County of Pennington Ex Rel. Northwest Pipe Fittings, Inc. v. St. Paul Fire & Marine Insurance Co.

508 N.W.2d 376, 1993 S.D. LEXIS 142, 1993 WL 461771
CourtSouth Dakota Supreme Court
DecidedNovember 10, 1993
Docket18095
StatusPublished
Cited by1 cases

This text of 508 N.W.2d 376 (County of Pennington Ex Rel. Northwest Pipe Fittings, Inc. v. St. Paul Fire & Marine Insurance Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Pennington Ex Rel. Northwest Pipe Fittings, Inc. v. St. Paul Fire & Marine Insurance Co., 508 N.W.2d 376, 1993 S.D. LEXIS 142, 1993 WL 461771 (S.D. 1993).

Opinions

HENDERSON, Justice.

A group of suppliers of construction materials appeals a circuit court’s summary judgment order dismissing their action to recover on a payment bond. We affirm.

FACTS

Corner Construction Company (hereinafter “Corner Construction”) was selected as the prime contractor for the Pennington County Jail Project (hereinafter “jail project”). Corner Construction entered into a plumbing subcontract with William Smith, d/b/a The Plumbers, (hereinafter “The Plumbers”). Apollo Piping Supply Company, Northwest Pipe Fittings, Inc., and Building Sprinkler Co. Inc. (hereinafter collectively referred to as “the materialmen”) supplied materials to The Plumbers for the jail project.

When Corner Construction was chosen to complete the jail project it was required (under SDCL 5-21-1) to obtain a payment and [377]*377performance bond. Corner Construction obtained this bond from St. Paul Fire and Marine Insurance Company (hereinafter “St. Paul”)- The payment portion of the bond is to ensure the contractor promptly pays “all persons supplying him with labor or material. ..SDCL 5-21-1. The bond St. Paul provided was broader than required by the statute in that it provided protection to all “claimants,” including anyone “having a direct contract ... with a subcontractor.” However, the terms of the bond also specified that:

No suit or action shall be commenced hereunder by any claimant: (a) Unless claimant, other than one having a direct contract with the Principal, shall have given ivritten notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished,.... (emphasis added).

The jail project was completed in late 1990 and final settlement between the County Building Authority and Corner Construction occurred on approximately December 14 or 18, 1990. In November 1991, the material-men filed suit alleging they had not been paid for materials they supplied for the jail project. The materialmen sought payment from St. Paul as the surety for the performance and payment bond.

In March 1992, the materialmen filed a motion for summary judgment. St. Paul resisted the motion for summary judgment. All parties agreed to treat St. Paul’s opposition as a cross-motion for summary judgment. In support of its cross-motion for summary judgment, St. Paul alleged that the materialmen had not complied with the notice provisions of the bond. None of the materialmen came forward with any evidence establishing they provided such notice, nor did they deny they had failed to provide such notice. The circuit court concluded that there was no genuine issue of material fact that notice had not been given. The circuit court entered summary judgment in favor of St. Paul holding that the materialmen had not given timely notice to St. Paul as required by the terms of the bond. The mate-rialmen appeal.

ISSUE

Is a ninety-day notice requirement in St. Paul’s bond inconsistent with the one year limitation period established in SDCL 5-21-6?

DECISION

The materialmen note that SDCL 5-21-6 establishes a one year statute of limitations for claims against a surety on a public project. Under the issue, as framed above, this is a case of first impression in South Dakota.

Chapter 5-21 of the South Dakota Codified Laws specifies the general requirements of performance bonds for public improvement contracts but does not specify the actual terms of the bonds. Under SDCL 5-21-5, unpaid materialmen have the right to intervene as parties in any action instituted by a public corporation against the surety. SDCL 5-21-6 specifies the limitation period for ma-terialmen to seek recovery under the bond and provides, in pertinent part:

If no suit should be brought by the public corporation within six months from the completion and final settlement of such contract, the person supplying the contractor with labor or material shall, upon application therefor and furnishing affidavit to the corporation that labor or material for the prosecution of such work has been supplied by him and payment for the same has not been made, be furnished with a certified copy of such contract and surety, upon which he shall have a right of action and shall be authorized to bring suit in the name of the public corporation in the circuit court for the county in which such contract was to be performed and not elsewhere, for his use and benefit, against such contractor and his surety, and to prosecute the same to final judgment; provided, that where suit is instituted by any such person on the surety of the contractor, it shall not be commenced until six months after the complete performance of such contract and [378]*378final settlement thereof but must be commenced within one year thereafter; ... (emphasis added).

SDCL 5-21-6.

The materialmen contend the 90-day notice requirement in St. Paul’s bond is in conflict with the one year statute of limitations set forth in SDCL 5-21-6. They rely on this Court’s holding that “the law should set limitation periods, not private contracts.” Sheehan v. Morris Inv., 410 N.W.2d 569 (S.D. 1987).

St. Paul contends the 90-day notice provision is simply a notice provision. Perforce, they reason it does not conflict with the limitations period set forth in SDCL 5-21-6. St. Paul urges this Court to adopt the reasoning applied in Bunker v. United States Fidelity & Guaranty Co., 72 F.2d 899 (10th Cir.1934), which stated:

In the absence of statutory prohibition, it is doubtful if customary and reasonable provisions as to notice, proofs of loss, cancellation, and the like, would alter or impair the obligation imposed by statute.

Id. at 901. St. Paul further contends there is no statute which prohibits a surety from imposing notice requirements in its bonds.

Both litigants are correct in their recitation of the law. This Court’s expressed rule is that limitations periods should be set by law rather than by private contract. Shee-han, 410 N.W.2d at 570.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
508 N.W.2d 376, 1993 S.D. LEXIS 142, 1993 WL 461771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-pennington-ex-rel-northwest-pipe-fittings-inc-v-st-paul-fire-sd-1993.