Craig & Kelly Turner v. Gordon Baldwin

CourtCourt of Appeals of Washington
DecidedOctober 13, 2020
Docket52470-8
StatusUnpublished

This text of Craig & Kelly Turner v. Gordon Baldwin (Craig & Kelly Turner v. Gordon Baldwin) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Craig & Kelly Turner v. Gordon Baldwin, (Wash. Ct. App. 2020).

Opinion

Filed Washington State Court of Appeals Division Two

October 13, 2020 IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II CRAIG and KELLY TURNER, No. 52470-8-II

Appellants,

v.

GORDON BALDWIN, NORMAN SIMON, UNPUBLISHED OPINION BARBARA SIMON, MARK TAYLOR, SARAH TAYLOR, PIERCE COUNTY, and STATE OF WASHINGTON SHORELINES HEARINGS BOARD,

Respondents,

And

WASHINGTON STATE DEPARTMENT OF ECOLOGY,

Respondents Below.

SUTTON, A.C.J. — Craig and Kelly Turner appeal a superior court order affirming a

Shoreline Hearings Board decision denying their application for permits under the Shoreline

Management Act of 1971 (SMA) to construct a single-use pier/dock, boathouse, and boatlift on

the northeast shoreline of Hale Passage at Point Fosdick in Pierce County. The Turners argue that

the Board’s findings are not supported by substantial evidence, the findings do not support the

Board’s conclusions of law, and the decision is clearly erroneous, arbitrary, and capricious. They

also argue that Pierce County’s Shoreline Master Program (PCC SMP) and regulations as applied

violate their fundamental constitutionally protected rights to build a pier/dock at this location. We No. 52470-8-II

hold that the superior court and the Board did not err as the findings are supported by substantial

evidence, they support the Board’s conclusions of law to deny the permits, and are not clearly

erroneous, arbitrary, or capricious.1 We also hold that the Turners do not have a fundamental right

to build the proposed pier/dock at this location. Both the Turners and some of the respondents

request appellate attorney fees and costs. We agree with the respondents, and award Gordon

Baldwin, Norman and Barbara Simon, and Mark and Sarah Taylor reasonable appellate attorney

fees and costs, and we deny the Turners’ request.

FACTS

I. SHORELINE DEVELOPMENT

The Turners own a single-family residence on Hale Passage at Point Fosdick in Gig Harbor.

The property has 100 feet of shoreline frontage and a bulkhead approximately four feet high. The

Turners applied for a substantial development permit and a conditional use permit to: (1) construct

a 150-foot long by 8-foot wide single-use pier/dock; (2) place a 20-foot long by 10-foot wide

boatlift at the south end of the proposed pier/dock; and (3) construct a 192-square-foot boathouse

landward of the existing bulkhead.2 The proposed pier/dock would be located at the northeast

shore of Hale Passage at Point Fosdick, across from Fox Island.

Under the PCC SMP, the Turners needed to obtain a shoreline development permit for the

proposed pier/dock and a conditional use permit for the boatlift and boathouse. PCC 20.56.030,

1 Based on our holding, we decline to consider the Turners’ challenges to findings of fact 3, 7, 15, 22, 23, 25, and 27. 2 They also wanted to remove an existing hot tub and construct an integrated swimming pool and hot tub, but these items are not issues on appeal.

2 No. 52470-8-II

20.72.030-.040. Shoreline development permit applications are subject to Washington State’s

SMA, chapter 90.58 RCW, its policies, and regulations.

After reviewing the Turners’ permit application, a Pierce County Hearings Examiner

approved a shoreline development permit for the proposed pier/dock, pool, and hot tub; approved

a conditional use permit for the boatlift at the end of the pier/dock; but denied a permit for the

boathouse. As required, the Washington State Department of Ecology reviewed and approved the

conditional use permit for the boatlift, but because the County denied a conditional use permit for

the boathouse, the Department of Ecology rendered no decision on this aspect of the proposal. The

Taylors, who own adjoining shoreline property immediately to the east, and Baldwin and the

