This text of Washington § 39.10.390 (General contractor/construction manager procedure—Subcontract work.) is published on Counsel Stack Legal Research, covering Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wash. Rev. Code § 39.10.390 (2026).

Text

(1)Except as provided in this section, bidding on subcontract work or for the supply of equipment or materials by the general contractor/construction manager or its subsidiaries is prohibited.
(2)The general contractor/construction manager, or its subsidiaries, may bid on subcontract work or for the supply of equipment or materials if:
(a)The work within the subcontract bid package or equipment or materials is customarily performed or supplied by the general contractor/construction manager;
(b)The bid opening is managed by the public body and is in compliance with RCW 39.10.380 ; and
(c)Notification of the general contractor/construction manager's intention to bid is included in the public solicitation of bids for the bid package or for the equipment or materials.
(3)In no event

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 39.10.380
Washington § 39.10.380
§ 39.10.210
Washington § 39.10.210

Legislative History

[2021 c 230 s 13;2014 c 42 s 7;2013 c 222 s 16;2007 c 494 s 306.]

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Washington § 39.10.390, Counsel Stack Legal Research, https://law.counselstack.com/statute/wa/39.10.390.