Couch v. Natural Resources & Environmental Protection Cabinet

986 S.W.2d 158, 1999 Ky. LEXIS 19, 1999 WL 79377
CourtKentucky Supreme Court
DecidedFebruary 18, 1999
DocketNo. 98-SC-322-DG
StatusPublished
Cited by4 cases

This text of 986 S.W.2d 158 (Couch v. Natural Resources & Environmental Protection Cabinet) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Couch v. Natural Resources & Environmental Protection Cabinet, 986 S.W.2d 158, 1999 Ky. LEXIS 19, 1999 WL 79377 (Ky. 1999).

Opinion

OPINION OF THE COURT

Having considered the arguments of the parties and the opinion of the Court of Appeals, we conclude that the opinion of the Court of Appeals is sound and well-reasoned. We, therefore, affirm and adopt the opinion of the Court of Appeals in full and set it forth as follows:

“This is an appeal from a judgment entered by the Perry Circuit Court reversing a final order, issued by the secretary of appellant Natural Resources and Environmental Protection Cabinet (cabinet), assessing civil penalties against appellee Bert Couch for certain violations of KRS Chapter 350 relating to surface coal mining. On appeal, the cabinet contends that the court erred (1) by finding that the enforcement proceeding was barred by limitations, (2) by failing to find that Couch waived a certain contention as to the applicability of KRS 350.990(9), (3) by finding that the evidence was insufficient to establish that Couch was an agent of the corporate permittee, and (4) by finding that the evidence was insufficient to establish that Couch knowingly and willfully ordered, authorized, or carried out surface coal mining activities in violation of applicable law. We agree with all of the cabinet’s contentions. Hence, we reverse and remand.

“This proceeding stems from a land disturbance which took place in Perry County in 1983, allegedly for the purpose of constructing a road to a family cemetery. The record shows that on their second attempt, Couch and one Bradley Woolum obtained approval but no financial assistance for the project from the Perry Fiscal Court. G & W Construction Company (G & W) then was incorporated in July 1983, and Woolum was designated as its president, director and shareholder. Although Woolum and Couch did not apply for or receive a surface mining permit, on July 25, 1983, they obtained a Mines and Minerals license which permitted them to sell coal from the site. Couch provided the start-up capital for G & W and paid its various bills as they came due. Apparently, he expected to be reimbursed for these expenditures out of the net proceeds derived from the sale of coal removed from the project site:

“The occurrence of certain subsequent events led the cabinet to assess proposed penalties against Couch and others, and a hearing eventually followed. These events are succinctly summarized in the hearing officer’s report in pertinent part as follows:

5. On July 28, 1983, Officer Addison advised Woolum of the regulatory requirement of government financing and stated that the Department thought the subject disturbance was illegal. The following day, Officer Addison advised Woolum and Couch of the requirements pertaining to permitting and exemptions. Defendants were advised not to remove coal from the site.
6. On July 30, 1983, Officer Addison flew over the site and observed that coal had been uncovered and removed.
7. On August 1, 1983, Officer Addison learned from Pine Branch Coal Sales that on July 30, some 203.88 tons of coal had [160]*160been hauled and dumped on its coal yard from the Krypton site by G & W Construction Company. On August 4 an additional 182.82 tons of coal was hauled to Pine Branch Coal Company from the Krypton site.
8. On August 8, 1983, in an overflight Officer Addison observed a second pit uncovered and being removed.
9. On August 8,1983, Notices of Noncompliance Nos. 080045 and 080044 and Cessation Order 080045 were issued to G & W Construction, Albert Engle, Albert Engle, Jr., Patricia Engle, Bradley Woolum, Bert Couch and Joe Hurt for the following violations of KRS 350 and the regulations promulgated pursuant thereto:
a. Mining without a permit, in violation of 405 KAR 7:040;
b. Failure to maintain adequate silt control, in violation of 405 KAR 16:090;
c. Failure to salvage and store all available topsoil, in violation of 405 KAR 16:050;
d. Improper spoil disposal, in violation of 405 KAR 16:130;
e. Improper blasting, in violation of 405 KAR 16:020.
10. The Notices of Noncompliance and Cessation Order were delivered on site to Bradley Woolum and were mailed by certified mail to G & W, Bradley Woolum, Bert Couch, Albert Engle, Albert Engle, Jr., Patricia Engle and Joe Hurt at P.O. Box 12, Bonneyman, KY, the corporation’s address.
11. In disregard of these notices and order to cease mining, defendants Woolum and Couch hauled coal from the site from dusk until the early morning hours of August 9, 1983. On August 9, Officer Addison observed a new pit of coal had been removed.

The hearing officer recommended that the secretary enter a final order finding that G & W violated KRS 350.060, that Woolum and Couch were G & W’s officers or agents, and that Woolum and Couch were individually liable for willfully and knowingly authorizing, ordering, or carrying out G & W’s violations. KRS 350.990(9). Subsequently, the secretary adopted the hearing officer’s report and recommendations, and issued a final order imposing a $50,000 penalty against G & W, as well as a $50,000 joint and several penalty against Woolum and Combs.

“Couch appealed to the Perry Circuit Court and the order, insofar as it affected Couch, was vacated and set aside. The court found that insufficient evidence was adduced to establish either that Couch was G & W’s agent, that Couch knowingly and willfully ordered, authorized, or carried out surface coal mining violations within the meaning of KRS 350.990(9), or that Couch was subject to penalties pursuant to KRS 350.990(9). This appeal followed.

“First, the cabinet contends that the court erred by finding that the administrative proceeding below was barred by the statute of limitations applicable to collection actions. The cabinet asserts that Couch waived any limitations defense to the proceeding by failing to raise it prior to filing his exceptions to the hearing officer’s report. However, even if we assume that the limitations issue was not waived, we agree with the cabinet’s contention that the court erred by finding that the proceeding is barred by limitations.

“KRS 413.120(3) requires a penalty or forfeiture action to be commenced “within five years after the cause of action accrued.” KRS 350.028(4) empowers the cabinet “[t]o issue, after an opportunity for a hearing, a final order imposing civil penalties for violations of this chapter.” However, 405 KAR 7:0921

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Givens v. Commonwealth
359 S.W.3d 454 (Court of Appeals of Kentucky, 2011)
COM. NAT. RES. & ENVIR. PROT. v. Kentec
177 S.W.3d 718 (Kentucky Supreme Court, 2005)
Commonwealth v. Evans
45 S.W.3d 442 (Kentucky Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
986 S.W.2d 158, 1999 Ky. LEXIS 19, 1999 WL 79377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/couch-v-natural-resources-environmental-protection-cabinet-ky-1999.