Cougar Bay Co., Inc. v. Bristol

597 P.2d 1070, 100 Idaho 380, 1979 Ida. LEXIS 456
CourtIdaho Supreme Court
DecidedJuly 23, 1979
Docket12452
StatusPublished
Cited by39 cases

This text of 597 P.2d 1070 (Cougar Bay Co., Inc. v. Bristol) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cougar Bay Co., Inc. v. Bristol, 597 P.2d 1070, 100 Idaho 380, 1979 Ida. LEXIS 456 (Idaho 1979).

Opinion

DONALDSON, Chief Justice.

Defendants-appellants, Jimmie and Donald Bristol, d/b/a Bristol Brothers, a partnership, as well as Pappy’s Pizza, Inc., bring this appeal from an adverse decision on the merits in district court in favor of the plaintiff-respondent, Cougar Bay Company, Inc. The Bristols appeal results from an action involving the foreclosure of a materialman’s lien as a result of a contract to construct a Pappy’s Pizza restaurant in Kellogg, Idaho. 1

In the fall of 1973, the Bristols engaged an architect to prepare preliminary drawings for a pizza restaurant to be located upon leased premises in Kellogg. From its inception the restaurant was to be an essentially prefabricated modular structure which would serve as a prototype model for other Pappy’s Pizzas to be constructed in other areas in the future. The architect drafted outline specifications for the project in October 1973.

In January 1974, Loren Murphy, vice president of Cougar Bay, began meeting with the Bristols to discuss preliminary plans for the construction of the prototype prefabricated Pappy’s Pizza in Kellogg. These meetings together with the architect’s preliminary drawing led to Cougar Bay’s submission of a written “estimate” on January 30, 1974 estimating the price for construction of the project to be $70,000. Then, on April 30, 1974, Cougar Bay submitted a “summarized projected cost breakdown” for the Kellogg restaurant estimating the cost of construction to be $82,044, including a $7,000 contractor’s fee.

By a written agreement dated May 13, 1974, Cougar Bay and the Bristols contracted for the construction of the pizza parlor on the basis of Cougar Bay’s April 30 projected cost breakdown and their estimate of the total cost of construction ($82,-044). Under the terms of that contract Cougar Bay agreed to commence construction of the project immediately. In return, the Bristols agreed to advance Cougar Bay $10,000 and to secure financing within 90 days of the contract date. If the Bristols obtained financing, the work would proceed in accordance with the plans of the architect; although at the time the parties entered into this agreement, there were no written specifications in existence. Cougar Bay also guaranteed the labor costs would not exceed $21,528 by more than ten percent. Cougar Bay began construction shortly after May 13.

During the initial stages of construction the Bristols sought to secure financing for the project in the amount of $81,304 *382 through the Small Business Administration. (SBA) The testimony elicited at trial indicates that the SBA, as a precondition to approving the Bristols’ loan, required them to execute a standard American Institute of Architects contract. (AIA contract) Mr. Murphy of Cougar Bay supplied the Bristols with this form contract which provided among other things that the basis of the payment would be the cost of the work plus a fee. Pursuant to the AIA contract the parties agreed, by virtue of the deletion of section 5.2, that there would be no guaranteed maximum cost on the project; rather, they agreed to an “estimated maximum cost” of $82,044 as per the April 30 projected cost breakdown. The AIA contract also provided for the $7,000 contractor’s fee as well as provision for the charge (cost of additional work plus 10%) for any changes in the work during its progress.

The date of the parties’ execution of the AIA contract was completely in dispute at trial. Cougar Bay contended that the parties signed it in August on or about the time that it took out a cost bond on the project as required by the SBA. The Bristols argued that they executed it on the date indicated on the first page of the AIA contract — April 30, 1974. The trial court found that the preponderance of the evidence indicated that the parties executed the AIA contract in August, 1974.

By November 1974, Cougar Bay had substantially completed the Kellogg Pizza project. Upon completion Cougar Bay presented a final billing, with cost itemization, to the Bristols. The total cost of the work including the cost for work changes and the contractor’s fee was $115,348.68. The Bristols acknowledged an increase of $16,215.67 representingf charges for work changes, and have paid Cougar Bay a total of $98,259.67. However they contended at trial and now contend on appeal that their obligation should not exceed the $98,259.67 already paid which is the sum of the $82,044 maximum estimated cost and the charge for extra work done.

