Continental Cablevision of Ohio, Inc. v. American Electric Power Company

715 F.2d 1115, 54 Rad. Reg. 2d (P & F) 747
CourtCourt of Appeals for the Sixth Circuit
DecidedSeptember 2, 1983
Docket81-3650
StatusPublished
Cited by24 cases

This text of 715 F.2d 1115 (Continental Cablevision of Ohio, Inc. v. American Electric Power Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Cablevision of Ohio, Inc. v. American Electric Power Company, 715 F.2d 1115, 54 Rad. Reg. 2d (P & F) 747 (6th Cir. 1983).

Opinion

PHILLIPS, Senior Circuit Judge.

Plaintiffs, several cable television (CATV) operators and an association of such operators in Ohio (Continental Cablevision), brought this antitrust action against American Electric Power Company (AEP) and its wholly owned subsidiary, Ohio Power Company, seeking treble damages and injunctive relief. Plaintiffs alleged that defendants conspired together and with other Ohio electric and telephone companies to fix rates for pole attachment rentals in violation of § 1 of the Sherman Act and abused their naturally acquired monopoly power by establishing and maintaining unreasonable rates in violation of § 2 of the Act. Defendants denied any liability and filed a counterclaim alleging a group boycott among several CATV companies in violation of § 1 of the Sherman Act and a pendent state-law counterclaim for pole attachment rentals due from those CATV companies that attached cables to Ohio Power’s poles but refused to pay the increased rate.

Following an extensive trial, District Judge Robert M. Duncan entered a comprehensive opinion addressing each argument made on behalf of the parties. Judge Duncan concluded that plaintiffs failed to prove that defendants engaged in an unlawful price-fixing conspiracy or otherwise abused their monopoly power. With respect to defendants’ counterclaim, the court held that the conduct of the CATV companies did not amount to a group boycott. In a separate Memorandum Order, Judge Duncan ruled that Ohio Power was entitled to recover on its pendent counterclaim for pole attachment rentals.

This appeal ensued with plaintiffs claiming that the district court erred as a matter of law in finding defendants did not violate §§ 1 & 2 of the Sherman Act in establishing and maintaining pole attachment rates. Pursuant to Rule 34(f) of the Federal Rules of Appellate Procedure the parties waived oral argument and the case was submitted on briefs. We affirm.

I.

A CATV system is a facility capable of receiving television and other broadcast signals from distant locations and distributing those signals to subscribers by means of an interconnected network of transmission cables. To provide its service, a CATV company must have a means of getting the cables into the homes of subscribers. Traditionally, CATV companies have used existing utility poles, owned by electric and telephone companies, as the distribution network for their cables. Although it is possible for a CATV company to place cables underground or construct its own set of poles, such alternatives are costly and impractical. Consequently, since electric and telephone companies often share their utility poles with each other, in any given locale there generally is only one set of utility poles and only one pole owner with which to negotiate.

Since 1951 defendants have permitted CATV operators to attach their cables to utility poles on a nondiscriminatory basis. As a condition, CATV operators are required to sign and abide by the terms and conditions of the standard CATV pole attachment agreement drafted by AEP’s service company. 1 The terms of the standard *1117 agreement provide that CATV operators are to assume all out-of-pocket expenses attributable to the attachment of their equipment to defendants’ poles. The agreement provides further that CATV companies are to pay an annual rental fee per pole. The establishment and maintenance of the attachment rate is the subject of the present litigation.

Prior to February 1965, defendants imposed an annual pole attachment rate of $2.00 per pole. Subsequently, the service company increased the rate to $4.00 per pole, per annum. „ Apparently, this increase was a result of AEP following the then prevailing attachment rate charged by several telephone companies. For approximately ten years, the $4.00 rate remained in effect. Thereafter, in 1975, defendants imposed the present annual rate of $5.60 per pole.

