Cooper v. Klopfenstein

185 N.W.2d 604, 29 Mich. App. 569, 9 U.C.C. Rep. Serv. (West) 114, 1971 Mich. App. LEXIS 2001
CourtMichigan Court of Appeals
DecidedJanuary 20, 1971
DocketDocket 8272
StatusPublished
Cited by4 cases

This text of 185 N.W.2d 604 (Cooper v. Klopfenstein) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cooper v. Klopfenstein, 185 N.W.2d 604, 29 Mich. App. 569, 9 U.C.C. Rep. Serv. (West) 114, 1971 Mich. App. LEXIS 2001 (Mich. Ct. App. 1971).

Opinion

Bronson, P. J.

On February 10, 1965, plaintiffs and defendant, interested in developing certain plots *571 of land, entered into a written contract. The contract provided that plaintiffs were to furnish land, most of which they owned or were in the process of acquiring, and defendant was to furnish the labor and equipment to develop the land. In exchange for the consideration provided, plaintiffs and defendant were to receive shares of stock in the parties’ newly formed corporation. In March of 1966, the contract was modified to enlarge the amount of land to be developed. Defendant was also given a promissory note by the corporation in the amount of $45,000. The contractual agreements between the parties were prepared primarily under the direction of the defendant, and the contracts expressly stated that time was of the essence.

The record reveals that the defendant subsequently pledged certain shares of his stock in the newly formed corporation to a commercial bank, as security for a private loan. The defendant defaulted on the loan and the bank sold the stock pursuant to their security agreement with the defendant. The sale of the stock was private, and the bank sold the stock to the plaintiffs. The purchase of the stock from the bank was made for the asking price established by the bank.

Plaintiffs subsequently filed suit, alleging that defendant had breached the contract by failing to proceed as rapidly as possible with the development of the land. Other specific allegations of defendant’s breach of the written contract were also averred. Plaintiffs requested that the contract be declared null and void and that the defendant’s rights under the contract be terminated. Plaintiffs also sought to be released from liability on the $45,000 note held by the defendant.

The cause was tried in Hillsdale County Circuit Court where the trial judge, sitting without a jury, *572 made the following findings of fact and rulings of law relevant to the issues on appeal:

“The following matters constitute the factual findings of this court which have been established by a preponderance of the proofs, and the ruling of this court upon the legal questions submitted. In light of the necessity that this court make a determination as to whether the defendant breached the contracts involved here, it is necessary that the court make a legal finding at this point that time was of the essence in this contract. The contract prepared under the direction of the defendant so provided in paragraph 16. 17 Am Jur 2d, Contracts, par 508, states: “ ‘As a general rule, where time is of the essence of a contract, and one of the parties has not performed, and is not ready .and able to perform his part of the agreement on the day fixed, the adverse party may elect to consider it at an end.’

This rule has been approved by the Supreme Court of the State of Michigan in Bedford v. Tetzlaff, 338 Mich 102 [1953], and Brody v. Crozier [1928], 242 Mich 660. It is argued by the defendant that since no dates certain for performance was [sic] set forth in the contractual instruments that the provision that time was of the essence is meaningless. This court cannot agree. The law is well settled without the necessity of citation that in construing a contract, the court shall not construe it piecemeal but rather as a whole. Paragraph 5 of the original agreement, plaintiffs’ exhibit #1, provides that the contractor would commence work immediately upon the signing of the contract and continue the work to completion as rapidly as possible and without interruption excepting such as may be caused by weather conditions and other matters not within the control of the contractor. There was no showing on the part of the defendant in his proofs that earlier completion could not have been accomplished because of the factors beyond his control. The court *573 therefore applies the time is of the essence paragraph 16 to the provisions of paragraph 5 and rules that with respect to this comparison time was of the essence in so far as the plaintiffs herein were concerned. The court finds as a matter of fact that the defendant did not put forth his best efforts to complete the project within a reasonable time. The court finds there was a four-week period in the middle of the summer of 1966 in which no work was done and that the defendant did not have men or equipment on the job from September 1967 through December 1,1967. Letters from attorneys employed by the plaintiffs, four in number, from August 26, 1966, through December 1, 1967, pointed out to the defendant that the work was not progressing with sufficient speed, pointed out to the defendant that the contract provided that time was of the essence, and threatened action for nullification if work was not resumed. There is no indication in the evidence that the defendant heeded these warnings by putting forth a greater effort. There was evidence, however, that at this time the defendant was engaged in a similar project known as Lake Diane in this general area and was moving men and equipment back and forth between the jobs in an apparent effort to mollify all owners.

“The court finds that the plaintiffs have established by a great preponderance of the proofs that the defendant has not completed the sanding of the beaches along the shoreline, the grading of lots, roads and the surfacing of roads, and roads have not been completed to the specifications of the Hillsdale County Eoad Commission. The photographs received in evidence being plaintiffs’ exhibits #13 through #19, clearly illustrate the failure to sand beaches and the failure to remove stumps and debris from the waters’ edge and the photographs received into evidence being plaintiffs’ #9 through #11, #4 through #7, and #20 and #21, show that some of the planned roads have not even been *574 graded or cut to specifications. The testimony of Roy Rodd, a civil engineer, who is the head of the Hillsdale County Highway Department, was particularly telling on the point of the insufficiency of the roadways. It is clear that the roads as they exist will require a great deal of work before they are accepted by the County of Hillsdale for maintenance purposes. Under these circumstances it is most difficult to expect the sale of lots in this lakeshore subdivision.

“A flagrant violation of paragraph 10, plaintiffs’ exhibit #1 was shown by a preponderance of proof. 1 The defendant in his testimony equivocated with respect to the existence of this policy, but finally admitted that the policy issued to the defendant and payable to Cooper February 16, 1965, lapsed in May of 1968.”

On appeal, defendant alleges that the trial court erred by finding’ that the defendant had breached the contract. Defendant further contends that the trial court’s finding that rescission of the contract would result in defendant being returned to the status quo constituted error. We disagree.

Time was specifically made the essence of the contract entered into by the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
185 N.W.2d 604, 29 Mich. App. 569, 9 U.C.C. Rep. Serv. (West) 114, 1971 Mich. App. LEXIS 2001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cooper-v-klopfenstein-michctapp-1971.