Corzine v. 2005 Defense Base Closure & Realignment Commission

388 F. Supp. 2d 446, 2005 U.S. Dist. LEXIS 20025, 2005 WL 2175454
CourtDistrict Court, D. New Jersey
DecidedSeptember 6, 2005
Docket05-4294 (MLC)
StatusPublished
Cited by4 cases

This text of 388 F. Supp. 2d 446 (Corzine v. 2005 Defense Base Closure & Realignment Commission) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corzine v. 2005 Defense Base Closure & Realignment Commission, 388 F. Supp. 2d 446, 2005 U.S. Dist. LEXIS 20025, 2005 WL 2175454 (D.N.J. 2005).

Opinion

MEMORANDUM OPINION

COOPER, District Judge.

The plaintiffs brought this action on September 2, 2005, seeking, inter alia, a judgment declaring that the defendants violated the Defense Base Closure and Realignment Act (“BRAC”) — 10 U.S.C § 2687, et seq. — by failing to remove the military base located at Fort Monmouth from the closure list, which was (1) compiled by the defendant Secretary of Defense Donald Rumsfeld (“the Secretary”), and (2) reviewed by the defendant 2005 Defense Base Closure & Realignment Commission (“the Commission”). (Compl., at 28-29.) The plaintiffs now seek to enjoin the Commission from transmitting its report on the Secretary’s initial recommendations (“the Report”) to the President of the United States. (Dkt. entry no. 6.) The Court will deny the application and dismiss the complaint for lack of subject matter jurisdiction.

BACKGROUND

I. The Parties

The plaintiffs — who are, among others, (1) elected officials from New Jersey, and (2) military personnel and their family members — (Compl., at 4-14) — seek to enjoin the Commission from transmitting the Report to the President. 1 They seek also an expedited trial on the merits pursuant to Federal Rule of Civil Procedure 65(a)(2) to resolve the issues presented here. Specifically, they allege the Commission exceeded its statutory authority under BRAC in the following ways:

A. When the BRAC Commission conditioned closure of Fort Monmouth upon the Department of Defense’s (DoD) implementation of unspecified safeguards to avoid degradation of current programs and disruption to the Global War on Terror, the Commission failed to fully approve or fully disapprove the Fort Monmouth recommendation. Such a “conditional closure” was not authorized or contemplated by the BRAC Act, and it runs counter to the BRAC Act’s purpose of bringing clarity and finality to the base closure process.
B. When the BRAC Commission added an amendment to the “conditional closure” directing the Secretary of Defense to submit a report to the appropriate congressional oversight committee regarding the status of the aforementioned safeguards, it reinserted Congress back into the base closure process in a way that was neither authorized nor contemplated by the BRAC Act. This, too, is directly contrary to the purpose of the BRAC Act, which went to great lengths to minimize Congressional involvement in the base closure process.
C. After the BRAC Commission found that the recommendation to close Fort Monmouth deviated substantially from six of the eight final criteria and the Force Structure Plan, it violated the BRAC Act when it did not recommend removal from the closure list. The BRAC statute does not contemplate conditional, “curative” changes that are essentially entirely new recommendations. Rather, where the BRAC Commission finds wholesale substantial deviation from the criteria *448 and the Force Structure Plan, it is limited to the sole remedy of removal from the list. If, on the other hand, the BRAC Commission want[s] to add a base to the closure list, it must do so through the statutorily mandated “adds” procedure.
D. Lastly, even if BRAC Commission did not exceed the scope of its con-gressionally delegated conditional authority to “make changes” to DoD recommendations, it still violated the law because the changes recommended do not adequately address or substantively cure the statutory deficiencies of the recommendation.
E. The 2005 BRAC Act requires all recommendations to meet eight final criteria and comport with the DoD’s Force Structure Plan. According to the BRAC Commission’s findings and amendments, Secretary Rumsfeld’s recommendation to include Fort Monmouth on the closure list violated final criteria 1, 2, 3, 4, 5 & 7 and failed to comport with the Force Structure Plan. By failing to comply with the BRAC Act’s mandates, Secretary Rumsfeld violated the law. The result for Fort Monmouth was severe: had the Fort not been added to the closure list unlawfully by Secretary Rumsfeld, it would not otherwise have been considered for closure, since it was not place on the list via the BRAC Commission’s “adds” process.
F. Section 2913(e) of the BRAC Act requires the Secretary of Defense to consider costs that will be incurred by other non DoD federal entities located on military installations slated for closure or realignment. Secretary Rumsfeld violated this provision of the law when he failed to follow this statutory mandate and consider the costs to the Veterans Administration, the FBI, and the Federal Emergency Management Agency (FEMA), all of which operate at Fort Monmouth.

(PI. Br., at 18-19.) The plaintiffs assert jurisdiction pursuant to the federal question provision of 28 U.S.C. § 1331, the mandamus provision of 28 U.S.C. § 1361, and the Declaratory Judgment Act (“DJA”), 28 U.S.C. §§ 2201-2202.

The defendants, in response, contend that the plaintiffs have no likelihood of success on the merits because their claims “suffer from fatal justiciability flaws”. (Def. Br., at 12.) They claim that the Court lacks subject matter jurisdiction— and thus is precluded from reviewing the Report — under the holding in Dalton v. Specter, 511 U.S. 462, 114 S.Ct. 1719, 128 L.Ed.2d 497 (1994), and in light of the “text, structure, and purpose” of BRAC. Id. at 479, 114 S.Ct. 1719. 2

II. BRAC

The process by which military bases are selected for closure and realignment is governed by BRAC. The purpose of BRAC is “to provide a fair process that will result in the timely closure and realignment of military installations inside the United States.” 10 U.S.C § 2901.

The Secretary prepares first “[a] force-structure plan for the Armed Forces based on an assessment by the Secretary of the *449 probable threats to the national security during the 20-year period beginning with fiscal year 2005.” Id. at § 2912(a)(1)(A). The Secretary then reports on the infrastructure necessary to implement the plan. Id. at § 2912(a)(2). Based on this report, the Secretary certifies whether the need exists to close or realign military bases. Id. at § 2912(b)(1). The base-closure process terminates if the Secretary fails to provide such a certification. Id. at § 2912(b)(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MAGNOLIA NEIGHBORHOOD v. City of Seattle
230 P.3d 190 (Court of Appeals of Washington, 2010)
Magnolia Neighborhood Planning Council v. City of Seattle
230 P.3d 190 (Court of Appeals of Washington, 2010)
Bredesen v. Rumsfeld
500 F. Supp. 2d 752 (M.D. Tennessee, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
388 F. Supp. 2d 446, 2005 U.S. Dist. LEXIS 20025, 2005 WL 2175454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corzine-v-2005-defense-base-closure-realignment-commission-njd-2005.