Corscadden v. Kenney

572 P.2d 1234, 175 Mont. 98, 1977 Mont. LEXIS 846
CourtMontana Supreme Court
DecidedDecember 23, 1977
Docket13653
StatusPublished
Cited by9 cases

This text of 572 P.2d 1234 (Corscadden v. Kenney) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corscadden v. Kenney, 572 P.2d 1234, 175 Mont. 98, 1977 Mont. LEXIS 846 (Mo. 1977).

Opinion

MR. JUSTICE HARRISON

delivered the opinion of the Court.

Nelson E. Corscadden, d/b/a Corscadden Steel Construction *99 Company, brought this action against Stephen J. Kenney, seeking damages occasioned by an alleged breach of contract by Kenney. Kenney answered and counterclaimed for alleged equipment rental due and damages resulting from alleged defective workmanship and default by Corscadden. A nonjury trial was commenced in the District Court, Valley County, on December 2, 1976. By its findings of fact and conclusions of law dated December 30, 1976, the District Court, the Honorable Thomas Dignan presiding, rendered judgment for plaintiff Corscadden in the amount of $8,961.55 with interest at 6 percent per annum, and denied Kenney’s counterclaim. Kenney appeals the judgment and the denial of his counterclaim.

Defendant Kenney, a contractor from Hardin, Montana, was the successful bidder with the United States Corps of Engineers on a contract to rehabilitate a barge at Fort Peck, Montana. A portion of the rehabilitation consisted of welding on the barge. Corscadden submitted a bid to Kenney, seeking to subcontract performance of the welding services. The bid was rejected. However, in May, 1975, a verbal agreement was entered into between Kenney, by his superintendent Ralph Marcher, and Corscadden. Kenney hired Corscadden and his employees on an hourly basis to furnish labor by certified welders, welding material and two welding machines at a rate of pay of $16 per man hour. Corscadden and his employees were to begin performance in May, 1975. Although Corscadden and his employees were based in Glasgow, Montana, a distance of 17 miles from the job site, no agreement was reached at the time concerning mileage charges.

Corscadden moved the welding equipment from Glasgow to Fort Peck and began performance on May 12, 1975. On June 22, however, a dispute arose between the parties concerning the rate at which the work was progressing. Corscadden terminated the employment and moved his men and equipment off the job.

On June 24, unable to locate replacement welders, Marcher reached a verbal agreement with Corscadden for continued performance, the terms of which, for the greater part, are in dispute. *100 The parties agree that Corscadden and his men were entitled to a new rate of pay of $22 per hour. Corscadden contends, however, the parties agreed the new rate of pay would operate retroactively to the beginning of the job, covering some 145V2 man hours worked, and mileage charges of $1 per actual mile traveled between Glasgow and Fort Peck, also applicable retroactively. Such items were alleged to have been payable upon completion of the work. Marcher disputes the latter terms. In any event, Corscadden and his men did return to work on June 24, 1975, and commenced performance under the terms of the new agreement.

At trial, the parties disputed liability for rent on certain items of Corscadden welding equipment. Kenney and Marcher admitted liability for an exhaust fan, one grinding machine, oxygen and acetylene bottles and gauges, and a cutting head. However, Corscadden testified additional items of equipment, consisting of a second grinding machine, a paint respirator, a “scarfing tip”, and flood lights were also rented. Marcher asserted the rental rates were to have been those established by a local rental agency, Moen’s Equipment Rental of Glasgow. Corscadden testified there was no agreement to so restrict the rental rates, but rather the rates charged were those he typically charges for rental of such items; a rate higher than that charged by Moen’s. It should be noted, in this regard, that certain of the items in dispute were not available for rental at Moen’s.

A further dispute concerns the cost of time and travel for a three day testing and recertification of one of Corscadden’s employees, Zane Geer. Corscadden contends Kenney is liable for such costs under the express terms of the prime contract between the United States and Kenney. Kenney denies liability for such costs, arguing Corscadden had agreed to provide certified welders.

In support of his counterclaim for damages due to delay and defective workmanship, Marcher testified Corscadden failed to provide the two-man work force agreed upon during May and June, 1975. Other welders were employed by Kenney to complete the job. Kenney stated that, due to the delay, he was unable to bid on other potential jobs. Other defense witnesses indicated, how *101 ever, the delays were due primarily to the failure of Kenney’s crew to have welding steel available and make the job site ready for work. It is undisputed that Kenney was subjected to no fine or penalty due to the ultimate delay in completing performance on the prime contract. Additionally, Marcher testified Corscadden’s failure to provide the proper one-fourth-inch welds required by the terms of the prime contract resulted in approximately 200 hours of rewelding and, thus, additional delay and cost to Kenney. Kenney stated he was damaged in an approximate amount in excess of $ 10,000. Corscadden testified, however, he was not made aware of the specifications regarding weld thickness and was not informed of the insufficiency of the work at the time it was being performed, although Marcher himself was in constant supervision of the welding work.

Corscadden testified that due to Kenney’s failure to make scheduled payments on their agreement, he was forced to obtain high cost bank loans to finance his employees’ salaries and continued operations. As a result, Corscadden allegedly suffered a loss of credit and damages to his business reputation.

Corscadden and his men completed their work on August 20, 1975. Kenney contends his final payment of $6,541.44, by check dated October 30, 1975, was accepted and cashed in full satisfaction of the account. Corscadden denied such sums were accepted as final payment.

The District Court gave judgment for Corscadden on all items of damage, save those for loss of credit and business reputation. Awarded to Corscadden were the following:

Total 824V2 hours labor at $22 per hour, including 24 hours compensation for recertification of Corscadden employee Geer .........................$18,139.00

Mileage charges, retroactive to May 12, 1975....... 3,706.00

Equipment rental and other charges.............. 3,727.55

TOTAL DUE CORSCADDEN FROM KENNEY .... $25,572.55

Less payments made by Kenney ................. (16,611,00)

BALANCE DUE AND OWING..................$ 8,961.55

*102 The court computed 6 percent interest on the rental and other charges from December 15, 1975, the date at which the last of the equipment was returned, and 6 percent interest on the balance owing on the labor and mileage accounts from October 30, 1975, the date at which the last of the payments on such account was made.

The District Court denied Kenney’s counterclaim on the ground that the work was done under the direct supervision of Kenney’s foreman, Marcher, who failed tó disclose the plans and specifications to the welders. Thus, Corscadden could not be held responsible for the delays due to faulty welding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morning Star Enterprises, Inc. v. R. H. Grover, Inc.
805 P.2d 553 (Montana Supreme Court, 1991)
Van Hook v. Baum
800 P.2d 151 (Montana Supreme Court, 1990)
Goodover v. Lindey's, Inc.
757 P.2d 1290 (Montana Supreme Court, 1988)
Wortman v. Griff
651 P.2d 998 (Montana Supreme Court, 1982)
Sawyer-Adecor International, Inc. v. Anglin
646 P.2d 1194 (Montana Supreme Court, 1982)
Kartes v. Kartes
636 P.2d 272 (Montana Supreme Court, 1981)
Harris v. Harris
616 P.2d 1099 (Montana Supreme Court, 1980)
Lumby v. Doetch
600 P.2d 200 (Montana Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
572 P.2d 1234, 175 Mont. 98, 1977 Mont. LEXIS 846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corscadden-v-kenney-mont-1977.