Cortiza v. Rosenblat
This text of 291 So. 2d 425 (Cortiza v. Rosenblat) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Jose CORTIZA, dba Joe's Welding Shop
v.
Ralph ROSENBLAT and M. & R. Company.
Court of Appeal of Louisiana, Fourth Circuit.
*426 Drake & Fernandez, Manuel O. Fernandez, New Orleans, for plaintiff-appellee.
Joel P. Loeffelholz, New Orleans, for defendants-appellants.
Before SAMUEL, SCHOTT and BOURG, JJ.
SAMUEL, Judge.
This is a suit to recover $620, represented to be the balance due on a contract for remodeling work on a building located at 4007 Prytania Street in New Orleans. The defendants, M. & R. Company, a partnership, and Ralph Rosenblat, one of its partners, answered averring, insofar as issues before this court are concerned, the plaintiff did not complete the job in a workmanlike manner in accordance with the plans and specifications incorporated in the contract. Alternatively, Rosenblat asserted that M. & R. Company is an ordinary partnership with the result that he is only bound to the extent of his virile share in the partnership should judgment be rendered against it.
After a trial on the merits, judgment was rendered in favor of the plaintiff against both named defendants and against one Max Fuksman, Rosenblat's sole partner, in the amount of $500. From that judgment, Rosenblat, the partnership, and Fuksman[1] have appealed.
*427 The contract document consists of a half page contract which expressly incorporates two blue-line drawings. In the contract plaintiff agreed to remove a wooden second floor balcony and replace it with an ornamental iron and steel porch measuring 48 feet in length by 6 feet in width. The total price for the job was $2,000, and it is admitted the defendants have paid all but $500 of this amount.
Rosenblat and Fuksman both complained that the contract was not performed in a workmanlike manner. They testified the welding is rough, weatherboards were not replaced in front of the building, a steel beam was not embedded in the front of the building at the level of the second story porch in order to anchor the porch to the building, (apparently alternatively) the steel support at the back of the porch abutting the face of the building was not placed in its proper spot in accordance with the drawing, the junction between the new steel porch and the front of the house was not waterproofed and allowed rain water to drain down the face of the building, and the metal plates which form the base of the support columns did not fit flush with the first story concrete porch upon which the entire new structure was built.
Plaintiff presented the testimony of Jose Fernandez, an engineer who testified he had prepared the drawings and written the contract. He stated the work had been done in accordance with the drawings and the contract. In addition, he testified the metal plates at the base of the iron columns did not fit flush with the concrete porch because the porch itself was not flat; but the plates formed their weightbearing function properly and were secured by bolts into the concrete to hold the column in place.
A review of the drawings, and particularly the overhead drawing made part of the contract, shows that at all times the parties contemplated the porch would be supported where it joined the house by four columns composed of ¾ inch angle iron. These columns are shown on the drawing and there is no provision in the contract for the installation of a metal beam in or against the front of the building at the second floor porch level into which the porch was to be anchored.
The only possible variances in the contract and drawings are the lack of paint on certain weatherboards replaced by the plaintiff and the improper position of one of the rear columns against the front of the house. Both the plaintiff and his witness testified the weatherboards were not painted. However, there is nothing in the contract which calls for the plaintiff to perform painting other than a primer and one coat on the steel installed by him.
In addition the drawings provide that the four posts at the back of the porch abutting the house were to be located directly behind its corresponding post at the front of the porch. One of the rear posts was moved to one side approximately 3 feet because it would have interfered with access to what appears to be built-in mailboxes in the front of the building. The defendants contend these mailboxes should have been considered when the drawings were made and that plaintiff is in breach of the contract by installing the column as he did. It is undisputed that moving the column approximately 3 feet had no effect on the structural integrity of the porch.
Plaintiff testified, and the lower court found, that he placed the column where he did with full knowledge and at the order of the defendants. It is clear that neither plaintiff not the defendants considered the existing mailboxes when the plans were approved.
Under the law this court is not compelled to decide who should bear the loss for this mutual oversight or to determine what amount, if any, should be deducted from the contract price. The record is clear that the plaintiff at least substantially performed the contract. The law is equally clear that building contracts are an exception to the general rule that a *428 party cannot recover on a commutative contract unless he can prove full performance. On the contrary, a construction contractor can sue for and recover the full contract price merely upon proof of substantial performance. In such a case the owner's remedy is to allege and prove the extent of any unfinished or defective work and the cost of completion or correction thereof in order to reduce the contractor's recovery by the amount of the cost of completion or correction; the burden is not upon the contractor to prove the value of the work actually done; the burden rests squarely upon the owner to prove the cost of correction or completion.[2]
In the present case, even if the defects complained of by defendants actually exist, the record contains no evidence whatsoever regarding the cost of completion or correction. The defendants did not attempt to carry their burden of proof in this regard. Accordingly, we find plaintiff is entitled to recover the remaining $500 balance of the contract price.
The trial court had no authority to cast Max Fuksman as a party defendant in this case. He was never named as a defendant, nor was he cited or served at any time. It is admitted that he is a partner of Rosenblat, that together they own M. & R. Company, the defendant partnership, and that he signed the contract in question. However, his only procedural connection with this case is his testimony in favor of the named defendants. Article 6 of the Louisiana Code of Civil Procedure reads as follows:
"Jurisdiction over the person is the legal power and authority of a court to render a personal judgment against a party to an action or proceeding. This jurisdiction must be based upon:
(1) The service of process on the defendant, or on his agent for the service of process;
(2) The service of process on the attorney at law appointed by the court to defend an action or proceeding brought against an absent or incompetent defendant who is domiciled in this state; or
(3) The submission of the party to the exercise of jurisdiction over him personally by the court, or his express or implied waiver of objections thereto." LSA-C.C.P. Art. 6.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
291 So. 2d 425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cortiza-v-rosenblat-lactapp-1974.