Crawford Painting & Drywall Company v. J.W. Bateson Co., Inc.

857 F.2d 981, 1988 U.S. App. LEXIS 14934, 1988 WL 99930
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 10, 1988
Docket87-5545
StatusPublished
Cited by6 cases

This text of 857 F.2d 981 (Crawford Painting & Drywall Company v. J.W. Bateson Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crawford Painting & Drywall Company v. J.W. Bateson Co., Inc., 857 F.2d 981, 1988 U.S. App. LEXIS 14934, 1988 WL 99930 (5th Cir. 1988).

Opinion

REAVLEY, Circuit Judge:

Claiming breach of contract, fraud, negligence and civil RICO violations, the subcontractor who lost money on a large construction contract has recovered over $7,000,000 by the district court’s judgment. Finding no legal basis for a recovery, we reverse the judgment and dismiss the cause.

A. BACKGROUND

J.W. Bateson Co., Inc. executed a contract with the United States Army Corps of Engineers on September 19, 1976 to do extensive remodeling and new construction at Wilford Hall United States Air Force Area Medical Center in San Antonio, Texas. Bateson and Crawford Painting and Drywall Company executed a contract on March 14, 1977 for Crawford to do the dry wall work for $2,164,000. Bateson, Crawford, and the other sixteen subcontractors encountered difficulties on this project from the beginning. Reliable drawings of the existing facilities were not available. Construction had to proceed around the continuing operation of a very large hospital. But the largest source of trouble was the great volume of the change orders. As is so often the case, as the medical personnel and hospital administrators became conversant with the plans prepared by the Corps, the user insisted on modifications which the Corps then required of the prime contractor. In the early stages of the construction, Bateson would receive as many as 20 change orders in a week. Though the scheduled completion date was originally July 30, 1981, the project was not finally completed until August 4, 1983.

One document, often discussed in this record and identified as P00253, was an agreement between Bateson and the Corps on April 19,1979 to extend the time for the completion of the contract and its phases. By that agreement an additional 148 com-pensable work days were allowed to the contractors. Additional extensions were necessary before the actual completion.

Knowing that all of the subcontractors, as well as Bateson itself, were entitled to *984 pursue substantial claims for additional compensation against the Corps under the Contract Disputes Act, 41 U.S.C. §§ 601 et seq., Bateson brought all of the subcontractors together in the spring of 1982 for the purpose of collaborating on a joint claim. The parties signed what was called the Liquidation Agreement for that purpose, and they did file with the Corps a joint claim which covered the claims of each subcontractor and the prime contractor. Crawford executed these documents on October 28, 1982.

During the course of negotiations in early 1984 Bateson and the Corps agreed upon a certain number of extra compensable days of construction. That number was less than the number claimed in the 1982 documents. When Crawford was advised of this negotiated number, his investigation led him to believe that Bateson had released and cut off the subcontractors from any delay claim prior to the 1979 P00253 and that this was the cause of the reduction in compensable days which Bateson purported to agree upon in 1984. Crawford then revised its own claim and, after a delay to obtain an unqualified certification by Bateson for the Corps, the revised claim was finally accepted by the Corps. This claim has since been denied by the contracting officer of the Corps and is pending in the Court of Claims. See 41 U.S.C. § 609(a)(1).

Looking at the evidence in the worst light for Bateson, as we must do in the face of the jury verdict, Crawford was left in the dark on requests and agreements between the Corps and Bateson to change and reschedule the work. By the time of the 1979 negotiations between owner and prime contractor, the latter was at some risk because of possible liability for liquidated damages due to the contractor’s failure to meet the contract schedule. The jury was entitled to believe that, in negotiating with the Corps, Bateson’s concern was not to protect the claims of Crawford so much as to care for its own position in the balance between its potential liability to the Corps and its own claims against the Corps.

Crawford filed this lawsuit against Bate-son on March 28, 1985. Federal jurisdiction was predicated on civil RICO counts under 18 U.S.C. § 1964(c), and other claims were made under state law for fraud, breach of contract, and negligence. The trial commenced on November 4, 1986 and concluded on December 22. It required 18 days of testimony and several boxes of exhibits. The tone of the trial was set by the opening statement of Crawford’s attorney when he told the jury “that J.W. Bate-son Co. abused and defrauded Mr. Crawford in the course of the construction of that project and caused Mr. Crawford to lose a business that it took him over 50 years to establish.” He contended in this opening argument, as has been contended in all of the court papers and throughout the proceedings, that the case is marked by the “landmark of fraud, and it runs through this project just like the San Antonio River runs through San Antonio....”

Two witnesses, the son of the owner of the Crawford Company and a professor of economics, testified on Crawford’s damages. But no evidence was submitted to relate any item of damage to specific acts or omissions of Bateson. These witnesses simply took all of Crawford’s financial experience during the Wilford Hall project, including the collapse of the Crawford business, and added the losses together for very large totals. Johnny Crawford, for example, presented two different computations which he called his performance method and shortfall method. The performance method added together the same items claimed against the Corps for job delay, with very large costs of borrowing because of interest paid to banks for short term credit, the loss of the business, legal and professional fees in the controversy and lawsuit with Bateson, and arrived at a total of $1,779,152.41. By the shortfall method he added all costs of Crawford in connection with the Wilford Hall project, together with 15% for administrative overhead and 10% for profit, plus the very large outlays for interest expense during these years. From this he deducted the $2,665,-000 paid by Bateson for the project work, leaving total shortfall damages of $3,178,- *985 013. The economics professor computed damages by his “claims method” at $1,778,-740.18 to which he added the interest costs for $3,659,958. In his shortfall computation he allowed for all of the profits on other jobs that Crawford would have made if it had not undertaken the Wilford Hall project, and added the other losses and costs for total damages computed to be $5,085,658.

The jury was apparently impressed by plaintiffs presentation. Plaintiff failed only on its civil RICO claim. The jury found for the plaintiff on fraud, breach of contract, and negligence. The judgment of the trial court was based upon findings of $2,383,333.33 damages for fraud and an award of $4,000,000 punitive damages. Attorneys fees were awarded of $730,000.

It should be immediately apparent from the first reading of these briefs that the fraud award and the punitive damages cannot stand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Tex. v. American Tobacco Co.
14 F. Supp. 2d 956 (E.D. Texas, 1997)
Ralston Purina Co. v. McKendrick
850 S.W.2d 629 (Court of Appeals of Texas, 1993)
US for Use of Allied Bldg. Prod. v. Federal Ins.
729 F. Supp. 477 (D. Maryland, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
857 F.2d 981, 1988 U.S. App. LEXIS 14934, 1988 WL 99930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crawford-painting-drywall-company-v-jw-bateson-co-inc-ca5-1988.