C.R. Pittman Construction Co. v. United States

92 Fed. Cl. 20, 2010 U.S. Claims LEXIS 55, 2010 WL 966644
CourtUnited States Court of Federal Claims
DecidedMarch 10, 2010
DocketNo. 08-196C
StatusPublished
Cited by3 cases

This text of 92 Fed. Cl. 20 (C.R. Pittman Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.R. Pittman Construction Co. v. United States, 92 Fed. Cl. 20, 2010 U.S. Claims LEXIS 55, 2010 WL 966644 (uscfc 2010).

Opinion

[23]*23 OPINION and ORDER

SMITH, Senior Judge.

This dispute arose after flooding from Hurricane Katrina damaged equipment that was necessary for the performance of two contracts between the Plaintiff, C.R. Pittman Construction Co., Inc., and the United States Army Corps of Engineers. Plaintiff alleges that a clause in both contracts, specifically the Damage to Work Clause, entitles Plaintiff to payment for the damaged equipment. The parties filed cross-motions for summary judgment on the issue, and oral argument was held in New Orleans, LA. After careful review and consideration, and for the reasons set forth below, the Court holds that the Defendant is not responsible for the flood-damaged equipment under the contracts.

I. FACTS

On September 20, 2000, the Army Corps of Engineers (the Corps) awarded C.R. Pittman Construction Co. a fixed-price contract for the construction of the Southeast Louisiana Urban Flood Control Project, Dwyer Road Pumping Station in Orleans Parish, LA (Dwyer Contract). (Pl.’s Summ. J. Mot. on Damage to Work Clause 2.) The Dwyer Contract included demolition and removal of the existing pump station, purchase of equipment and materials, and construction of a new pump station. On September 16, 2002, the Corps awarded Plaintiff a second fixed-price contract for the construction of a similar pumping station in Jefferson Parish, LA (Cousins Contract). The Cousins Contract included the purchase of equipment and materials, and construction of a new pump station. Id.

As required under the Contracts, Plaintiff purchased the equipment and materials for the contracts, the Corps made progress payments to the Plaintiff to purchase specified equipment, and Plaintiff stored certain equipment and materials at an agreed upon off-site storage area prior to construction and installation. Id. at 4. The off-site equipment included generators, climber screen cleaners, and pumps. Id. at 3. On August 29, 2005, Hurricane Katrina struck the New Orleans area, flooding the storage sites and damaging the off-site equipment. Both parties agree that the flood damage to the off-site equipment will require total replacement or substantial refurbishment, prior to its installation. Id. at 4.

On March 6 and 7, 2006, the Corps demanded that Plaintiff replace the damaged equipment. On July 11, 2006, the Corps advised the Plaintiff that the Corps had overpaid progress payments because the damaged equipment’s value no longer warranted the progress payments. Id. In response to Defendant’s assertion that Plaintiff had been overpaid, the Plaintiff put the Corps on administrative notice that the damaged equipment fell under the scope of the Damage to Work Clause as “part of the permanent work” and, therefore, the contracts placed responsibility for the damaged equipment on the Corps.

II. PROCEDURAL HISTORY

On April 6, 2007, the Contracting Officer issued two final decisions pertaining to each Contract, ordering Plaintiff to return to the Corps a total of $2,340,109.53 in progress payments, which were earlier paid for the equipment. On May 3, 2007, Plaintiff filed suit against the Corps in the United States District Court for the Eastern District of Louisiana, pursuant to the Federal Tort Claims Act, for flood damage to property seeldng supplemental jurisdiction or pendent jurisdiction for the Corps’ breach of contract. (Pl.’s Summ. J. Mot. on Deferment of Collection 1-2.) On May 22, 2007, Plaintiff formally requested a deferment of collection for the Contracting Officer’s order to return payment, in order to avoid financial hardship. Id. at 3.

The Contracting Officer forwarded Plaintiffs deferment of collection request to the United States Attorney’s Office. After an agreement was reached with the United States Attorney’s Office deferring collection (Deferment of Collection Agreement), the parties submitted a joint order to the District Court. Thereafter, the District Court issued an Order recognizing the Deferment of Collection Agreement. Id. at 4. The Deferment of Collection Agreement states: “It is further ordered that [Plaintiff] is granted a [24]*24deferment of collection of the claim at issue in this case during the pendency of the determination of [Plaintiffs] action against the Corps.” (Def.’s Resp. to PL’s Mot. on Deferment of Collection 5.)

On October 26, 2007, the Contracting Officer informed Plaintiff that “all contract earnings that have been withheld prior to September 2007 will continue to be withheld until the resolution of [the matter in the District Court].” Id. On January 22, 2008, the District Court dismissed the matter without prejudice for jurisdictional reasons. Thereafter, Plaintiff re-filed its action in this Court and requested that the Court recognize the Deferment of Collection Agreement. (Pl.’s Summ. J. Mot. on Deferment of Collection 4.)

After Plaintiff filed this action, the Defendant filed a Motion to Dismiss Certain Claims for Lack of Subject Matter Jurisdiction. Id. at 4-5. After briefing and oral argument, the Court deferred judgment on the Motion to Dismiss and requested that the parties fully brief the core issues relating to the Contract language. Plaintiff then filed two Motions for Summary Judgment with the Court.

First, Plaintiff filed a Motion for Summary Judgment on the Damage to Work Clause, arguing that the Defendant is responsible for the damaged equipment. Plaintiff also filed a second Motion for Summary Judgment on Deferment of Collection, in which Plaintiff argued that the Corps breached the agreement between the parties to defer collection of the amounts specified in the Contracting Officer’s final decisions.

In response, Defendant filed a Cross-Motion for Partial Summary Judgment on the Issue of Responsibility for Damage to Equipment, arguing that the contracts impose responsibility on the Plaintiff for the damaged materials at issue. Defendant also filed a Motion to Strike and Response to Plaintiffs Motion for Summary Judgment on Deferment of Collection. Following full briefing and oral argument, the Court now addresses the cross-motions for Summary Judgment on the issue of who is responsible for the flood-damaged equipment.

III. STANDARD OF REVIEW

Summary judgment is appropriate where there are no genuine disputes over material facts and the moving party is entitled to prevail as a matter of law. RCFC 56(c); see Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Material facts are those facts that “might affect the outcome” of the litigation. Id. at 248, 106 S.Ct. 2505. A genuine dispute concerning a material fact exists when the evidence presented would permit “a reasonable jury [to] return a verdict for the non-moving party.” Id. Thus, in order to prevail upon a motion for summary judgment, a party must demonstrate that no disputed facts exist that would change the outcome of the litigation. Any doubt over a factual issue must be resolved in favor of the non-moving party, to whom the benefit of presumptions and inferences runs. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (citing United States v. Diebold Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer Group, Ltd. v. United States
121 Fed. Cl. 105 (Federal Claims, 2015)
C.R. Pittman Construction Co. v. United States
106 Fed. Cl. 691 (Federal Claims, 2012)
Allied Technology Group, Inc. v. United States
94 Fed. Cl. 16 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
92 Fed. Cl. 20, 2010 U.S. Claims LEXIS 55, 2010 WL 966644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cr-pittman-construction-co-v-united-states-uscfc-2010.