Simons, who own the two shoreline properties immediately to the west, appealed the County’s

decision approving the pier/dock and the boatlift. The Turners cross-appealed the County’s denial

of a conditional use permit for the boathouse, and the Taylors intervened to oppose the boathouse

appeal. The three shoreline appeals were consolidated.3

II. PROCEDURE

A. THE BOARD’S FINDINGS, CONCLUSIONS, AND DECISION

On appeal, the Board reversed the County’s approval of the proposed pier/dock, and found

that it was not a preferred use under the PCC SMP, the regulations, or SMA policies. The Board

further found that the proposed pier/dock and boathouse did not satisfy the criteria for a shoreline

development permit under the PCC SMP, the regulations, or the SMA policies. The Board ruled

3 Respondent Department of Ecology filed a brief only related to whether the Turners’ proposed boathouse is a water dependent use or an accessory use under the PCC SMP and the SMA.

3 No. 52470-8-II

that the proposed pier/dock failed to satisfy three separate and independent criteria under PCC

20.56.040(A). In sum, the Board found that (1) the proposed pier/dock would obstruct and impair

marine oriented recreation areas and thus, the second part of the first criteria under PCC

20.56.040(A)(1) was not satisfied; (2) reasonable moorage alternatives to the proposed pier/dock

exist for the Turners, and thus, PCC 20.56.040(A)(5) criteria was not satisfied; (3) the intensity of

the Turners’ intended use of the proposed pier/dock was not compatible with the surrounding

environment and land and water uses, and thus, PCC 20.56.040(A)(7) criteria was not satisfied;

and (4) the Turners’ proposed boathouse was not a water dependent accessory use, and thus, it did

not qualify for a conditional shoreline permit under PCC 20.62.050(D)(2).

1. The Proposed Pier/Dock and Boatlift4

The Board concluded that the proposed pier/dock “will obstruct or impair marine oriented

recreation” and found that this shoreline is regularly used by boaters, rowers, kayakers and

swimmers to navigate around the extreme waterward end of the proposed project. Clerk’s Papers

(CP) at 589 (conclusion of law (CL) 17).

The Turners own their private tidelands. The beach in this area consists of sand and pea

gravel and is regularly used by many beach walkers who visit or live along or near this shoreline.

The Turners have allowed beach walkers to cross regularly onto their shoreline and they testified

that they would continue to do so.

4 Although the proposed boatlift requires a separate permit and is therefore a separate issue, we discuss the boatlift and the proposed pier/dock together because the boatlift can only exist if the pier/dock exists.

4 No. 52470-8-II

Pierce County Planning and Land Services staff evaluated the impacts to marine oriented

recreation from the proposed pier/dock and concluded that:

[M]arine oriented recreation will incur an impact as the approval of the [pier/]dock could result in rowers/kayakers and swimmers traveling further into deeper[,] open waters of Hale Passage to navigate around the extreme waterward end of the [pier/dock]. In addition, if approved, it will create a perception to a beach walker that beach access is limited in this area.

CP at 579 (findings of fact (FF) 35) (internal quotation marks omitted).

There are no docks for over six miles to the east and one mile to the west of the Turners’

proposed pier/dock; it would be the first of its type along this stretch of shoreline. Pierce County

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Samson v. City of Bainbridge Island
202 P.3d 334 (Court of Appeals of Washington, 2009)
May v. Robertson
218 P.3d 211 (Court of Appeals of Washington, 2009)
Buechel v. Department of Ecology
884 P.2d 910 (Washington Supreme Court, 1994)
Maytown Sand & Gravel, LLC v. Thurston County
423 P.3d 223 (Washington Supreme Court, 2018)
Port of Seattle v. Pollution Control Hearings Board
90 P.3d 659 (Washington Supreme Court, 2004)
Durland v. San Juan County
340 P.3d 191 (Washington Supreme Court, 2014)
Cornelius v. Department of Ecology
344 P.3d 199 (Washington Supreme Court, 2015)
Samson v. City of Bainbridge Island
149 Wash. App. 33 (Court of Appeals of Washington, 2009)
Robertson v. May
153 Wash. App. 57 (Court of Appeals of Washington, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Craig & Kelly Turner v. Gordon Baldwin, Counsel Stack Legal Research, https://law.counselstack.com/opinion/craig-kelly-turner-v-gordon-baldwin-washctapp-2020.