Cornerstone General Contractors, Inc., V. Pellco Construction, Inc.

CourtCourt of Appeals of Washington
DecidedOctober 4, 2021
Docket81642-0
StatusUnpublished

This text of Cornerstone General Contractors, Inc., V. Pellco Construction, Inc. (Cornerstone General Contractors, Inc., V. Pellco Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornerstone General Contractors, Inc., V. Pellco Construction, Inc., (Wash. Ct. App. 2021).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

PELLCO CONSTRUCTION, INC., a ) No. 81642-0-I Washington corporation, ) ) DIVISION ONE Appellant, ) ) UNPUBLISHED OPINION v. ) ) CORNERSTONE GENERAL ) CONTRACTORS, INC., a Washington ) corporation, NORTHSHORE SCHOOL ) DISTRICT NO. 417, a Washington school ) district municipal corporation, ) ) Respondent. ) )

HAZELRIGG, J. — PELLCO Construction, Inc. appeals from a denial of its

motion for a preliminary injunction. PELLCO concedes that its appeal is moot, as

a disappointed bidder’s only remedy at law is to seek injunctive relief before a

contract is executed. Because PELLCO has not demonstrated a substantial and

continuing public interest justifying review, despite mootness, we dismiss the

appeal.

FACTS

This dispute arises out of public bidding for Northshore School District’s

Inglemoor High School Concert Hall & Music Building project. Cornerstone

General Contractors, Inc. (Cornerstone) serves as the general

Citations and pinpoint citations are based on the Westlaw online version of the cited material. No. 81642-0-I/2

contractor/construction manager (GC/CM) for the project. Prior to bidding,

PELLCO reached out to the school district several times to express concerns with

the fairness and effectiveness of the bid package structure. The school district

considered PELLCO’s feedback, issued responsive addenda, and slightly altered

the bid packages, to address PELLCO’s concerns. Most significantly, Cornerstone

and Northshore School District split the structures bid package into two discrete

packages: one for concrete, one for steel. Interested parties could submit bids for

one package or “combination” bids for both packages.

PELLCO Construction, Inc. (PELLCO) bid on the concrete package and

submitted the lowest responsive, responsible bid for the package. However,

Cornerstone’s combination bid was lower than the sum of PELLCO’s concrete bid

and the lowest separate bid for the steel package. PELLCO timely protested

Cornerstone’s bid, alleging that RCW 39.10.390 prohibits GC/CMs from bidding

on subcontractor work unless the GC/CM performs the work with its own labor (as

opposed to subcontracting the work). PELLCO filed a motion for preliminary

injunction to enjoin Cornerstone from executing the contract. After oral argument,

the King County Superior Court denied PELLCO’s motion. PELLCO now appeals.

ANALYSIS

PELLCO’s challenge presents a question of statutory interpretation as it

argues that the plain meaning of RCW 39.10.390 precludes GC/CMs from bidding

on subcontract work if the GC/CM subcontracts that work (as opposed to

performing it with its own labor, equipment, and expertise). As such, PELLCO

alleges that Cornerstone was legally precluded from bidding on both the concrete

-2- No. 81642-0-I/3

and steel packages because it does not perform steel fabrication or erection work

through its own forces and instead sub-contracts its steel work. Northshore School

District and Cornerstone argue that the plain meaning of RCW 39.10.390 only

requires that the GC/CM perform the subcontract work it bids on by taking

contractual responsibility for the work, either by performing with its own forces or

by further subcontracting the work.

We must first determine whether we will consider the merits of PELLCO’s

claim at all. PELLCO concedes that, as a disappointed bidder, it has lost standing

to seek a legal remedy. Cornerstone has already executed the structures

subcontract, and the project will be complete in December 2021. Cornerstone and

Northshore School District ask us to dismiss PELLCO’s petition as moot, while

PELLCO asks us to grant discretionary review under the public interest exception.

I. Mootness

A disappointed bidder in a public contract dispute has limited remedies

available—they may sue to enjoin the contract before it is executed. Dick

Enters., Inc. v. Metro. King County, 83 Wn. App. 566, 569, 922 P.2d 184 (1996).

