County of Blue Earth v. Nat. Surety Co.

205 N.W. 277, 164 Minn. 390
CourtSupreme Court of Minnesota
DecidedOctober 9, 1925
DocketNo. 24,614.
StatusPublished
Cited by2 cases

This text of 205 N.W. 277 (County of Blue Earth v. Nat. Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Blue Earth v. Nat. Surety Co., 205 N.W. 277, 164 Minn. 390 (Mich. 1925).

Opinions

1 Reported in 205 N.W. 277. Judicial Ditch No. 7 in Watonwan and Blue Earth counties was established by the order of the district court in April, 1913. The two counties entered into a construction contract, under which work commenced in May, 1914, and continued intermittently until the contractors ceased work in 1909. Thereupon appellant, as surety on their bond, was called on to complete the work, employed one of the contractors for that purpose, and drew upon the retained percentage of the contract price to pay him.

The drainage was unsatisfactory and, in July, 1922, appellant was notified that the work had not been done properly and that bids would be received for the completion thereof. The lowest bid exceeded the amount of the benefits as determined by the viewers, and all bids wre rejected. In March, 1923, this action was brought on the bond to recover damages for breach of contract. Respondents recovered a verdict of $21,531.83, and this appeal is from an order denying a motion for a new trial. *Page 392

1. Many assignments of error are based on rulings excluding evidence which appellant attempted to introduce in the examination of L.E. Lambert, the civil engineer in charge of construction from May, 1914, to October, 1918.

The original survey was the work of W.F. Brooks, an engineer appointed by the court when the drainage proceeding was commenced. His plans and specifications were made part of the contract and the contractors agreed to do the work in accordance therewith.

Respondents' principal witness was an engineer named Meyer, who was appointed by the court, after the work ceased, to inspect the work and report his findings. He made a comprehensive report of the defects he discovered and testified at great length concerning the particulars in which the work failed to conform to the plans and specifications. Lambert was called to rebut the conclusions which would necessarily be drawn from Meyer's testimony. While the work was in progress, Lambert had Brooks' field notes, plans, specifications and profiles, and they were before him when he testified. It appeared that he had laid out the work on the ground by taking levels and setting grade stakes; that much of the construction work was done under his direct supervision and the remainder under the supervision of inspectors he employed; that, as the work progressed, he inspected the tile as it was laid and, from time to time, issued certificates to the contractors or their subcontractors; that he had kept a record of his survey and had deposited the book in the office of the clerk of court, but at the time of the trial the book could not be found.

Lambert was repeatedly asked whether the tile was laid at the elevation shown by Brooks' profiles, whether the elevations shown by the grade stakes he (Lambert) set were the same as those shown by the profiles, and whether the pipe was laid at the depth marked on the grade stakes and prescribed by the original plans and profiles. To all such questions objection was interposed on the ground that they called for opinions of the witness, and that, until his note book was produced, there was no foundation for a conclusion *Page 393 that the tile had or had not been laid at the depth or grade Brooks had specified. We cannot agree that these questions called for the conclusion of the witness. He had personal knowledge of the manner in which the tile was laid. The absence of the note book might affect the weight of the testimony, but not its admissibility. Kies v. Warrick, 149 Minn. 177, 182 N.W. 998. To deprive appellant of the benefit of Lambert's testimony on a vital issue in the case was prejudicial error.

Lambert knew whether the contractors had done their work in accordance with Brooks' plans and specifications. The work was done under his supervision. It was his duty to see that it was done in the manner prescribed by the contract, and the questions called for statements of fact. The modern tendency is all in the direction of liberality in the admission of evidence. Dun. Dig. § 3312. As an illustration, see Phillips v. Menomonie H.P.B. Co.109 Minn. 55, 122 N.W. 874, a case where the performance of a contract was in issue and it was held that the trial court, in its discretion, might allow a party to testify that he had performed the contract, if the answer amounted to no more than a mere shorthand rendering of the facts.

Certain questions of law, fully argued in the briefs, will come up again when the case is retried. It seems desirable that we should state our views as to some of these questions.

2. Appellant attempted to prove that the contractors dug the ditch to a depth and laid the tile at the level indicated by the grade stakes set by Lambert. The court ruled that such evidence was inadmissible, unless it was shown that the grade shown by Lambert's stakes was the same as the grade shown by Brooks' profiles and required by the contract. The ruling was correct. The provisions of the contract relative to directions given by the engineer did not relieve the contractors from their obligation to do the work in accordance with the plans and specifications.

Brooks was the engineer appointed by the court to make the survey and prepare the plans and specifications. These were the plans to which the court gave its approval. They were the bases *Page 394 for the assessment of benefits. The contractors' bid was based upon them. The contract obligated the contractors to dig the ditch and lay the tile in accordance with their requirements. The engineer had no authority to modify them during the progress of the work without the consent of the court. G.S. 1913, §§ 5526, 5555.

Defendant takes the position that, if it could show that the tile was laid at the depth indicated by Lambert's grade stakes, it need not go further and show that this was the depth required by Brooks' specifications and profiles. The court is of a contrary opinion. Neither Brooks nor Lambert had any authority except such as was conferred on them by the statute. Lambert had certain duties to perform while supervising the work of the contractors. His duties were defined by the statute. In discharging them he represented the two counties. Seastrand v. D.A. Foley Co. 135 Minn. 5, 159 N.W. 1072. His authority was derived from the law. He had no authority to direct the contractors to do the work in any other manner than the law required. By statute, as well as by the express terms of the contract, the contractors were bound to do the work in the manner specified in Brooks' survey and report. When they notified the engineer that they had completed the job, it became his duty to inspect the work and, if he found that they had completed it according to the contract, plans and specifications, it was his duty to report that fact to the court and give the contractors a certificate to that effect. G.S. 1923, § 6694.

The limited authority of the engineer is shown by the last proviso of the section, which declares that none of the certificates issued by the engineer under the drainage law shall constitute prima facie or other evidence of the truth of the contents thereof, or of the fulfilment of the contract. In referring to this provision, it was said in State v. Clarke,112 Minn. 516, 128 N.W. 1008

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kalman v. County of Grant
209 N.W. 638 (Supreme Court of Minnesota, 1926)
Dragon Motor Car Co. Ltd. v. Storrow
205 N.W. 694 (Supreme Court of Minnesota, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
205 N.W. 277, 164 Minn. 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-blue-earth-v-nat-surety-co-minn-1925.