Coughlin Construction Co. v. Nu-Tec Industries, Inc.

2008 ND 163, 755 N.W.2d 867, 2008 N.D. LEXIS 166, 2008 WL 4069492
CourtNorth Dakota Supreme Court
DecidedSeptember 4, 2008
Docket20070311
StatusPublished
Cited by55 cases

This text of 2008 ND 163 (Coughlin Construction Co. v. Nu-Tec Industries, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coughlin Construction Co. v. Nu-Tec Industries, Inc., 2008 ND 163, 755 N.W.2d 867, 2008 N.D. LEXIS 166, 2008 WL 4069492 (N.D. 2008).

Opinions

SANDSTROM, Justice.

[¶ 1] Nu-Tec Industries, Inc. (“Nu-Tec”), Ronald J. Balzer, Rudy Balzer, and James Balzer appeal from a judgment and amended judgment awarding Coughlin Construction Company, Inc. (“Coughlin”), $151,122 in damages, costs, and fees for breach of a construction contract. They also appeal from an order denying their motion for amended findings. We conclude the district court’s award of damages [870]*870is not clearly erroneous and the court did not err in piercing the corporate veil of Nu-Tec. We affirm.

I

[¶ 2] On May 6, 2002, Coughlin, as the general contractor, entered into a contract •with the City of Minot to construct the 16th Street Railroad Underpass Project for approximately $3.1 million. Coughlin accepted a bid from Nu-Tec, as a subcontractor, to install two 600-foot replacement water lines on the project for approximately $99,000. The plans and specifications authorized the use of directional drilling to install the new water lines with 20-inch and 24-inch high-density polyethylene (“HDPE”) pipe. Although Nu-Tec was to install the pipe, Coughlin was responsible for purchasing the pipe and fusing the sections together under the parties’ standard subcontract agreement. Coughlin supplied the HDPE pipe in 50-foot sections, which it fused into single 600-foot pieces before Nu-Tec began installation.

[¶ 3] Nu-Tec began installing the water lines on June 24, 2002. Nu-Tec successfully installed the 20-inch HDPE water line pipe but encountered problems while attempting to install the 24-inch pipe. On June 29, 2002, the 24-inch pipe became stuck at approximately one-half of the way through the 600-foot pull. During the following month, Nu-Tec unsuccessfully attempted to install or extract the 24-inch pipe from the ground. Coughlin, exercising its rights under the subcontract agreement, notified Nu-Tec that it was terminating its employment and that Nu-Tec would be obligated to pay the costs Coughlin incurred for installing the remainder of the 24-inch pipe. Coughlin completed installation of the 24-inch water line with its own employees and equipment using open trench construction techniques and ductile iron pipe with fusion couplers. Coughlin used the 24-inch HDPE pipe pulled in by Nu-Tec and installed an additional 300 feet of ductile iron pipe.

[¶ 4] In July 2004, Coughlin sued Nu-Tec for damages on the basis of theories of breach of contract, guarantee, and negligence. Coughlin sought compensation for the cost of installing the remainder of the 24-inch water line, for the work it performed and equipment it provided, and for acceleration costs incurred. Coughlin also sought to pierce the corporate veil of Nu-Tec and hold its shareholders personally liable.

[¶ 5] During the bench trial, Nu-Tec argued the 24-inch pipe became stuck because of unanticipated soil conditions. Coughlin presented expert testimony that the pipe became stuck because Nu-Tec failed to add water ballast to the pipe and tried to pull it through the ground with under-powered machinery. The district court found the opinion of Coughlin’s expert witness was more persuasive and ruled Nu-Tec had breached its subcontract with Coughlin by failing to perform. The court awarded Coughlin $119,675.85 in damages and $31,446.15 in costs and fees, for a total judgment of $151,122 plus interest. The court also ruled it was appropriate to pierce the corporate veil of Nu-Tec, a closely-held family corporation consisting of the Balzers, and held the Balzers jointly liable for the judgment. The court denied Nu-Tec’s motion to amend the findings and judgment.

[¶ 6] The district court had jurisdiction under N.D. Const, art. VI, § 8, and N.D.C.C. § 27-05-06. The appeal of Nu-Tec and the Balzers is timely under N.D.R.App.P. 4(a). This Court has jurisdiction under N.D. Const, art. VI, §§ 2 and 6, and N.D.C.C. § 28-27-01.

II

[¶ 7] Nu-Tec and the Balzers argue the district court erred as a matter of law [871]*871in awarding damages, because it impermis-sibly granted Coughlin a double recovery for completing the installation of the 24-inch pipe.

[¶ 8] Nu-Tec and the Balzers argue Coughlin was paid twice for installing the 300 feet of pipe because it received payment from the City of Minot for completing that part of the work, it was awarded damages for the full amount of its extra expenses for completing the installation, and it kept the amount it would have otherwise paid Nu-Tec for the work. Relying on N.D.C.C. § 32-03-36, which states in part, “no person can recover a greater amount in damages for the breach of an obligation than the person could have gained by the full performance thereof,” they contend Coughlin impermissibly received $27,000 more than it would have received through Nu-Tec’s full performance of the contract.

