CPC International, Inc. v. Techni-Chem, Inc.

660 F. Supp. 1509, 4 U.C.C. Rep. Serv. 2d (West) 485, 1987 U.S. Dist. LEXIS 4317
CourtDistrict Court, N.D. Illinois
DecidedMay 26, 1987
Docket85 C 1192
StatusPublished
Cited by1 cases

This text of 660 F. Supp. 1509 (CPC International, Inc. v. Techni-Chem, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CPC International, Inc. v. Techni-Chem, Inc., 660 F. Supp. 1509, 4 U.C.C. Rep. Serv. 2d (West) 485, 1987 U.S. Dist. LEXIS 4317 (N.D. Ill. 1987).

Opinion

MEMORANDUM OPINION

PRENTICE H. MARSHALL, District Judge.

Before us are defendant Techni-Chem’s motions for summary judgment on both counts of plaintiff CPC’s amended complaint for breaches of warranty and contract. Although there was some question of our jurisdiction over this action, evidence submitted by the plaintiff establishes the diversity of citizenship of the parties. The parties agree that California substantive law governs.

In July 1983 CPC entered into a written contract to buy from Techni-Chem a system of equipment designed to process and refine fructose. The system consists of two “fractionators” and related equipment. The essence of a fractionator is an enclosed cylinder containing a resin. Corn syrup containing 42% fructose—that is, 42% by weight-of the solids in the syrup is fructose—is caused to flow through the resin. A syrup containing 70 to 90% fructose is recovered from the resin bed. This high purity fructose syrup is mixed with lower purity syrup to produce the end product, 55% fructose, which is used as a sweetener in many foods.

In the sales contract Techni-Chem warranted that the system could produce a certain minimum amount of 55% fructose per day. The section of the sales contract *1511 labeled “Performance” contains the following language:

TECHNI-CHEM, INC. guarantees to repair or replace on an expeditiously priority basis, free of charge, F.O.B. jobsite, any part of the equipment which fails within one (1) year of placing in operation, not to exceed eighteen (18) months from shipment, because of defective design, material, or workmanship with removal and return by purchaser.
This system is further guaranteed to be capable of producing a minimum of 640,000 pounds D.S. of 55% Fructose per day (24 hour basis) provided it is supplied with feed materials of the parameters listed below and operated in accordance with written instructions supplied with the system.

Plaintiff’s Exhibit 1 [Contract] at 16 (emphasis added). This provisional production guarantee is at the heart of the dispute surrounding one of Techni-Chem’s motions for summary judgment.

Techni-Chem delivered the system to CPC’s plant in Stockton, California, and in March 1984 operation of the two fractionators began. Although the system did produce 55% fructose, it was never able to meet the production guarantee, according to CPC. Techni-Chem personnel worked intermittently from March to December to bring the system into compliance, but without success. They left the CPC plant for the last time in December, 1984.

On February 7, 1985, CPC filed this action for breach of express warranty. CPC contends that due to defects in design, material, and workmanship, the system is incapable of meeting the production guarantee. 1

In the meantime, CPC continued to use the system and brought in an outside consultant in an attempt to increase the system’s rate of output. CPC replaced some of the system’s equipment with equipment manufactured by a company other than Techni-Chem and it otherwise modified the system.

On June 12, 1985, CPC’s counsel sent to Techni-Chem’s counsel a letter which purported to revoke CPC’s acceptance of the system and demanded a full refund of the purchase price. Nevertheless, CPC continued, and apparently still continues, to use the system. On June 21, 1985, we granted CPC leave to amend its complaint to add a second claim, in which CPC alleges that Techni-Chem breached the contract by tendering nonconforming goods.

Techni-Chem first challenges Count I— CPC’s breach of warranty claim—arguing that the production guarantee in the contract is expressly conditioned upon CPC abiding by the parameters for feed material listed in the contract and the operating instructions provided with the system. It contends that CPC did not comply with the conditions and therefore the warranty never took effect.

CPC responds that the proviso which follows the performance guarantee in the contract was not a condition precedent, and it adduces evidence to support its position. Techni-Chem counters that we must interpret the contract provisions, including the guarantee and the proviso, based on the plain language of the contract, without the assistance of parol evidence.

Under California law, “the language of a contract is to govern its interpretation, if the language is clear and explicit.” Brandt v. Lockheed Missiles & Space Co., 154 Cal.App.3d 1124, 1129-30, 201 Cal.Rptr. 746, 749 (1984). If an ambiguity is apparent to the reader, extrinsic evidence is admissible to explain the terms of the written instrument. Cordonier v. Central Shop *1512 ping Plaza Associates, 82 Cal.App.3d 991, 1001, 147 Cal.Rptr. 558, 563 (1978).

The guarantee in the written contract contains at least two ambiguities. First, while the guarantee is clearly conditioned on compliance with the terms of the proviso, the contract does not identify the party to ensure compliance. Second, the proviso does not specify when and how often the parameters were to be satisfied. At one extreme, the proviso might mean that Techni-Chem guaranteed the production of 640,-000 pounds of 55% fructose per day only if the system were always provided with feed which met the parameters. In its memorandum Techni-Chem appears to embrace this position, for it adduces evidence to show that the feed did not meet certain parameters a certain percentage of the time. At the other extreme, the proviso might mean that Techni-Chem bore the burden of proving that the system was capable of meeting the production guarantee, and therefore the guarantee took effect even if the system were never provided the proper feed. CPC argues for this interpretation.

Of course we must read the contract as a whole, and if other language in the contract clarifies the ambiguity in the guarantee, we may not look at parol evidence. The only other language in the contract which sheds light on the meaning of the guarantee occurs in two passages from two separate sections labeled “Services.” The first one reads:

The price of this equipment includes technical and engineering installation and startup supervision and service for a period of up to and including forty (40) man days. This service is based on two (2) men, twenty (20) days, and two (2) total trips for all items. This amount of service is normal to provide proper supervision for technical and engineering services during installation and startup of the equipment. Should additional time be required, through no fault of TECHNI-CHEM, INC., the additional time will be charged at our standard per diem of $375.00 per man per eight (8) hour day, plus travel expenses to the jobsite from [Techni-Chem’s principal place of business in] Belvidere, Illinois.
Contract at 15.

This language is also not clear and explicit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
660 F. Supp. 1509, 4 U.C.C. Rep. Serv. 2d (West) 485, 1987 U.S. Dist. LEXIS 4317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cpc-international-inc-v-techni-chem-inc-ilnd-1987.