Correct Piping Co. v. City of Elkins

308 F. Supp. 431, 1970 U.S. Dist. LEXIS 13063
CourtDistrict Court, N.D. West Virginia
DecidedJanuary 27, 1970
DocketCiv. A. No. 730-E
StatusPublished
Cited by3 cases

This text of 308 F. Supp. 431 (Correct Piping Co. v. City of Elkins) is published on Counsel Stack Legal Research, covering District Court, N.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Correct Piping Co. v. City of Elkins, 308 F. Supp. 431, 1970 U.S. Dist. LEXIS 13063 (N.D.W. Va. 1970).

Opinion

MEMORANDUM OPINION

MAXWELL, Chief Judge.

Plaintiff, an Indiana corporation, in association with William G. Hartman [432]*432and Harold R. Elbon, partners, trading and doing business as Building Associates, as contractor, entered into a written contract with the defendant, City of Elkins, a West Virginia municipal corporation, to furnish labor, materials and other services for construction of extensions ,to the defendant city’s water system. The specifications and contract documents are embodied in an instrument entitled “Extensions to Water System Water Line to Reidboard Plant El-kins, West Virginia 1962 AR-W.Va.-55.-042.2." The contract is shown to have been executed by all parties on February 22, 1963.

The complaint recites that, by agreement dated March 24, 1964, recorded in the office of the Clerk of the County Court of Randolph County, West Virginia, Messrs. Hartman and Elbon assigned all their rights and interests in the contract to plaintiff who agreed to complete the contract obligations, including “change orders.” Paragraph 10 of the complaint asserts that plaintiff completed construction of the project and that defendant city placed the water line in operation on or about October 27, 1963.

Defendant caused to be prepared a final estimate for the project, dated November 14, 1963, indicating completion of the project and that the sum of $12,-004.52 was yet due to plaintiff-contractor thereon. Negotiations failed .to produce a settlement between the parties and this action was instituted December 1, 1966, for plaintiff’s recovery of the total sum of $39,526.20 from defendant for balance due on the contract, extra work and materials, interest and other sums itemized.

Defendant city, denying many allegations of the complaint, admits in paragraph 11 of its answer that it owes plaintiff the sum of $12,004.52. Defendant denies interest items claimed by plaintiff, asserting that the project funds had to be requisitioned from the Federal Government and that a Federal Government audit had to be completed before payment could be made to plaintiff, all of which circumstances were known to plaintiff prior to execution of the contract.

A “Joint Motion by Plaintiff and Defendant for Judgment on the Pleadings” was filed on October 12, 1967, and on that date the Court entered judgment for plaintiff and against defendant for the sums of $280.41 for materials sold by plaintiff to defendant and $12,004.-52, the amount recognized by the final estimate to be due plaintiff on the contract. All other items claimed by plaintiff were denied in the Court’s judgment order, except the item of interest was left open for adjudication after the parties had submitted briefs and had an opportunity to present evidence thereon. Consequently, the only issue before the Court at this time is whether any interest is owing by defendant to plaintiff on the sum of $12,004.52 and, if so owing, for what period of time.

Jurisdiction of this action is based on diversity of citizenship and amount in controversy. 28 U.S.C.A. § 1332. No question appears as to jurisdiction.

The complaint recites that the contract here involved was dated December 19, 1962, and is incorporated in the complaint by reference. Defendant’s answer admits the correctness of these recitals. The contract document discloses the contract was executed on February 22, 1963.

The complaint, paragraph 3, recites that Final Estimate No. 5, dated November 14, 1963, is incorporated by reference. Defendant’s answer does not deny this incorporation and defendant’s brief, page 1, recognizes the preparation and execution of the final estimate and that a copy thereof has been submitted to the Court.

The contract documents, Special Conditions, page 33, item 8, read:

“Before the work is accepted and final payment made therefor, Contractor will execute a maintenance bond in form and with corporate surety approved by Owner in an amount equal to twenty (20) percent of the contract price * *

[433]*433Paragraph 3 of the complaint refers to the maintenance bond. Defendant’s brief, page 4, refers to the executed maintenance bond, dated June 12, 1964, a copy of which is attached to and made a part of the brief.

The three instruments, the contract, the final estimate and the maintenance bond, are thus identified and recognized by the parties and are considered parts of the record in this action. Defendant’s answer, paragraph 10, and its brief refer to the Federal Government audit of the project, but the audit itself is not found in the record. The General Conditions of the contract documents, item 14, page 7, relates to inspections by representatives and agents of the Housing and Home Finance Administrator but does not mention a Federal Government audit.

The substantive law of West Virginia, relating to contracts and interest, will apply in this action. 28 U.S.C.A. § 1652; Erie R. Co. v. Tompkins, 304 U.S. 64, 54 S.Ct. 817, 82 L.Ed. 1188 (1938); Tow v. Miners Memorial Hospital Association, 305 F.2d 73 (Cir. 4th 1962); Culbertson v. Jno. McCall Coal Co., 275 F.Supp. 662 (S.D.W.Va.1967); 20 Am.Jur.2d, Courts, §§ 207-209 (1965); Annot., 21 A.L.R.2d 247 (1952).

“The principles of law governing the construction of contracts generally are applicable to building and construction contracts.” 13 Am.Jur.2d, Building and Construction Contracts, § 8 (1964). “A contract must be considered as a whole, effect being given, if possible, to all parts of the instrument.” Wood Coal Co. v. Little Beaver Mining Co., 145 W.Va. 653, 116 S.E.2d 394 (1960). The intention of the parties to the contract shall be controlling and the courts may not rewrite the contract for them. Eastern Gas and Fuel Associates v. Midwest-Raleigh, Inc., 374 F.2d 451 (Cir. 4th 1967); 4 Williston on Contracts, § 610A (3d Ed Jaeger 1961). “Uncertainties in an intricate and involved contract should be resolved against the party who prepared it.” Charlton v. Chevrolet Motor Co., 115 W. Va. 25, 174 S.E. 570 (1934); Lewis v. Barnes Construction Co., 179 F.Supp. 673 (N.D.W.Va.1959); Castner, Curran & Bullitt, Inc. v. Sudduth Coal Co., 282 F. 602 (Cir. 4th 1922); 4 Williston on Contracts, § 621 (3d Ed. Jaeger 1961). The parol evidence rule “requires, in the absence of fraud, duress, mutual mistake, or something of the kind, the exclusion of extrinsic evidence, oral or written, where the parties have reduced their agreement to an integrated writing.” 4 Williston on Contracts, § 631 (3d Ed. Jaeger 1961); Hartmann v. Windsor Hotel Co., 136 W.Va. 681, 68 S.E.2d 34 (1951); Wyckoff v. Painter, 145 W.Va. 310, 115 S.E.2d 80 (1960). Another general principle of contract law is stated in the following language from 17 Am.Jur.2d, Contracts, § 288 (1964):

In the case of a contract with a state or other government, the language of the contract, as in other cases, is to be given its usual and ordinary meaning, if that is possible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nisbet v. Watson
251 S.E.2d 774 (West Virginia Supreme Court, 1979)
United States v. Marietta Manufacturing Co.
53 F.R.D. 390 (S.D. West Virginia, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
308 F. Supp. 431, 1970 U.S. Dist. LEXIS 13063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/correct-piping-co-v-city-of-elkins-wvnd-1970.