[¶ 9] Nu-Tec and the Balzers acknowledge this issue was not expressly raised at any point in the district court proceedings, but contend “the damages ‘battle’ was framed by both parties in very general terms” and the court had a duty to correctly apply the law on the proper measure of damages to the facts and arrive at a correct damages calculation. This argument is not persuasive, because it conflicts with several well-established principles of appellate review. First, their argument implies that district court judges are obligated to arrive at the correct amount of damages regardless of input and objections by the parties. However, judges “are not ferrets” who “engage in unassisted searches of the record for evidence to support a litigant’s position.” State v. Noack, 2007 ND 82, ¶ 8, 732 N.W.2d 389. Moreover, we do not review a damages issue de novo, but apply the clearly erroneous standard of review. E.g., Hanson v. Boeder, 2007 ND 20, ¶ 7, 727 N.W.2d 280. Second, the appellants’ attorney on appeal is not the same attorney who represented them at trial, and new counsel on appeal is limited to the same issues that prior counsel would have been able to raise. E.g., State v. Wiest, 2001 ND 150, ¶ 6 n. 2, 632 N.W.2d 812; Klem v. Greenwood, 450 N.W.2d 738, 743 (N.D.1990). Third, this Court does not address new issues raised for the first time on appeal. E.g., Knife River Coal Mining Co. v. Neuberger, 466 N.W.2d 606, 608 (N.D.1991). For example, in Robert v. Aircraft Inv. Co., Inc., 1998 ND 62, ¶ 14, 575 N.W.2d 672, the appellant claimed the amount for cost of repair damages in a tort case should have been reduced by the salvage value of an engine, propeller, and core. This Court declined to address the issue because a “reduction for the value of salvage was not sought at trial,” and “ ‘[w]e do not consider questions that were not presented to the trial court and that are raised for the first time on appeal.’ ” Id. (quoting Messer v. Bender, 1997 ND 103, ¶ 10, 564 N.W.2d 291). The situation in this case is no different. As with other issues that arise during a trial, objections to damages must be raised in the district court to preserve those issues for appellate review.

[¶ 10] We reject the appellants’ attempt to raise this issue for the first time on appeal and decline to address it.

Ill

[¶ 11] Nu-Tec and the Balzers argue the district court erroneously failed to offset the damages by $13,000 for the value of the unused 24-inch pipe. They claim Coughlin, under its duty to mitigate damages, should have sold the unused pipe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

UMB Bank N.A. v. Eagle Crest Apartments
2023 ND 4 (North Dakota Supreme Court, 2023)
West Dakota Oil v. Kathrein Trucking
2022 ND 111 (North Dakota Supreme Court, 2022)
Taszarek v. Lakeview Excavating
2021 ND 237 (North Dakota Supreme Court, 2021)
Three Aces Properties v. United Rentals
2020 ND 258 (North Dakota Supreme Court, 2020)
Voigt v. Nelson
2020 ND 113 (North Dakota Supreme Court, 2020)
Taszarek v. Lakeview Excavating, Inc.
2019 ND 168 (North Dakota Supreme Court, 2019)
Marchan v. John Miller Farms, Inc.
352 F. Supp. 3d 938 (U.S. District Court, 2018)
Armstrong v. Clarkson College
297 Neb. 595 (Nebraska Supreme Court, 2017)
Monster Heavy Haulers, LLC v. Goliath Energy Services, LLC
2016 ND 176 (North Dakota Supreme Court, 2016)
Estate of Amundson
2015 ND 253 (North Dakota Supreme Court, 2015)
Macquarie Bank Limited v. Bradley D. Knickel
793 F.3d 926 (Eighth Circuit, 2015)
Peterbilt of Fargo, Inc. v. Red River Trucking, LLC
2015 ND 140 (North Dakota Supreme Court, 2015)
Solid Comfort, Inc. v. Hatchett Hospitality Inc.
2013 ND 152 (North Dakota Supreme Court, 2013)
Interest of N.C.M., D.C.M., and J.J.M.
2013 ND 132 (North Dakota Supreme Court, 2013)
Watts v. Magic 2 x 52 Management, Inc.
2012 ND 99 (North Dakota Supreme Court, 2012)
Dorothy J. Pierce Family Mineral Trust v. Jorgenson
2012 ND 100 (North Dakota Supreme Court, 2012)
Everkrisp Vegetables Inc. v. Tobiason Potato Co.
870 F. Supp. 2d 745 (D. North Dakota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2008 ND 163, 755 N.W.2d 867, 2008 N.D. LEXIS 166, 2008 WL 4069492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coughlin-construction-co-v-nu-tec-industries-inc-nd-2008.