Cont'l Heller Corp. v. Amtech Mech. Servs., Inc.

53 Cal. App. 2d 500
CourtCalifornia Court of Appeal
DecidedFebruary 18, 1997
DocketNo. B081741
StatusPublished

This text of 53 Cal. App. 2d 500 (Cont'l Heller Corp. v. Amtech Mech. Servs., Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cont'l Heller Corp. v. Amtech Mech. Servs., Inc., 53 Cal. App. 2d 500 (Cal. Ct. App. 1997).

Opinion

[503]*503Opinion

JOHNSON, J.

In this case, we hold an agreement by a subcontractor to indemnify a general contractor for loss “which arises out of or is in any way connected” with the subcontractor’s “acts or omissions” in the performance of its work does not require a showing the subcontractor was at fault in causing the general contractor’s loss or that its performance was a “substantial” or “predominating” cause of the loss. We also concur in the trial court’s finding the subcontractor is liable to the contractor for its attorney fees in prosecuting this action to recover under the agreement.

Facts and Proceedings Below

In 1978, Oscar Meyer hired the Continental Heller Corporation (Continental) as its general contractor on a project to expand a meat packing plant. Continental subcontracted with the Ralph Manns Company for the installation of an ammonia refrigeration system in the expanded plant. While Manns was working on the refrigeration system, it was acquired by Amtech Mechanical Services, Inc. (Amtech), which assumed the assets and liabilities of Manns including the subcontract with Continental.

In 1989, an explosion occurred at the plant causing property damage and injuring several Oscar Meyer employees. The explosion was caused by the failure of a valve manufactured by the Wolfe-Linde Company and installed by Amtech in the course of its work on the refrigeration system.

Numerous complaints and cross-complaints followed the explosion. Continental tendered defense of the claims against it to Amtech pursuant to an indemnity agreement contained in the subcontract. Amtech declined to accept the tender of defense. Continental then settled the claims against it for $20,000 and brought this action against Amtech for contractual indemnity seeking to recover the $20,000 settlement plus its costs and attorney fees in defending the claims against it and in prosecuting this action.

Based on the language of the indemnity agreement, which we discuss in detail below, the trial court concluded Continental was entitled to the full recovery it sought from Amtech. The court specifically found Amtech was not negligent in installing the valve and Amtech did not “proximately cause” the leak and subsequent explosion. However, the court concluded, under the indemnity agreement between the parties it was not necessary for Continental to prove fault or a causal connection between the work performed by Amtech and the subsequent leak and explosion in order to establish a duty on the part of Amtech to defend and indemnify Continental. The court awarded [504]*504Continental the $20,000 it paid in good faith settlement of the claims against it plus approximately $80,000 in costs for defending those claims and $12,000 for attorney fees and costs incurred in prosecuting this action for indemnity.

On appeal, Amtech argues to trigger its duty to indemnify Continental there must have been a “failure of performance in the work” it undertook and this failure of performance must have been a “substantial factor” or “predominating cause” of the loss. Alternatively, it argues Continental was not entitled to attorney fees incurred in prosecuting this action.

For the reasons explained below, we reject both arguments.

Discussion

I. Continental’s Losses Are Within the Scope of Indemnity Defined in the Contract.

A. The Standard of Review

The parties agree that where, as here, the trial court construed the indemnity provision at issue without the aid of extrinsic evidence the interpretation of this provision is a question of law subject to our de novo review. (Four Star Electric, Inc. v. F &H Construction (1992) 7 Cal.App.4th 1375, 1380 [10 Cal.Rptr.2d 1].)

B. The Scope of Indemnity Under the Contract

Indemnity agreements are construed under the same rules which govern the interpretation of other contracts. (Myers Building Industries, Ltd. v. Interface Technology, Inc. (1993) 13 Cal.App.4th 949, 969 [17 Cal.Rptr.2d 242].) Accordingly, the contract must be interpreted so as to give effect to the mutual intention of the parties. (Civ. Code, § 1636.) The intention of the parties is to be ascertained from the “clear and explicit” language of the contract. (Civ. Code, §§ 1638-1639.) And, unless given some special meaning by the parties, the words of a contract are to be understood in their “ordinary and popular sense.” (Civ. Code, § 1644.)

