Creedon.

A principal is liable for the actions of its agent that are within the scope of the agent’s actual or apparent authority. Restatement (Second) of Agency § 140. Actual authority is created by words or conduct of the principal, which reasonably cause the agent to determine that the principal wishes the agent to act on the principal’s behalf. Edwards v. Born, Inc., 792 F.2d 387, 389-90 (3d Cir.1986). Apparent authority, on the other hand, can be created by words or conduct of the principal, which reasonably cause a third party to believe that the agent is acting on the principal’s behalf. Id. at 390.

The Court concludes that no jury could reasonably find that Forest had actual authority to act on Banc One’s behalf.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
470 F. Supp. 2d 457, 2007 U.S. Dist. LEXIS 4432, 2007 WL 149002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creedon-controls-inc-v-banc-one-building-corp-ded-2007.