Creamery Package Manufacturing Co. v. Benton County Creamery Co.

95 N.W. 188, 120 Iowa 584
CourtSupreme Court of Iowa
DecidedMay 22, 1903
StatusPublished
Cited by12 cases

This text of 95 N.W. 188 (Creamery Package Manufacturing Co. v. Benton County Creamery Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creamery Package Manufacturing Co. v. Benton County Creamery Co., 95 N.W. 188, 120 Iowa 584 (iowa 1903).

Opinion

Ladd, J.

Prior to March 4, 1899, the Benton County ■Creamery Company, a copartnership composed of Chester A. Hodge and L. C. Eggleston, was engaged in establishing ;a creamery at Yin ton. A building for that purpose was nearly completed. A canvass had been made, and oral agreements entered into with farmers, by whom the milk •of ten or twelve hundred cows had been pledged on condition that, beginning May 1st, it should be taken at the farms, and, after the separation" of the butter fat therefrom, the skim milk returned, and the expenses incident to making the butter, shipping, and marketing it paid, all at a cost to them of four cents per pound, they to receive the balance obtained for the butter. To carry out their part of the arrangement, the defendants had employed a .butter maker at $50 per month, and men with teams to haul the milk on various routes, all i^o commence work May 1st. Some correspondence had been had with plaintiff, and on March 4, 1899, acting through an agent, Pat-feiam, it contracted to furnish defendants an outfit for said creamery for $1,625, tobe shipped “at any time designated by second party after three weeks from date thereof and before sixty days from date thereof.” The agent was fully informed of the arrangements detailed, and of the necessiiy of having the creamery ready for operation by May 1st. On the 14th of April the machinery for an ice plant was bought through the same agent, on the representation that the creamery outfit was ready for shipment, and that the refrigerator machinery, except some coils and tanks, was also ready, and all save these would be placed in a car and forwarded wifhiit forty-eight hours. This is ■denied by the agent, but satisfactorily established by other ■evidence. Had the shipment been made as proposed, the [586]*586defendants might have opened their creamery on the day-expected, though the ice plant might not have been, entirely completed by that time. Instead of loading all. in one car, the articles were separately shipped from the-1st to the 15th of May, and plaintiff’s expert did not arrive until May 17th; From ten days to two weeks are ordinarily required to place such machinery, and the ice plant, was not in readiness for operation until June 5th. In the-meantime many of the promised patrons of the creamery,, being relieved from their .obligation by failure to open, on May 1st or within a reasonable time thereafter, deliv ered their milk to other parties; and defendant, instead of receiving from ten to twenty thousand pounds of milk per day, as the evidence tended to show they would have done had the creamery been ready May 1st, had in fact taken, in but five hundred pounds. To secure the return of park of their customers, even, they were compelled to do the-work at a greatly reduced price. The defendants demanded in their counterclaim the payment of damages owing to the breach of the condition of the contract fixing the time of delivery. The objection interposed is that prospective profits of this character are too uncertain,, remote, and speculative to furnish a basis of compensation..

.Recovery of anticipated profits was generally denied, in the earlier decisions. An exception seems to have been-first made in the casé of torts. Gibson v. Fischer, 68 i. delay in furnishing raa-chinery: ulative damages. Iowa, 29. Later such profits were allowed,. _ _ . the omect ox the contract, or fairly within the contemplation of the parties, and! their loss was the direct consequence -of the breach. Hirschorn v. Bradley, 117 Iowa, 130; Rule v. McGregor, 117 Iowa, 419. In the two cases last cited, the agreements had for their design profits to be derived directly therefrom. In others the character of the agreement may be such as to advise the parties of the precise' nature of the loss likely to flow directly from a failure to fulfill, as the [587]*587interruption of an established buisness, as was pointed out. in the leading case of Hadley v. Baxendale, 9 Exch. 341. But in others there may be a loss of prospective profits,, which, owing to the impossibility of ascertaining whether resulting directly from the failure to perform, or the relative loss therefrom as compared with other causes, are rejected by the courts as a measure of damages, because-of being too uncertain and conjectural for the practical administration of justice. The chief difficulty in distinguishing between the two latter classes is in determining whether the alleged loss of profits resulted directly from the breach of the agreement. If it does, and it was within the contemplation of the parties, the better opinion seems-to be that the profits which would in all reasonable probability have been acquired but for such breach should be awarded; otherwise recovery is to be denied unless some other measure of damages, as the reasonable value of the-use lost, is available.

Turning now to the case at bar, it is to be observed that neither the making of profits, nor providing the opportunity to do so, formed a part of the contract. No doubt, the ultimate purpose of all business enterprise is the derivation of some advantage through the investment of labor or capital, or both; butj when the manufacturer engages to supply machinery for a plant, it is no part of the contract that a profitable business shall be carried on by the machinery furnished. If there be delay, he may be responsible for the loss of the use, or possibly for inter-ést on the investment, where there is no rental value, but not for loss of profits in the business proposed, which necessarily are contingent upon many circumstances, and which might or might not have been made. Penneypacher v. Jones, 106 Pa. 237, 242; Mining Syndicate v. Fraser,. 130 D. S. 611 (9 Sup. Ct. Rep. 665, 32 L. Ed. 1031); Howard v. Stillwell, 139 U. S. 199 (11 Sup. Ct. Rep. 500, 35 L. Ed. 147). Moreover, this enterprise was new, and exper-[588]*588fence had furnished no criterion by which to estimate the probable profits. See Goebel v. Hough, 26 Minn. 252 (2 N. W. Rep. 847); Cushing v. Seymour, 30 Minn. 305 (15 N W. Rep. 249); Paola Gas Co. v. Paola Glass Co., 56 Kan. 614 (44 Pac. Rep. 621, 54 Am. St. Rep. 598). Those to be derived by defendants' from the operation of the creamery depended so largely upon its management, the acquirement and continuance of patronage, the conditions of the butter market, and other considerations, that it would be exceedingly difficult, if not utterly impossible, to ascertain with any degree of accuracy the fruits of the enterprise lost by reason of the delays complained of. Even whero the direct object of a contract, it is not easy, as was observed in Rule v. McGregor, to fix upon a satisfactory estimate. But without further discussion, it is perhaps enough to say that for the mere delay in furnishing machinery which does not interrupt an established business, according to the settled doctrine of this court, prospective profits cannot be allowed by way of damages. Brownwell v. Chapman, 84 Iowa, 504; Novelty Ironworks v. Oatmeal Co., 88 Iowa, 524.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harsha v. State Savings Bank
346 N.W.2d 791 (Supreme Court of Iowa, 1984)
Corning v. Iowa-Nebraska Light & Power Co.
282 N.W. 791 (Supreme Court of Iowa, 1938)
J. L. Owens Co. v. Leland Farmers Elevator Co.
198 Iowa 271 (Supreme Court of Iowa, 1924)
Sargent v. Frank Cram & Sons
194 Iowa 152 (Supreme Court of Iowa, 1922)
Shaffer v. Morgan
188 Iowa 772 (Supreme Court of Iowa, 1920)
Morgan v. Sutlive Bros.
126 N.W. 175 (Supreme Court of Iowa, 1910)
Swift & Co. v. Redhead
122 N.W. 140 (Supreme Court of Iowa, 1909)
Inman Manufacturing Co. v. American Cereal Co.
142 Iowa 558 (Supreme Court of Iowa, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
95 N.W. 188, 120 Iowa 584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creamery-package-manufacturing-co-v-benton-county-creamery-co-iowa-1903.