Coopersmith v. Rose

81 Pa. D. & C. 356, 1951 Pa. Dist. & Cnty. Dec. LEXIS 224
CourtPennsylvania Court of Common Pleas, Northampton County
DecidedJune 11, 1951
Docketno. 75
StatusPublished

This text of 81 Pa. D. & C. 356 (Coopersmith v. Rose) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Northampton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coopersmith v. Rose, 81 Pa. D. & C. 356, 1951 Pa. Dist. & Cnty. Dec. LEXIS 224 (Pa. Super. Ct. 1951).

Opinion

Woodring, J.,

We are herein concerned with two motions made in an arbitration proceeding subsequent to the award. The award was in favor of plaintiff. Defendant filed his motion for a rule to show cause why the award should not be modified or corrected. Thereafter, plaintiff applied to the court for an order confirming the award. We will consider both motions in this opinion.

A brief summary of the facts, as contained in the transcript of testimony, which is in excess of 400 pages, and in a large number of exhibits, is as follows:

Defendant acquired a building lot in the City of Easton and employed an architect to design a home to be erected thereon. Plans and some specifications were prepared and submitted to contractors for estimates of cost. Plaintiff is a contractor and after receipt of the plans wrote a letter (exhibit 3) to defendant on August 15, 1947, in which he said:

[358]*358“We hereby submit our estimate of Fourteen Thousand Dollars ($14,000.00) for the furnishing of all Labor, Materials, plant and equipment to complete this project.”

Plaintiff then described the proposed method of construction, which proposal differed from the plans and specifications. Plaintiff’s letter closes with:

“We trust that the above meets with your approval and that we may be favored with your order.”

On August 18, 1947, plaintiff, contractor, and defendant, owners of the premises, entered into a written contract under seal on a form of the A. I. A. (American Institute of Architects), wherein the contractor agreed to provide all the materials and perform all the work for the construction of a residence. Article IX provides:

“It is hereby mutually agreed between the parties hereto that the sum to be paid by the Owners to the Contractor for said work and materials shall be cost of labor and materials directly employed in the work plus 10%. . . .”

Article XII provides:

“In case the Owners and contractor fail to agree in relation to matters of payment . . . then the matter shall be referred to a Board of Arbitration to consist of one person selected by the Owners, and one person selected by the Contractor, these two to select a third. The decision of any two of this Board shall be final and binding on both parties hereto.”

The contract fails to provide a completion date and Article V authorizes the owners to terminate the employment of the contractor after three days’ written notice and upon the certification of the architect and to employ other persons to finish the work.

Work on the building commenced in the fall of 1947, and continued into the month of December, at which time it was suspended because of inclement weather. [359]*359Operations were recommenced in the spring of 1948, and continued into November or December of that year, at which time the residence building was substantially completed. During the building operation plaintiff submitted bills and statements of account for labor and materials on October 20,1947, in the amount of $4,828.51; June 5,1948, in the amount of $12,516.60, and on June 29, 1948, in the sum of $2,885.46. These bills were all paid with the exception of the 51 cents of the October 20, 1947 bill, in the total sum of $20,-230.06. On August 2,1948, plaintiff submitted a works progress statement in the sum of $2,744.08, and a 10 percent commission statement to that date in the sum of $2,297.47. On December 10, 1948, plaintiff submitted a final bill in the sum of $12,167.28, for labor and material, and $3,239.78, for the 10 percent commission. Plaintiff totals this bill in the sum of $14,907.07 (our addition would indicate that the correct total is $15,407.07.)

It is to be noted that no formal or substantial protest was made by defendant upon receipt of the bills of October 1947 and June 1948, and none was made upon receipt of the progress statements of August and October 1948. Subsequent to receipt of the final bill, the architect wrote plaintiff on December 29, 1948, which letter includes as follows:

“We can find nothing which would justify the tremendous difference between your estimates and the staggering bill which you finally presented. . . . Wilful neglect of your obligation to Mr. Rose has resulted in unreasonable hardship and embarrassment to all concerned.”

The letter concludes by advising plaintiff that defendant “is turning the matter over to his attorney.”