Plans for an increased attachment rate surfaced in 1974, when the AEP network began experiencing severe economic problems due mainly to the inability of the operating companies to secure timely electric rate increases. The service company assigned to Donald Ruff, operating manager of transmission and distribution, the task of formulating and recommending an appropriate rate increase.

In performing this task, Ruff attended a national trade association conference and conferred with representatives of other utility companies. In determining whether defendants’ rates were within the “ballpark,” Ruff discovered that cable attachment rates varied from $1.00 to $9.00 per contract, with some companies anticipating increases. In January 1975, Ruff attended a meeting held by the executive vice presidents from AEP’s operating companies. At the meeting, Ruff recommended that a CATV attachment rate of $7.00-$7.20 be adopted. As noted by the district court, Ruff apparently arrived at this figure by using cost data obtained from various operating companies and an inflation factor. However, the operating companies rejected Ruff’s proposed rate and, in turn, opted for the present annual rate of $5.60 per pole. The operating companies found the $7.00 rate “too much” and that the $5.60 rate was a reasonable figure.

Subsequent to the establishment of the $5.60 rate, defendants and other utility companies frequently exchanged information relating to the rates, terms and conditions governing CATV pole attachments. Indeed, there is no dispute that defendant Ohio Power made available its current attachment rate and that other Ohio utilities were familiar with CATV agreements used by various utility companies. The information took various forms and was disseminated in a variety of ways, including telephone conversations, letters, surveys, questionnaires and discussions at national and regional trade association conventions. The information focused primarily on existing pole attachment rates and proposed increases. Sometimes the information was general in nature and at other times, quite specific. There is little doubt that the information was helpful to those utilities being approached by CATV operators seeking attachment agreements.

Perceiving the pole attachment rates as unreasonable, and unable to secure any justification for the increase, plaintiffs filed this antitrust action against AEP and Ohio Power. Plaintiffs contend that the exchange of rate information among defendants and other utilities amounted to a conspiracy to fix pole attachment rates in violation of § 1 of the Sherman Act. The CATV companies argue also that § 2 of the Act was violated by. defendants abusing their naturally acquired monopoly power in imposing unreasonable pole attachment rates.

II.

Section 1 of the Sherman Act proscribes every contract, combination or con *1118 spiracy in restraint of trade or commerce. 15 U.S.C. § 1. To sustain a § 1 claim, plaintiffs must prove by a preponderance of the evidence two essential elements:

(1) That defendants entered into a contract, combination or conspiracy; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Polyurethane Foam Antitrust Litigation
152 F. Supp. 3d 968 (N.D. Ohio, 2015)
In Re RAIL FREIGHT FUEL SURCHARGE ANTITRUST LITIGATION
287 F.R.D. 1 (District of Columbia, 2012)
Cason-Merenda v. Detroit Medical Center
862 F. Supp. 2d 603 (E.D. Michigan, 2012)
Martin McNulty v.
Sixth Circuit, 2010
In Re McNulty
597 F.3d 344 (Sixth Circuit, 2010)
Churchill Downs Inc. v. Thoroughbred Horsemen's Group, LLC
605 F. Supp. 2d 870 (W.D. Kentucky, 2009)
United States v. David P. True
250 F.3d 410 (Sixth Circuit, 2001)
Re/Max International v. Realty One, Inc.
900 F. Supp. 132 (N.D. Ohio, 1995)
United States v. General Electric Co.
869 F. Supp. 1285 (S.D. Ohio, 1994)
Davis v. Southern Bell Telephone & Telegraph Co.
755 F. Supp. 1532 (S.D. Florida, 1991)
General Aviation, Inc. v. Garrett Corp.
743 F. Supp. 515 (W.D. Michigan, 1990)
Stephen Jay Photography, Ltd. v. Olan Mills, Inc.
713 F. Supp. 937 (E.D. Virginia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
715 F.2d 1115, 54 Rad. Reg. 2d (P & F) 747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-cablevision-of-ohio-inc-v-american-electric-power-company-ca6-1983.