This text of Commercial Painting Company, Inc. v. The Weitz Company, LLC (Commercial Painting Company, Inc. v. The Weitz Company, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Painting Company, Inc. v. The Weitz Company, LLC, (Tenn. Ct. App. 2014).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON July 23, 2014 Session

COMMERCIAL PAINTING COMPANY, INC. V. THE WEITZ COMPANY, LLC ET AL.

Appeal from the Chancery Court for Shelby County No. CH0615733 Kenny W. Armstrong, Chancellor

No. W2013-01989-COA-R3-CV - Filed November 18, 2014

In this construction contract dispute, the trial court granted summary judgment in favor of the defendant general contractor as to all of the plaintiff subcontractor’s tort claims. The parties proceeded to trial on the remaining issues and judgment was awarded in favor of the subcontractor. Both parties raise numerous issues on appeal. Because we conclude that the trial court applied an improper standard in granting summary judgment, we vacate the order of summary judgment in favor of the general contractor. In addition, because the subcontractor’s tort claims may alter the remaining issues in this case, we decline to consider the remaining issues raised by the parties. Vacated and remanded.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Vacated and Remanded

J. S TEVEN S TAFFORD, J., delivered the opinion of the Court, in which D AVID R. F ARMER, J., and R OBERT L. C HILDERS, S P. J., joined.

Scott A. Frick, Memphis, Tennessee, for the appellant, Commercial Painting Company, Inc.

Jeffrey C. Smith, Memphis, Tennessee, for the appellee, The Weitz Company, LLC.

Holly Streeter-Schaefer, Kansas City, Missouri, admitted Pro Hac Vice, for the appellee, The Weitz Company, LLC.

OPINION Background

This case arises over a contract dispute between general contractor, Defendant/Appellee The Weitz Company, Inc. (“Weitz”), and its dry-wall subcontractor, Plaintiff/Appellant Commercial Painting Company, Inc. (“Commercial Painting”). Weitz is a foreign limited liability company who was employed to construct a multi-building retirement community in Germantown, Tennessee. Commercial Painting is a closely-held Tennessee corporation owned by Mark Koch. Commercial Painting’s primary business is performing commercial and residential construction wallcovering, painting, drywall installation, metal stud installation, and other projects.

The contract at issue involved the construction of a multi-building facility in Shelby County. After Commercial Painting successfully bid on the project, in September of 2004, the parties entered into a subcontract for Commercial Painting to perform substantial work on the project. The subcontract provided that Commercial Painting would be paid $3,222,400.00 for its work on the project. Specifically, the subcontract obligated Commercial Painting to perform drywall installation throughout the project. In some places, Commercial Painting was required to perform a high level finish on the dry wall, in order that the wall could be painted. For the remainder of the contract obligations, however, Commercial Painting was only required to perform a mid-level finish on the walls. Whether Commercial Painting actually performed at this level would become an issue of much dispute as the project progressed.

Allegedly, at the time the parties entered into the subcontract, Weitz was already approximately six to eight months behind schedule on the project. Commercial Painting would later assert that Weitz improperly and unreasonably compressed construction schedules in order to make up for the delay on the project. According to Weitz, however, the project became further behind once Commercial Painting began working on the project in the winter of 2004 due to Commercial Painting’s allegedly poor worksmanship and failure to provide enough workers to timely complete the project. Because of this, Weitz allegedly began negotiating with the project owner regarding an extension on the contract completion date. It appears that the project owner eventually allowed a six-month extension, but Commercial Painting was only informed that an extension of approximately four months had been granted. According to Commercial Painting, Weitz intentionally and fraudulently failed to disclose the full extent of the extension, in violation of the letter and spirit of the contract.1 Even with the extension, however, Commercial Painting alleged that Weitz continued to

1 According to Commercial Painting, Weitz failed to disclose the full extent of the extension because it hoped to complete the project forty-five days early, thereby earning a bonus from the project owner for early completion.

2 compress its schedules and improperly supplement its work because the extension did not entirely mitigate the eight-month delay on the project.

