County of Westchester v. Welton Becket Associates

102 A.D.2d 34, 478 N.Y.S.2d 305, 1984 N.Y. App. Div. LEXIS 18305
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 29, 1984
StatusPublished
Cited by103 cases

This text of 102 A.D.2d 34 (County of Westchester v. Welton Becket Associates) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Westchester v. Welton Becket Associates, 102 A.D.2d 34, 478 N.Y.S.2d 305, 1984 N.Y. App. Div. LEXIS 18305 (N.Y. Ct. App. 1984).

Opinion

OPINION OF THE COURT

Thompson, J.

In this complex litigation arising out of the construction of the Westchester County Courthouse in White Plains, New York, this court must address three separate issues. Subdivision (b) of section 15-108 of the General Obligations Law provides that a release given in good faith by an injured person to one wrongdoer relieves that wrongdoer from liability to any other person for contribution as provided for in CPLR article 14. We must decide in this case if nonsettling parties seeking contribution under CPLR article 14 from settling parties have sufficiently alleged causes of action for indemnification against the latter so as to allow the nonsettling parties to keep the settling parties in the litigation. We must also decide if allowing a discontinuance with prejudice of the actions among the settling parties and a dismissal of all claims among them will unfairly prejudice or impair the rights of other entities which will remain parties to the litigation. Finally, we must address the question of whether a plaintiff seeking to assert a fraud claim against certain settling parties has sufficiently alleged a cause of action against those parties in light of the absence of a direct relationship between them.

THE PARTIES

In 1968, the County of Westchester entered into a contract with Welton Becket F.A.I.A., to design a new court[37]*37house. This contract was subsequently assigned to and assumed by Welton Becket Associates and Welton Becket & Associates (hereinafter collectively Becket). Becket retained Cosentini Associates and Way man C. Wing as consulting engineers, and Cosentini Associates retained Eitingon & Schlossberg Associates as its consulting engineer.

In 1970, contracts were awarded by the county to three prime contractors. J. R. Stevenson Corp. became the general contractor, Luna Industries, Inc., became the electrical contractor and Martin Mechanical Corporation became the mechanical contractor. J. R. Stevenson Corp. retained Belt Painting Corp., Cafasso Lathing & Plastering Co., Inc., and the joint venture of Giamboi Bros., Inc., and E. M. Fitzsimons & Associates, Inc., as subcontractors. For purposes of these appeals the four distinct groups involved in the litigation shall hereinafter be referred to as follows:

[[Image here]]

THE LITIGATION

On April 29, 1970 the contractors were advised to proceed with the construction, and although they were supposed to complete their work within 975 days, it has been alleged that the courthouse was not ready for full occupancy until April 29, 1975. Problems with regard to defective workmanship also arose. As a result, four separate lawsuits ensued. In three of those actions the contractors sued the county to recover damages, inter alia, for delay caused by the county and for the value of extra work performed. The county counterclaimed against the contractors and their sureties to recover damages based on the [38]*38delay in completing the courthouse and for defective workmanship. In each of those three actions the county also brought a third-party action against certain of the design professionals and others for contribution and indemnification. The design professionals asserted cross claims among themselves. Fourth-party actions were started, and in action No. 2 Stevenson and its sureties initiated fifth and sixth-party actions for contribution and indemnification against, inter alia, the subcontractors and Home Indemnity Company (Home), which had bonded two of the contractors. Certain subcontractors and Home in turn asserted cross claims against certain of the design professionals and others for contribution and indemnification.

In action No. 1, the county sued the design professionals (except Eitingon, which was subsequently impleaded by Cosentini) for negligence and breach of contract based on design defects which had existed. The design professionals asserted cross claims among themselves for contribution and indemnification, and also impleaded certain of the contractors and subcontractors for contribution and indemnification.1

[39]*39THE MOTIONS TO DISCONTINUE AND TO AMEND PLEADINGS

In December, 1982 the county reached a settlement with the design professionals in all the actions. Stipulations of discontinuance and releases were executed. The county and the design professionals then sought an order directing entry of judgment dismissing action No. 1 against the design professionals. They also sought an order directing entry of judgment dismissing all claims, including cross claims, counterclaims, and third and fourth-party claims, which had been brought against the design professionals in actions Nos. 2, 3 and 4. The design professionals also sought summary judgment dismissing the claims brought against them for contribution and indemnification by the fifth and sixth-party defendants (the subcontractors and Home). The design professionals believed they were entitled to remove themselves from the litigation by reason of section 15-108 of the General Obligations Law which provides, in pertinent part:

