Contech Engineered Solutions, LLC v. Apptech Solutions, LLC

CourtDistrict Court, W.D. Virginia
DecidedApril 6, 2020
Docket7:19-cv-00762
StatusUnknown

This text of Contech Engineered Solutions, LLC v. Apptech Solutions, LLC (Contech Engineered Solutions, LLC v. Apptech Solutions, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contech Engineered Solutions, LLC v. Apptech Solutions, LLC, (W.D. Va. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA ROANOKE DIVISION

CONTECH ENGINEERED SOLUTIONS, LLC, ) an Ohio Limited Liability Company, ) ) Plaintiff, ) ) Civil Action No.: 7:19-cv-00762 v. ) ) APPTECH SOLUTIONS, LLC, f/k/a Appalachian ) Technology Solutions, LLC, ACS DESIGN, LLC, ) DANIEL EARLY, and SCOTT EASTER, ) ) Defendants. )

MEMORANDUM OPINION AND ORDER

This is a diversity action1 brought by Contech Engineered Solutions, LLC (Contech) for breach of contract, indemnification, and engineering and design malpractice arising out of the design and construction of wastewater treatment projects in Mora, New Mexico, and Gloucester, Virginia. ACS Design, LLC (ACS Design), David Early, and Scott Easter move to dismiss Contech’s claim for common law indemnification. For the reasons stated below, this motion will be denied. I. BACKGROUND2

Contech is a company that provides site solutions for the construction and development of industry. ACS Design is a water and wastewater engineering firm. Early is the sole current member of ACS Design and Apptech Solutions, LLC (Apptech). Easter is a former member of ACS Design and Apptech. Contech also sues Apptech, a water and wastewater manufacturing and

1 The court may exercise subject matter jurisdiction over this matter because the parties are completely diverse and the amount in controversy exceeds $75,000. 28 U.S.C. § 1332(a)(1); (see Dkt. Nos. 3–6.) 2 The following factual background is taken from the allegations in the amended complaint, which are presumed to be true for purposes of this motions. engineering solutions provider to the civil engineering industry. Apptech has not made an appearance in this case. In 2011, the parties entered into a series of written agreements regarding the licensing, design, marketing, and sales of certain products for the wastewater treatment market: a License Agreement, a Design Services Agreement, and a Marketing Agreement. In 2014, defendants in this action sued Contech, alleging that Contech was not performing under these agreements. See Case No. 7:14-cv-00568-EKD-RSB. On September 21, 2015, the parties executed an Amended

Settlement Agreement and Limited Releases (Settlement Agreement) to resolve the litigation. Contech also preserved claims and rights of action it may have against ACS Design, Apptech, Early, and/or Easter arising out of or related to engineering, design, or other services they provided concerning projects listed on “Schedule A” of the Settlement Agreement. The Mora Project in Mora, New Mexico, and the Waterview Project in Gloucester, Virginia, are identified on Schedule A. According to the Settlement Agreement, defendants agreed to cooperate with Contech by providing engineering and related services at no cost to Contech for the projects listed on Schedule A. A. The Mora Project The Mora Project was initiated by a Design Build Project Scope and Request for Proposal

for a 60,000 gallon per day wastewater treatment plant. Mora hired Energy Independence Partners (EIP) as the general contractor. On March 12, 2014, EIP issued a proposal to Mora in the amount of $1,697,250, which identified EIP, ACS Design, and RMCI, Inc. as the design/build team and engineers for the Mora Project. Contech was hired to fabricate and deliver the wastewater treatment system. One or more of the defendants continued to revise the design for the Mora Project after Contech’s fabrication of the treatment system; the revisions continued until at least November 7, 2016. A series of design and engineering errors by defendants resulted in a poorly designed facility requiring numerous design revisions and significant additional work by defendants. EIP abandoned the project and is effectively dissolved. Mora turned to Contech and the defendants for assistance in addressing the design and engineering issues. Defendants attempted to revise the design for the Mora Project to address its flaws, and defendants represented that their recommended modifications to the treatment system would allow Mora to meet the expected effluent parameters, but they did not. Apptech and ACS Design were experiencing their own financial troubles in early 2016 and could not afford to implement these

costly modifications. After a certain time, defendants became unresponsive to requests by Contech regarding corrections to the design. Contech agreed to pay the upfront cost for the required modifications. In exchange, Contech reserved all rights against defendants for reimbursement or recovery of all costs incurred because of the design issues. Defendants were also responsible for project management, contracting, implementation and costs associated with other parts of the Mora Project, including but not limited to the lagoon cleanout, relining, and load banks for the emergency backup power generator. Contech completed the additional required work and turned the project over to the owner in March of 2019. To date, Contech has paid approximately $536,898 for the costs associated with the faulty design.

B. The Waterview Project The owners of the Waterview Mobile Home Park hired a company called Sydnor Hydro to install and operate an 18,400 gallon per day wastewater treatment plant. One or more of the defendants was the engineer who designed the wastewater system for the Waterview Project. One or more of the defendants also designed and manufactured the control building for the project. Contech was hired to fabricate and deliver the wastewater treatment system designed by the defendants. Defendants continued to revise the design for the Waterview Project after Contech’s fabrication of the system until 2018. Several design issues and engineering errors resulted in a poorly designed facility requiring numerous design revisions and significant additional work by defendants. Defendants revised the design to address these flaws, falsely representing that the modifications would allow for the Waterview Project to meet the required effluent parameters. Eventually, due to ongoing financial problems, defendants became unresponsive to requests by Sydnor Hydro and Contech regarding corrections to the design. Contech was required to pay for the cost of the required modifications, and it reserved its

rights against defendants for reimbursement. Contech completed work on the Waterview Project in April of 2019. Contech has paid approximately $544,115 for the costs associated with defendants’ faulty design on the Waterview Project. C. Contech’s Claims Contech alleges claims for engineering and design malpractice, negligence, breach of the Settlement Agreement, contractual indemnification, and common law indemnification. Contech seeks damages of no less than $1,081,013. II. ANALYSIS “To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678

(2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). In other words, the plaintiff must plead facts that “allow the court to draw the reasonable inference that the defendant is liable” and must demonstrate “more than a sheer possibility that a defendant has acted unlawfully.” Iqbal, 556 U.S. at 678. When ruling on a motion to dismiss, a court must accept the complaint’s factual allegations as true. Id. Defendants move to dismiss count five, Contech’s claim for common law indemnification. They argue that under Virginia (and Ohio) law,3 no duty of indemnity can be implied when there is an express contractual provision for indemnity between the parties. See Fidelity & Deposit Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Dacotah Marketing & Research, L.L.C. v. Versatility, Inc.
21 F. Supp. 2d 570 (E.D. Virginia, 1998)
Collier v. Land & Sea Restaurant Co.
972 F. Supp. 2d 870 (W.D. Virginia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Contech Engineered Solutions, LLC v. Apptech Solutions, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contech-engineered-solutions-llc-v-apptech-solutions-llc-vawd-2020.