Cougar Bay then filed a materialman’s lien for the balance which the Bristols refused to pay in February 1975 and filed its complaint to foreclose the lien on May 30, 1975. The Bristols answered with a general denial, setting forth the affirmative defense of payment for all services rendered. The case was set for trial without a jury on March 1, 1976. Prior to trial, counsel for the Bristols withdrew from the case. The newly retained counsel attempted to file an “amended answer” two days before the trial and 211 days after the first answer had been filed. In essence the “amended answer” set forth counterclaims against Cougar Bay in the total amount of $600,798.91.

The trial judge denied the motion to amend and the action went to trial. At the conclusion of the trial and upon submission of briefs, the court issued a memorandum decision to the effect that the Bristols were indebted to Cougar Bay in the amount of $14,489.01 and that the lien should be foreclosed in that amount. The court signed findings of fact which were in conformity with the memorandum decision. The Bristols filed a motion for a new trial which the trial judge denied. The Bristols then brought this appeal. We affirm.

The Bristols in their appellate brief present ten issues on appeal. However it is our opinion that to dispose of this appeal requires only consideration and discussion of two areas: first, whether the trial court erred in denying the Bristols’ motion to amend their answer and second, whether there is substantial and competent evidence in the record to support the trial court’s findings of fact and conclusions of law.

With regard to the first issue we note that the decision of whether to permit amendment of a pleading is vested in the sound discretion of the trial court. The Idaho First National Bank v. Wells, Idaho, 596 P.2d 429 (1979); Smith v. City of Preston, 99 Idaho 618, 586 P.2d 1062 (1978); Jones v. Watson, 98 Idaho 606, 570 P.2d 284 (1977). This is especially true in the situation where a pleader fails to set up a counterclaim through mistake, inadvertence or excusable neglect. In such a situation the trial court' may, if justice so requires, give the pleader leave to set up the counterclaim by amendment. I.R.C.P. 13(f).

*383 In the instant case, newly retained counsel for the Bristols attempted to set up counterclaims against Cougar Bay in excess of $600,000 by amendment to the Bristols’ answer two days prior to trial. In denying this motion the trial judge stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoffman v. United Silver Mines, Inc.
775 P.2d 132 (Idaho Court of Appeals, 1989)
Hofmeister v. Bauer
719 P.2d 1220 (Idaho Court of Appeals, 1986)
Stout v. Westover
681 P.2d 1008 (Idaho Supreme Court, 1984)
Latham v. Garner
673 P.2d 1048 (Idaho Supreme Court, 1983)
Ada County Highway District ex rel. Fairbanks v. Acarrequi
673 P.2d 1067 (Idaho Supreme Court, 1983)
ADA COUNTY HIGH. DIST. v. Acarrequi
673 P.2d 1067 (Idaho Supreme Court, 1983)
Scott v. Castle
662 P.2d 1163 (Idaho Court of Appeals, 1983)
Burnham v. Bray
661 P.2d 335 (Idaho Court of Appeals, 1983)
Chadderdon v. King
659 P.2d 160 (Idaho Court of Appeals, 1983)
Lester v. Lester
658 P.2d 915 (Idaho Supreme Court, 1983)
Gilbert v. Nampa School District No. 131
657 P.2d 1 (Idaho Supreme Court, 1983)
W. F. Construction Co. v. Kalik
652 P.2d 661 (Idaho Court of Appeals, 1982)
Riverside Development Co. v. Ritchie
650 P.2d 657 (Idaho Supreme Court, 1982)
D. R. Curtis Co. v. Mason
649 P.2d 1232 (Idaho Court of Appeals, 1982)
Huff v. Uhl
647 P.2d 730 (Idaho Supreme Court, 1982)
Hoppe v. McDonald
644 P.2d 355 (Idaho Supreme Court, 1982)
Bastian v. Albertson's, Inc.
643 P.2d 1079 (Idaho Court of Appeals, 1982)
Eliopulos v. Kondo Farms, Inc.
643 P.2d 1085 (Idaho Court of Appeals, 1982)
J.E.T. Development v. Dorsey Construction Co.
642 P.2d 954 (Idaho Court of Appeals, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
597 P.2d 1070, 100 Idaho 380, 1979 Ida. LEXIS 456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cougar-bay-co-inc-v-bristol-idaho-1979.