“In interpreting an express indemnity agreement, the courts look first to the words of the contract to determine the intended scope of the indemnity agreement.” (Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal.App.3d 1724, 1737 [286 Cal.Rptr. 435].) The indemnity agreement between Continental and Amtech requires Amtech to indemnify [505]*505Continental for a loss which “arises out of or is in any way connected with the performance of work under this Subcontract.”1 The contract further provides Amtech’s liability for indemnity “shall apply to any acts or omissions, willful misconduct or negligent conduct, whether active or passive, on the part of Subcontractor.” (Italics added.) Amtech does not deny its installation of the valve in the refrigeration plant was “an act” carried out in “the performance of work under [the] Subcontract.” Nor does it deny the loss suffered by Continental was “in any way connected” with that act. Therefore, under the contract as written, Continental is entitled to indemnity from Amtech for its losses.

There is no merit to Amtech’s contention every cause of action for indemnity requires a showing of fault on the part of the indemnitor. On the contrary, courts will enforce indemnity agreements even for losses caused by acts over which the indemnitor had no control. (See Vinnell Co. v. Pacific Elec. Ry. Co. (1959) 52 Cal.2d 411, 416 [340 P.2d 604].) To the extent the case relied on by Amtech, Gouvis Engineering v. Superior Court (1995) 37 Cal.App.4th 642, 647-648 [43 Cal.Rptr.2d 785], suggests fault is an element of every cause of action for indemnity, the statement is pure dictum and taken out of context. In the present case, Continental’s entitlement to indemnity does not depend on a showing Amtech was at fault in performing its work on the refrigeration system. Rather, Amtech’s duty to indemnify Continental applies “to any acts or omissions ... on the part of [Amtech]” not just to its “willful misconduct or negligent conduct.” The language of the agreement leaves no doubt the parties intended Amtech should indemnify Continental irrespective of whether Continental’s loss arose by reason of Amtech’s negligence or for any other reason except for the sole negligence or willful misconduct of Continental. (See Civ. Code, § 2782.)

Nor has Amtech convinced us we should construe the indemnity agreement to require proof Amtech’s performance was a “substantial factor” or “predominating cause” of Continental’s loss in contravention of the agreement’s express language providing indemnity for loss which “arises out of or is in any way connected” with Amtech’s performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rossmoor Sanitation, Inc. v. Pylon, Inc.
532 P.2d 97 (California Supreme Court, 1975)
Pacific Gas & Electric Co. v. G. W. Thomas Drayage & Rigging Co.
442 P.2d 641 (California Supreme Court, 1968)
Jones v. Strom Construction Co.
527 P.2d 1115 (Washington Supreme Court, 1974)
Vinnell Co. v. Pacific Electric Railway Co.
340 P.2d 604 (California Supreme Court, 1959)
Robert & Co. Associates v. Pinkerton & Laws Co.
169 S.E.2d 360 (Court of Appeals of Georgia, 1969)
Graver Tank & Manufacturing Co. v. Fluor Corp., Ltd.
421 P.2d 909 (Court of Appeals of Arizona, 1966)
E. L. White, Inc. v. City of Huntington Beach
579 P.2d 505 (California Supreme Court, 1978)
Perkins v. Rubicon, Inc.
563 So. 2d 258 (Supreme Court of Louisiana, 1990)
Hillman v. Leland E. Burns, Inc.
209 Cal. App. 3d 860 (California Court of Appeal, 1989)
Appalachian Insurance v. McDonnell Douglas Corp.
214 Cal. App. 3d 1 (California Court of Appeal, 1989)
Meininger v. Larwin-Northern California, Inc.
63 Cal. App. 3d 82 (California Court of Appeal, 1976)
County of San Joaquin v. Stockton Swim Club
42 Cal. App. 3d 968 (California Court of Appeal, 1974)
Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co.
234 Cal. App. 3d 1724 (California Court of Appeal, 1991)
John E. Branagh & Sons v. Witcosky
242 Cal. App. 2d 835 (California Court of Appeal, 1966)
Indenco, Inc. v. Evans
201 Cal. App. 2d 369 (California Court of Appeal, 1962)
Four Star Electric, Inc. v. F & H CONSTRUCTION
7 Cal. App. 4th 1375 (California Court of Appeal, 1992)
Rowe v. Farmers Insurance Exchange
7 Cal. App. 4th 964 (California Court of Appeal, 1992)
Myers Building Industries, Ltd. v. Interface Technology, Inc.
13 Cal. App. 4th 949 (California Court of Appeal, 1993)
Otis Elevator Co. v. TODA CONSTRUCTION OF CA.
27 Cal. App. 4th 559 (California Court of Appeal, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
53 Cal. App. 2d 500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contl-heller-corp-v-amtech-mech-servs-inc-calctapp-1997.