Cooper Industries, Inc. v. Agway, Inc.

956 F. Supp. 240, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21018, 44 ERC (BNA) 1541, 1997 U.S. Dist. LEXIS 23435, 1997 WL 85341
CourtDistrict Court, N.D. New York
DecidedFebruary 27, 1997
Docket92-CV-0748
StatusPublished
Cited by1 cases

This text of 956 F. Supp. 240 (Cooper Industries, Inc. v. Agway, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cooper Industries, Inc. v. Agway, Inc., 956 F. Supp. 240, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21018, 44 ERC (BNA) 1541, 1997 U.S. Dist. LEXIS 23435, 1997 WL 85341 (N.D.N.Y. 1997).

Opinion

MEMORANDUM-DECISION & ORDER

McAVOY, Chief Judge.

I. BACKGROUND

The motion before the Court is brought by the above-referenced plaintiffs seeking summary judgment on the issue of liability as against the defendant Pall Trinity Micro Corporation (“PTM”) for response costs at the so-called Rosen superfund site. The defendant opposes the motion and has cross-moved for summary judgment in its favor.

This case is brought under the Comprehensive Environmental Response Compensation and Liability Act (“CERCLA”), 42 U.S.C. §§ 9601-9657. The facts of this case are well-known to the parties and the Court, and are set forth in the relevant sections of the decision of the Court below.

By way of an overview, the Court notes that the plaintiffs have and are currently paying the costs of removal and the costs of the remedial investigation at the Rosen Superfund Site, pursuant to a number of Administrative Orders on Consent issued by the EPA. The costs to date exceed $1.9 million.

In brief, the plaintiffs allege that PTM arranged for the removal of certain scrap metal and liquid waste from its facility directly and indirectly through Rosen Brothers. This relationship allegedly occurred intermittently during the nineteen seventies. The plaintiffs further allege that the Rosen Brothers dumped some or all of the waste removed from PTM at their “yard,” the so-called Rosen Site. Finally, the plaintiffs allege that the waste from PTM that was dumped at the Rosen Site caused the incur-rence of a portion of the response costs associated with the Rosen Site cleanup. On this basis the plaintiffs seek an order imposing CERCLA liability against the defendant PTM.

Briefly stated, in reply, the defendant argues that there is proof that PTM had a relationship with the Rosen Brothers for only six months in the early seventies. Moreover, the defendant alleges that at best small amounts of scrap metal were dumped at the Rosen Site. Finally, the defendant alleges that these small amounts of scrap metal could have contributed no more than back *242 ground levels to the Rosen Site environment. On this basis generally, the defendant argues that it should not be held liable for any response costs incurred in connection with the Rosen Site.

To establish liability under CERCLA, the plaintiffs must show that PTM is a responsible party as defined under CERCLA, that the Rosen site is a “facility” within the meaning of CERCLA, that hazardous substances were released at the Rosen site, that the plaintiffs have incurred response costs due to the release of hazardous substances at the Rosen site, and that the response costs are consistent with the National Contingency Plan. See B.F. Goodrich Co. v. Murtha, 958 F.2d 1192, 1198 (2d Cir.1992).

Pursuant to a Memorandum-Decision and Order of this Court, dated August 25,1995, it is established that: (1) the plaintiffs have incurred response costs due to the release of hazardous substances at the Rosen site; (2) the response costs are consistent with the National Contingency Plan; (3) the Rosen site is a “facility” within the meaning of CERCLA; and (4) hazardous substances were released at the Rosen site. Thus, the remaining issue to be determined with respect to PTM is whether it is a “responsible party.”

The plaintiffs have moved for summary judgment on the basis that the evidence conclusively shows (1) that PTM arranged for the disposal of its waste by the Rosen Brothers, the owners of the Rosen site, (2) that PTM waste actually was disposed of at the Rosen site, (3) that PTM’s waste contained CERCLA hazardous substances, and (4) that hazardous substances of the kind found in PTM’s waste were found at the site.

PTM responds by arguing that it, rather than the plaintiffs is entitled to summary judgment. The first arguments do not deal with the merits of a CERCLA claim. Rather, the defendant argues that the plaintiffs have failed to plead a claim for which relief can be granted, that CERCLA cannot be applied retroactively, and that CERCLA, as applied in this case, violates the Commerce Clause of the United States Constitution. Then, the defendant turns to the merits of the CERCLA claim allegedly asserted against it. PTM argues that the plaintiffs expert affidavit must be excluded, that the affidavits and testimony relied on by the plaintiffs is inadmissible on summary judgment, that the entire argument relied on by the plaintiffs is based on impermissible inferences, and that, with respect to manganese and copper from scrap metal at the Rosen site, PTM’s divisible share is zero.

The Court will address each of these arguments seriatim.

II. DISCUSSION

A. Motion to Dismiss for Failure to State a Claim, CERCLA Retroactivity, and CERCLA in Relation to the Commerce Clause

These issues were raised before the Court in the summary judgment motions relating to the defendant Mack Trucks, Inc. The Court subsequently heard oral argument and rendered a written decision. See Cooper v. Agway, 1996 WL 550128 (Sept. 23, 1996). The Court held that the plaintiffs’ Complaint was viable, that CERCLA applied retroactively, and that CERCLA did not violate the Commerce Clause.

“The law of the case doctrine ‘posits that when a Court decides upon a rule of law, that decision should continue to govern the same issues in subsequent stages in the same case.’” DiLaura v. Power Authority of N.Y., 982 F.2d 73, 76 (2d Cir.1992), quoting Liona Corp. v. PCH Assocs. (In Re PCH Assocs.), 949 F.2d 585, 592 (2d Cir.1991) (further citation omitted). As the issues listed above have previously been decided by this Court, they constitute the law of the case, and will not be revisited herein. The defendant PTM is referred to the Court’s reasoning in its September 23, 1996 Memorandum-Decision and Order for an extended discussion of these issues.

The defendant PTM’s motion to dismiss the Complaint on the aforementioned grounds is denied.

B. Standard For Summary Judgment

The standard for analyzing a summary judgment motion is well-settled. A motion *243 for summary judgment should be granted “if the pleadings ... together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). The movant bears the initial burden of showing the Court that, on the evidence before it, there is no genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 324, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seneca Meadows, Inc. v. ECI Liquidating, Inc.
121 F. Supp. 2d 248 (W.D. New York, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
956 F. Supp. 240, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21018, 44 ERC (BNA) 1541, 1997 U.S. Dist. LEXIS 23435, 1997 WL 85341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cooper-industries-inc-v-agway-inc-nynd-1997.