“§ 15-108. Release or covenant not to sue
“(a) Effect of release of or covenant not to sue tortfeasors. When a release or a covenant not to sue or not to enforce a judgment is given to one of two or more persons liable or claimed to be liable in tort for the same injury, or the same wrongful death, it does not discharge any of the other tortfeasors from liability for the injury or wrongful death unless its terms expressly so provide, but it reduces the claim of the releasor against the other tortfeasors to the extent of any amount stipulated by the release or the covenant, or in the amount of the consideration paid for it, or in the amount of the released tortfeasor’s equitable share of the damages under article fourteen of the civil practice law and rules, whichever is the greatest.
“(b) Release of tortfeasor. A release given in good faith by the injured person to one tortfeasor as provided in subdivision (a) relieves him from liability to any other person for contribution as provided in article fourteen of the civil practice law and rules” (emphasis supplied).

The design professionals reasoned that having settled with the injured party and being immune from contribution [40]*40claims by the contractors and subcontractors pursuant to section 15-108 of the General Obligations Law, they were entitled to remove themselves from the litigation as parties. They further argued that no cause of action for indemnity had been stated against them.

In opposition to the motion, Stevenson, Home, and several subcontractors argued that the nature of their claims against the design professionals was for indemnification as well as contribution, and section 15-108 therefore did not serve as an adequate basis for letting the design professionals out of the action. Reliance was placed, inter alia, upon a response by the county to a Stevenson interrogatory wherein, the county allegedly “admitted” that the design professionals were 100% responsible for the damages sustained by the county and sought to be recovered by it from Stevenson. Stevenson, which had not previously included a claim against the design professionals for indemnity in its pleadings, sought leave to amend its pleadings to allege such a claim.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Uddo v. DeLuca
E.D. New York, 2019
New York Schs. Ins. Reciprocal v. Milburn Sales Co., Inc.
2018 NY Slip Op 6924 (Appellate Division of the Supreme Court of New York, 2018)
Olin Corp. v. Lamorak Ins. Co.
332 F. Supp. 3d 818 (S.D. Illinois, 2018)
Morris v. Home Depot USA
2017 NY Slip Op 5717 (Appellate Division of the Supreme Court of New York, 2017)
QBE Insurance v. Adjo Contracting Corp.
121 A.D.3d 1064 (Appellate Division of the Supreme Court of New York, 2014)
Wells Fargo Bank, N.A. v. National Gasoline, Inc.
577 F. App'x 58 (Second Circuit, 2014)
Lzg Realty, LLC v. H.D.W. 2005 Forest, LLC
87 A.D.3d 727 (Appellate Division of the Supreme Court of New York, 2011)
Rosenbach v. Diversified Group, Inc.
85 A.D.3d 569 (Appellate Division of the Supreme Court of New York, 2011)
Perkins Eastman Architects, P.C. v. Thor Engineers, P.A.
769 F. Supp. 2d 322 (S.D. New York, 2011)
First Keystone Consultants, Inc. v. DDR Construction Services
74 A.D.3d 1135 (Appellate Division of the Supreme Court of New York, 2010)
Manti's Transportation, Inc. v. C.T. Lines, Inc.
68 A.D.3d 937 (Appellate Division of the Supreme Court of New York, 2009)
Expedite Video Conferencing Services, Inc. v. Botello
67 A.D.3d 961 (Appellate Division of the Supreme Court of New York, 2009)
Mathis v. United Homes, LLC
607 F. Supp. 2d 411 (E.D. New York, 2009)
Barron Partners, LP v. LAB123, INC.
593 F. Supp. 2d 667 (S.D. New York, 2009)
Wirsing v. Donzi Marine Inc.
30 A.D.3d 589 (Appellate Division of the Supreme Court of New York, 2006)
Arlington Central School District v. Horizon Roofing & Sheet, Inc.
27 A.D.3d 676 (Appellate Division of the Supreme Court of New York, 2006)
American Transtech Inc. v. U.S. Trust Corp.
933 F. Supp. 1193 (S.D. New York, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
102 A.D.2d 34, 478 N.Y.S.2d 305, 1984 N.Y. App. Div. LEXIS 18305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-westchester-v-welton-becket-associates-nyappdiv-1984.