Plaintiff instituted an action in the Court of Common Pleas of Northampton County to recover the amount of the final bill, together with interest. De[360]*360fendant objected to the action of assumpsit and contended that under the submission clause contained in the contract the question of payment should proceed to arbitration. The court, Woodring, J., by opinion dated June 28, 1949, directed the parties:

"To proceed with arbitration in accordance with the terms of the written contract dated August 18, 1947, and with the provisions of the Act of Assembly of 1927, P. L. 381, as amended.”

Arbitrators were appointed and hearings commenced November 9, 1949, and concluded April 26, 1950. The arbitrators made their award February 21, 1951, as follows:

"The arbitrators ... do award in favor of George Coopersmith, and against Joseph Rose and Freda M. Rose the sum of $14,082.07, with interest calculated at the rate of six per cent per year, beginning March 15, 1951.”

This amount is the full amount of plaintiff’s claim, less $825, which is credited because of defective or inadequate work in such matters as: placing of gravel fill, the making necessary the sanding of the floor, failure to protect finished surfaces while other work was going forward, failure to properly waterproof and soundproof, door defects, ceiling defects, placing of beams, bricklaying errors, and failure to complete drains. Defendant filed exceptions to the award and obtained a rule to show cause why the award should not be modified or corrected. Defendants’ exceptions to the award are four in number and may be summarized as follows:

1. That the arbitrators erred in rejecting- exhibit no. 3, pláintiff’s letter of estimate, under the parol evidence rule;

2. The arbitrators ignored defendants’ exhibit D, the architect’s letter of November 5, 1948;

[361]*3613. The arbitrators ignored the fact that other contractors were engaged (to complete the building) and that payments made to plaintiff were only made on account;

4. The arbitrators ignored their responsibility imposed by article 3 of the contract which article provides : “No alterations shall be made in the work except upon order of the architect. . . .”

Before further considering defendants’ several exceptions, we will turn out attention to the law of arbitration. Arbitration is not to be considered merely an additional phase of litigation but is a complete remedy in itself. A board of arbitrators is an independent forum, excepting as otherwise provided by statute. Speaking of the finality of an arbitration award Blackstone’s Commentaries, vol. 3, sec. 16, page 1036, contains:

“This decision, in any of these cases, is called an award. And thereby the question is as fully determined, and the right transferred or settled, as it could have been by the agreement of the parties or the judgment of a court of justice.”

■ The late Chief Justice Maxey in his opinion in Shannon et al. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grubb v. Rockey
79 A.2d 255 (Supreme Court of Pennsylvania, 1951)
McDevitt v. McDevitt
73 A.2d 394 (Supreme Court of Pennsylvania, 1950)
Shannon v. Pennsylvania Electric Co.
72 A.2d 564 (Supreme Court of Pennsylvania, 1950)
Pennsylvania Turnpike Commission v. Smith
39 A.2d 139 (Supreme Court of Pennsylvania, 1944)
Schar v. Maier
49 A.2d 387 (Supreme Court of Pennsylvania, 1946)
Goldstein v. Int. L. G. W. U.
196 A. 43 (Supreme Court of Pennsylvania, 1937)
Gianni v. Russell Co., Inc.
126 A. 791 (Supreme Court of Pennsylvania, 1924)
Pennsylvania Co. v. Lebanon Building & Loan Ass'n
10 A.2d 418 (Supreme Court of Pennsylvania, 1939)
First Nat. Bk. of Scranton v. Payne
37 A.2d 568 (Supreme Court of Pennsylvania, 1944)
Sukonik v. Shapiro
5 A.2d 108 (Supreme Court of Pennsylvania, 1939)
Canuso v. Philadelphia
192 A. 133 (Supreme Court of Pennsylvania, 1937)
Westinghouse Air Brake Co. Appeal
70 A.2d 681 (Superior Court of Pennsylvania, 1949)
Gloeckler v. Imrie
179 A. 883 (Superior Court of Pennsylvania, 1935)
West Republic Mining Co. v. Jones & Laughlins
108 Pa. 55 (Supreme Court of Pennsylvania, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
81 Pa. D. & C. 356, 1951 Pa. Dist. & Cnty. Dec. LEXIS 224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coopersmith-v-rose-pactcomplnortha-1951.