As previously discussed, the parties also disagreed as to the level of work required by the contract, and both parties asserted that they incurred additional delays and additional costs to bring the work to the desired level. Eventually, Weitz hired additional workers to supplement the work done by Commercial Painting, alleging that it was required due to Commercial Painting’s delays. Commercial Painting objected to the supplementation and later alleged that they were required to perform even more work to correct the work of the supplemental workers. At the conclusion of the contract, Weitz paid Commercial Painting on Pay Applications 1 through 12. However, Weitz refused to pay Commercial Painting on Pay Applications 13 through 17, which allegedly included previously agreed-upon work, as well as additional work beyond the contract amount.

Commercial Painting filed a complaint for damages on August 11, 2006, seeking an award of $1,929,428.74, constituting damages for unpaid progress payments, interest on retainage, extra work, unjust enrichment, plus attorney’s fees and interest. In addition to its claims against Weitz, Commercial Painting also sought a judgment against Weitz’s sureties. Weitz filed an Answer and Counterclaim on January 24, 2007, seeking $500,000 for costs incurred on the project due to delays caused by Commercial Painting. Weitz claimed an additional $233,217.51, representing damages under the liquidated damages provisions of the parties’ contract, as well as increased management expenses resulting from the need for additional supervision of the supplemental workers retained by Weitz to complete the project.

On February 10, 2009, Weitz filed a Motion for Partial Summary Judgment pertaining to Commercial Painting’s contract claims, arguing that Commercial Painting had waived its right to payment of some of its claims by its failure to comply with the modification terms in the subcontract. In response, in the fall of 2009, Commercial Painting filed two motions to amend its complaint to assert additional causes of action in tort, as well as a claim for punitive damages on the basis that the construction schedule attached to the subcontract was inaccurate and inconsistent with alleged statements about the schedule. The trial court granted Commercial Painting’s request to amend its complaint on October 29, 2009. Accordingly, Commercial Painting filed an Amended Complaint on November 25, 2009. In addition to its prior contract claims, Commercial Painting raised additional claims for fraud, intentional and negligent misrepresentation, and rescission/reformation of the subcontract. Specifically with regard to rescission, Commercial Painting contended that the subcontract “should be rescinded in its entirety, or in the alternative, reformed to adjust the subcontract price to include additional compensation to [Commercial Painting] for work, labor, and materials[,] which [Commercial Painting] has provided and incorporated into the Project.” Finally, Commercial Painting sought punitive damages against Weitz in the amount of

3 $10,000,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dorothy King v. Virginia Betts
354 S.W.3d 691 (Tennessee Supreme Court, 2011)
Abshure v. Methodist Healthcare-Memphis Hospitals
325 S.W.3d 98 (Tennessee Supreme Court, 2010)
B & B Enterprises of Wilson County, LLC v. City of Lebanon
318 S.W.3d 839 (Tennessee Supreme Court, 2010)
Tennie Martin, et.al. v. Southern Railway Company, et.al.
271 S.W.3d 76 (Tennessee Supreme Court, 2008)
Hannan v. Alltel Publishing Co.
270 S.W.3d 1 (Tennessee Supreme Court, 2008)
Colonial Pipeline Co. v. Morgan
263 S.W.3d 827 (Tennessee Supreme Court, 2008)
Walker v. Sunrise Pontiac-GMC Truck, Inc.
249 S.W.3d 301 (Tennessee Supreme Court, 2008)
Stovall v. Clarke
113 S.W.3d 715 (Tennessee Supreme Court, 2003)
Concrete Spaces, Inc. v. Sender
2 S.W.3d 901 (Tennessee Supreme Court, 1999)
McCarley v. West Quality Food Service
960 S.W.2d 585 (Tennessee Supreme Court, 1998)
Haynes v. Cumberland Builders, Inc.
546 S.W.2d 228 (Court of Appeals of Tennessee, 1976)
Early v. Street
241 S.W.2d 531 (Tennessee Supreme Court, 1951)
Loveday v. Cate
854 S.W.2d 877 (Court of Appeals of Tennessee, 1992)
Atkins v. Kirkpatrick
823 S.W.2d 547 (Court of Appeals of Tennessee, 1991)
McElroy v. Boise Cascade Corp.
632 S.W.2d 127 (Court of Appeals of Tennessee, 1982)
Carvell v. Bottoms
900 S.W.2d 23 (Tennessee Supreme Court, 1995)
Stone v. Hinds
541 S.W.2d 598 (Court of Appeals of Tennessee, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Commercial Painting Company, Inc. v. The Weitz Company, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-painting-company-inc-v-the-weitz-compan-tennctapp-2014.