Contract formation serves as a “bright-line cutoff” for bidder standing. Id. at 571.

PELLCO concedes that its appeal is moot, as the disputed contract has been

executed and work is scheduled to be completed by December 2021. However,

PELLCO asks this court to grant discretionary review in the public interest.

As a general rule, this court declines to review cases “where only moot

questions” remain to avoid giving advisory opinions. Sorenson v. City of

Bellingham, 80 Wn.2d 547, 558, 496 P.2d 512 (1972); Nat’l Elec. Contractors

-3- No. 81642-0-I/4

Ass’n v. Seattle Sch. Dist. No. 1, 66 Wn.2d 14, 17–18, 400 P.2d 778 (1965). There

is “[a] recognized exception to this general rule,” and this court will grant review of

an otherwise moot case if it involves “‘matters of continuing and substantial public

interest.’” Hart v. Dep’t of Soc. and Health Servs., 111 Wn.2d 445, 447, 759 P.2d

1206 (1988) (quoting Sorenson, 80 Wn.2d at 558). This is an exception to the

general rule, and we will only “deliver advisory opinions” on “‘rare occasions where

the interest of the public in the resolution of an issue is overwhelming.’” To-Ro

Trade Shows v. Collins, 144 Wn.2d 403, 416, 27 P.3d 1149, 1155 (2001)

(emphasis added) (quoting In re Disciplinary Proceeding Against Deming, 108

Wn.2d 82, 122–23, 736 P.2d 639, 744 P.2d 340 (1987) (Utter, J., concurring)).

In determining whether there is sufficient public interest to justify issuing an

advisory opinion, courts consider several criteria: 1) the public or private nature of

the question presented; 2) desirability of an authoritative determination for the

future guidance of public officers; 3) likelihood of future recurrence; 4) the level of

genuine adverseness and quality of advocacy; 5) the likelihood the issue will

escape review due to short-lived facts. Sorenson, 80 Wn.2d at 558; Westerman

v. Cary, 125 Wn.2d 277, 286–87, 892 P.2d 1067 (1994).

A. Public or Private Nature of the Question Presented

First, PELLCO argues that the public has a significant interest in this dispute

because millions of taxpayer dollars are spent on public contracting and thus the

public has an interest “in ensuring this money is being properly spent.”

Cornerstone and Northshore School District argue that this is a private dispute

between contracting companies, and the dispute is of a private, commercial nature.

-4- No. 81642-0-I/5

PELLCO’s suit arises out of its private, commercial interest in being

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westerman v. Cary
892 P.2d 1067 (Washington Supreme Court, 1995)
Sorenson v. City of Bellingham
496 P.2d 512 (Washington Supreme Court, 1972)
Orwick v. City of Seattle
692 P.2d 793 (Washington Supreme Court, 1984)
Hart v. DEPT. OF SOCIAL AND HEALTH SERVS.
759 P.2d 1206 (Washington Supreme Court, 1988)
Dick Enterprises, Inc. v. King County
922 P.2d 184 (Court of Appeals of Washington, 1996)
Millers Casualty Insurance Co. of Texas v. Briggs
665 P.2d 887 (Washington Supreme Court, 1983)
In Re the Personal Restraint of Montoya
744 P.2d 340 (Washington Supreme Court, 1987)
In Re the Disciplinary Proceeding Against Deming
736 P.2d 639 (Washington Supreme Court, 1987)
In Re Guardianship of Wells
208 P.3d 1126 (Court of Appeals of Washington, 2009)
In Re Recall Charges Against Feetham
72 P.3d 741 (Washington Supreme Court, 2003)
To-Ro Trade Shows v. Collins
27 P.3d 1149 (Washington Supreme Court, 2001)
To-Ro Trade Shows v. Collins
144 Wash. 2d 403 (Washington Supreme Court, 2001)
In re the Recall of Feetham
72 P.3d 741 (Washington Supreme Court, 2003)
Care Planning Associates v. Mayberry
208 P.3d 1126 (Court of Appeals of Washington, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Cornerstone General Contractors, Inc., V. Pellco Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornerstone-general-contractors-inc-v-pellco-construction-inc-washctapp-2021.