Creamery Package Mfg. Co. v. Cheyenne Ice Cream Co.

100 P.2d 116, 55 Wyo. 277, 1940 Wyo. LEXIS 12
CourtWyoming Supreme Court
DecidedMarch 12, 1940
Docket2125
StatusPublished
Cited by7 cases

This text of 100 P.2d 116 (Creamery Package Mfg. Co. v. Cheyenne Ice Cream Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creamery Package Mfg. Co. v. Cheyenne Ice Cream Co., 100 P.2d 116, 55 Wyo. 277, 1940 Wyo. LEXIS 12 (Wyo. 1940).

Opinion

*282 Blume, Justice.

On March 31, 1936, the plaintiff, the Creamery Package Manufacturing Company, a corporation organized under the laws of Illinois and having a branch office at Denver, Colorado, entered into a. contract at Denver, Colorado, with the defendant, the Cheyenne Ice Cream Company, for the shipment to, and installation at, Cheyenne, Wyoming, of certain refrigerating equipment. This equipment, as stated in the contract, consisted of a super-freezer door, a cold storage door, and certain manufactured products consisting of a compressor, a refrigerating machine, a main shaft, flywheel weighing 480 pounds, ammonia condensor six feet long and fifteen inches wide, ammonia receiver, interceptor, gauges, ammonia pipe connections, electric motor of fifteen horsepower, automatic control devices, and other manufactured products. It further agreed to furnish “hardening room to be insulated with eight-inch corkboard in walls, floor and ceiling; anteroom, to be insulated with four-inch corkboard in walls and ceiling, with six-inch corkboard insulation in partition between hardening room and anteroom.” The hardening room was to have an average temperature of 10° below zero, and the anteroom an average temperature of plus 40°, the company to furnish the piping. In that connection it was stated that “the company will furnish piping for the circulation of ammonia in the rooms * * * all valves, fittings and hangers. The *283 piping will be arranged in coils suitable for the purposes for which the rooms are intended. Valves will be placed where required for shutting oif any coil or room. The company will furnish necessary connections between coils and balance of the system.” The rooms were to contain “1075 ft. 1^4" shelf pipe coils for cooling the above room controlled by 1 -CP 8" x 24" Accumulator & float control for operating flooded system. Coils to be equipped with suction and liquid headers.” The plaintiff agreed to furnish one erecting engineer to install the equipment furnished by it and to furnish and pay all other help necessary for the placing, connecting and starting the machinery in operation. The purchaser agreed to furnish all masonry and carpenter work of every description, foundation of all machinery, electrical wiring, suitable openings in the building for the admission of the machinery and openings in walls and partitions for pipelines, and all material necessary to the completion of the contract not specifically mentioned to be furnished by the plaintiff. It was agreed that the purchase price should be §3155.00 upon the following terms, namely: Cash with the order of §1865.00, the balance to be paid in fifteen equal monthly installments of §86.00 each, beginning June 5, 1936. It was agreed that if the purchaser should default at any time in the amounts due under the contract the seller should have the right to retake possession of the property. It was further agreed that “any part of this agreement contrary to the laws of the state in which it is written or executed or to be enforced shall not invalidate any other part of this agreement.” The purchaser paid on the down payment the sum of §900 in April, 1936. It was entitled to a credit for freight paid of §190.86. It made a further payment of §588.25 on May 5, 1937, making a total which was credited by the seller on the down payment of §1679.11. The purchaser also paid six of the monthly install *284 ments due, but no other, and defaulted in the payments. Thereupon, on February 6, 1937, the plaintiff in this ease brought an action in replevin in the district court of Laramie County to recover possession of the property sold to the defendant. An answer was filed in that case, setting up the fact that plaintiff was not entitled to recover on the contract because of the fact that it was not domesticated in this state. The plaintiff thereupon dismissed that action, domesticated on May 1, 1937, and brought this action on February 15, 1938, to recover the balance due under the contract. The court, after the trial of the case, rendered judgment in favor of the defendant and from that judgment plaintiff has appealed.

1. On May 5, 1937, the defendant paid the sum of 1585.25 on the contract and demanded that it be credited on the deferred payments, and now claims that if that had been done the whole amount due to the plaintiff would be paid. It seems, further, that when the conditional sales contract was filed of record in Laramie County, Wyoming, an affidavit was attached thereto stating that the balance due was $1290.00. This did not take into consideration the amount then due on the down payment. It is the theory that the contract recites that the down payment was received and that this recital cannot be contradicted by parol testimony. The contract does not, in fact, contain any such recital. It merely recites, in stating the terms of the consideration, that the down payment should be $1865, but only $900 was actually paid. Even if the statement might be considered as a recital of having received that sum, that would be immaterial. Such recital “in a written instrument as to payment of the consideration is merely in the nature of a receipt and may be contradicted.” 22 C. J. 1167. The facts in this case do not fall within any exception to that rule. The affidavit above mentioned, reciting that only $1290 was due at *285 the time when the conditional sales contract was filed, would be but an admission which could be contradicted. The uncontradicted testimony in this case shows that the amount claimed by the plaintiff herein is due and owing. The judgment in this case should accordingly have been in favor of the plaintiff, unless the defense hereinafter mentioned is good.

2. Art. 10, Sec. 5, of the Constitution of this state, provides that no corporation organized under the laws of Wyoming Territory or any other jurisdiction than this state shall be permitted to transact business in this state until it shall have accepted the constitution of this state and filed such acceptance in accordance with the laws thereof. Section 28-141, Rev. St. 1931, makes provision to carry the foregoing constitutional provision into effect. The defendant herein pleaded that at the time when the contract above mentioned was entered into, plaintiff had not complied with the foregoing constitutional and statutory provisions; that plaintiff, in carrying out the contract, was doing business in this state, particularly in connection with constructing the hardening room and the anteroom mentioned in the contract. The plaintiff in its reply stated that it neither affirmed nor denied the construction of these rooms. That pleading was improper, and was equivalent to an admission, under Sec. 89-1026, Rev. St. 1931, which provides that every material allegation of new matter in the answer not controverted by the reply shall, for the purpose of the action, be taken as true. See also Building Association v. Clark, 43 O. S. 427; Lake v. Steinbach, 5 Wash. 659, 32 Pac. 767.

Plaintiff also denied that it was doing business in this state, and further alleged, and now contends, that even if it was doing business in the state in performing the contract, the right to set up the defense of non-domestication was waived by the defendant by reason *286

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waterworks Industries, Inc. v. Aplex Industries, Inc.
802 P.2d 894 (Wyoming Supreme Court, 1990)
True v. Hi-Plains Elevator MacHinery, Inc.
577 P.2d 991 (Wyoming Supreme Court, 1978)
Ford Motor Company v. Arguello
382 P.2d 886 (Wyoming Supreme Court, 1963)
Indiana Department of State Revenue v. Surface Combustion Corp.
111 N.E.2d 50 (Indiana Supreme Court, 1953)
Deaton Truck Lines, Inc. v. Bahnson Co.
36 S.E.2d 465 (Supreme Court of South Carolina, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
100 P.2d 116, 55 Wyo. 277, 1940 Wyo. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creamery-package-mfg-co-v-cheyenne-ice-cream-co-wyo-1940.