County Council v. Lee

148 A.2d 568, 219 Md. 209, 1959 Md. LEXIS 339
CourtCourt of Appeals of Maryland
DecidedFebruary 19, 1959
Docket[No. 122, September Term, 1958.]
StatusPublished
Cited by14 cases

This text of 148 A.2d 568 (County Council v. Lee) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County Council v. Lee, 148 A.2d 568, 219 Md. 209, 1959 Md. LEXIS 339 (Md. 1959).

Opinion

Hornpy, J.,

delivered the opinion of the Court.

The Circuit Court for Montgomery County, by its decree, declared that the clause—requiring the permittee to obtain the necessary easement for the construction, operation and maintenance of a storm drainage outlet—set forth in the paving permit issued by Montgomery County (the County) to T. Girard Lee (Lee or the permittee) was invalid, and ordered that when the permittee had complied with all other terms and conditions of the permit, he and the surety on his performance bond should be released and discharged from all obligations under the permit and bond. The County appealed.

Lee, who was a developer and builder of homes in Montgomery County, undertook the development in 1954 of the subdivision known as “Randolph Farms” in the area of the Washington Suburban Sanitary District. In the course of the development he obtained a permit for and graded Galena Road—along which he had constructed about twenty-five homes—to intersect, at its north end, with the county maintained Randolph Road.

Later, in the summer of 1955, after the grading had been accomplished in accordance with the requirements of the County and the Washington Suburban Sanitary Commission (the WSSC), Lee applied for a permit to pave Galena Road and submitted therewith his proposed plans, including a storm drainage plan prepared by his engineers. The drainage plan provided for surface water to flow through a culvert under Randolph Road into an outlet—described as “Outlet W-l”—at the north end of the culvert, and then into a drainage ditch, to be dug across the land of another, until it met-an existing ditch on the land north of Randolph Road. The drainage plan was approved by the WSSC as required by law [County Code (1955) §§ 74-52 (b), 74-95, 93-14], prior to its submission to the Public Works Department (the PWD) of the County. The County prematurely issued the paving permit (No. 4-599) on August 24, 1955, because the permittee was under “pressure” to get the paving under way. As a result the permittee was allowed to begin paving *212 before he had obtained the drainage ditch easement he had agreed to procure as one of the conditions on which the permit was predicated. The permit specifically required, among other things, that the permittee should “obtain [the] necessary easement for [the] construction, operation, and maintenance of Outlet W-l.” But he never complied with the requirement.

The efforts of the permittee to comply with the requirement by purchasing the easement, as was contemplated, proved fruitless. The owner of the land would not sell the permittee an easement, and he stopped trying. In the negotiations which followed between the PWD and the permittee, the department finally offered to condemn the necessary easement if the permittee would furnish an additional bond to cover the estimated condemnation damages and costs, but he declined to accept the offer.

In the several discussions with officials of the County with regard to the permit, both before and after it had been issued, the permittee interposed no objection to the requirement that he should procure the easement until most of the other required work had been completed. But, in his testimony at the trial, he indicated that he had always intended to do only what was “within his ability” and no more.

Most- of the required work was completed, but when the County notified the permittee that he was in default with respect to what remained, including the procurement of the easement, he filed a bill for an injunction to forestall forfeiture of the performance bond, and for a decree declaring the rights, status and legal relations of the parties to the permit and, particularly, as to the validity and binding effect of the requirement that the permittee should obtain the drainage ditch easement.

The demurrer to the original bill was sustained with leave to amend. The amended bill sought only a declaratory decree, claiming that the requirement was illegal and not binding because it was an abuse of power by the County; because it “extorted” private funds to provide for public works without just compensation; and because the requirement was too vague and indefinite to be valid and enforceable. The County, *213 demurring to the amended bill, contended there was a want of necessary parties, that the permittee was not entitled to any relief in equity and that the amended bill substantially changed the character of the original bill. When the demurrer to the amended bill was overruled, the County answered and the action came on for trial on its merits. Before the trial began the permittee sought and was granted leave to amend further by appending two additional prayers for relief to the amended bill—one to the effect that, if the disputed requirement be found valid and binding, the court should also determine the damages due the County, and the other to the effect that, if the requirement be found invalid, the court should require the County to release the performance bond upon satisfactory completion of the work remaining to be done other than the procurement of the drainage ditch easement. Although, at first, the County objected to the amendment, it finally conceded that the additional prayers would not prejudice its case, and proceeded to trial on the issues raised by the amended bill and its previous answer thereto.

On this appeal, the County has renewed its contention, pursuant to Maryland Rule 373 c, that its demurrer to the amended bill should have been sustained, primarily because it contends other persons should have been made parties. But, as we see it, it is not essential to consider any of the questions raised by the demurrer. Since the rights of the W. S. S. C. and the surety on the performance bond are not adjudicated in this proceeding and will not be affected or prejudiced by the decree to be entered in conformity with this opinion, we think the failure to require the joinder of those parties was not reversible error. See Code (1957), Art. 31A, § 11. Cf. Reddick v. State, 213 Md. 18, 130 A. 2d 762 (1957). Moreover, we think the County, when it acceded to the appendage of the additional prayers, in effect waived the question of jurisdiction and abandoned its contention that the amended bill altered the character of the original bill. See Moore v. McAllister, 216 Md. 497, 141 A. 2d 176 (1958).

On the merits, the chancellor was of the opinion that the requirement was invalid and unenforceable against the per *214 mittee because the County, by issuing the permit before the necessary “right of way” had been acquired or dedicated to public, use, undertook to transfer its responsibility to the permittee by requiring him to obtain the necessary easement for the drainage ditch over private property for a public use. We do not agree.

As may be seen, the question to be resolved requires an examination of the pertinent terms and provisions of the law regulating the construction and maintenance of roads and streets in Montgomery County, commonly known as the “Road Code,” and the relevant terms and provisions of the performance bond. The County divides its streets and roads into two categories depending on “who” is responsible for the original cost of construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
148 A.2d 568, 219 Md. 209, 1959 Md. LEXIS 339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-council-v-lee-md-1959.