Coy v. City of Duvall

298 P.3d 134, 174 Wash. App. 272
CourtCourt of Appeals of Washington
DecidedApril 1, 2013
DocketNo. 67737-3-I
StatusPublished
Cited by4 cases

This text of 298 P.3d 134 (Coy v. City of Duvall) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coy v. City of Duvall, 298 P.3d 134, 174 Wash. App. 272 (Wash. Ct. App. 2013).

Opinions

Dwyer, J.

¶1 — Neal Coy appeals from the trial court’s summary judgment dismissal of his claim against the city of Duvall (City). Coy contends that, although the City ultimately approved his preliminary plat application, it acted in an arbitrary and capricious manner during the application process. Pursuant solely to the “final decision” prong of RCW 64.40.020(1), Coy seeks an award of money damages for claimed injuries resulting from the City’s purportedly arbitrary and capricious conduct. Because the statute provides no cause of action in such circumstances, we affirm the trial court’s dismissal of Coy’s claim.

I

¶2 In May 2006, Coy submitted an application to the City for preliminary plat approval of a 32-unit residential subdivision on a 4.58-acre property. In his application, Coy proposed filling the entire on-site wetland. The City’s outside consultant peer reviewer, an ecologist at The Watershed Company, thereafter performed two site visits of the property to determine whether Coy’s proposal was consistent with the City’s code. He determined that Coy’s proposed mitigation plan was deficient and concluded that, because the wetland “serve [d] several functions,” it “appear [ed] that the code would not allow alteration of this wetland.”

¶3 On June 29, 2006, city planner Lara Thomas wrote to Coy’s consultant, David Evans & Associates Inc. (Evans), stating that the City’s wetland peer review process had been completed and that Coy’s wetland fill request did not meet the criteria set forth in the City’s code. On October 13, 2006, after receiving an extension of the period of time allowed for responding to the City’s letter, Evans suggested [275]*275to Doreen Booth, the City’s planning director, that the City’s response to the proposal was arbitrary and capricious and “constitute [d] a denial of rights afforded to others in the recent past.” Evans maintained that the City’s code allowed for the wetland fill proposed by Coy. On December 11,2006, Booth informed Evans by letter that the City’s planning staff could not “approve, or recommend approving, the filling of the wetland under the Sensitive Areas Regulations [Coy’s] project [was] vested in.”

¶4 In January 2007, Evans and the City explored the possibility of processing Coy’s application under the new city code, rather than the code in which the application had vested, and Coy submitted a wetland analysis based upon the new code. Ultimately, however, in May 2007, Coy decided not to pursue permit approval pursuant to the City’s new code; instead, he decided to remain vested in the prior code.

¶5 Then, in October, Coy’s attorney wrote to the City, requesting “the City’s prompt and immediate action to confirm that wetland alteration with off-site mitigation is authorized for this preliminary plat application.” The City’s outside counsel, Amy Pearsall, responded, maintaining that the City was not “prepared at this time to say that” Coy’s proposal was consistent with the City’s code. However, Pearsall proposed a compromise whereby the City would review a proposal consistent with Coy’s interpretation of the code if Coy could submit appropriate documentation demonstrating code compliance.

¶6 Following Coy’s submission of this documentation, the City’s outside consultant determined on July 14, 2008, that Coy had met the requirements for filling the wetland. However, an appropriate site for off-site mitigation could not be located; thus, the City allowed Coy to perform off-site mitigation by contributing to the Snohomish Basin Mitigation Bank. The hearing examiner approved Coy’s preliminary plat application on December 23, 2008.

[276]*276¶7 On January 22, 2009, Coy sued the City pursuant to RCW 64.40.020(1), which provides permit applicants with a cause of action for damages “to obtain relief from acts of an agency which are arbitrary, capricious, unlawful, or exceed lawful authority, or relief from a failure to act within time limits established by law.” Coy alleged that the City had both (1) failed to comply with the statutorily mandated time limit for processing the permit application and (2) acted in an arbitrary and capricious manner during the application process. The City moved for partial summary judgment, seeking dismissal of Coy’s claim for damages resulting from the alleged arbitrary and capricious conduct. On September 9, 2011, the trial court granted the City’s motion, dismissing that claim for relief. Coy thereafter stipulated to the dismissal of his claim asserting that the City had failed to comply with the application processing time limit. Thus, the trial court entered an order dismissing that remaining claim. The trial court thereafter granted the City’s motion for an award of attorney fees pursuant to RCW 64.40.020(2).1

¶8 Coy appeals from the trial court’s dismissal of his claim for relief from the City’s alleged arbitrary and capricious conduct.

II

¶9 Coy contends that he is entitled to delay damages due to the City’s purportedly arbitrary and capricious conduct during the application process, notwithstanding the fact that his permit application was ultimately approved. However, as we have recently held, the “final decision” prong of RCW 64.40.020(1), pursuant to which Coy seeks relief, provides for damages resulting only from an agency’s “final decision” — not from its conduct occurring prior to that decision. Thus, Coy did not state a viable cause of action pursuant to that statutory provision and the trial court did not err by dismissing the claim.

[277]*277¶10 RCW 64.40.020(1) grants to property owners who apply for land use permits a cause of action (1) “for damages to obtain relief from acts of an agency which are arbitrary, capricious, unlawful, or exceed lawful authority” or (2) for damages to obtain “relief from a failure to act within time limits established by law.” Such a cause of action arises only where there is an “act” by the agency, defined by statute as either (1) “a final decision by an agency which places requirements, limitations, or conditions upon the use of real property in excess of those allowed by applicable regulations” or (2) “the failure of an agency to act within time limits established by law in response to a property owner’s application for a permit.” RCW 64.40.010(6). The statute further provides that the recoverable “damages” are the “reasonable expenses and losses ... incurred between the time a cause of action arises and the time a holder of an interest in real property is granted relief as provided in RCW 64.40.020.” RCW 64.40-.010(4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durland v. San Juan County
Washington Supreme Court, 2014
Khushdev & Harbhajan Mangat v. Snohomish County
Court of Appeals of Washington, 2013

Cite This Page — Counsel Stack

Bluebook (online)
298 P.3d 134, 174 Wash. App. 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coy-v-city-of-duvall-washctapp-2013.