Construction Services, Inc. of Duluth v. Town of Alborn

Court of Appeals of Minnesota·Decided April 27, 2015·No. A14-977·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A14-0977

Construction Services, Inc. of Duluth, Appellant,

vs.

Town of Alborn,

Respondent.

Filed April 27, 2015

Affirmed

Reyes, Judge

St. Louis County District Court File No. 69DUCV132351

William D. Paul, William Paul Law Office, Duluth, Minnesota (for appellant)

Daniel R. Gregerson, Margaret L. Evavold, Gregerson, Rosow, Johnson & Nilan, Ltd., Minneapolis, Minnesota (for respondent)

Considered and decided by Hudson, Presiding Judge; Bjorkman, Judge; and Reyes, Judge.

UNPUBLISHED OPINION

REYES, Judge Appellant Construction Services, Inc. of Duluth challenges a district court’s summary judgment in favor of respondent Town of Alborn. Appellant seeks to collect funds it claims it is entitled to under the parties’ construction contract arguing that (1) it did not materially breach the parties’ contract; (2) respondent breached the contract by

failing to timely pay a draw request; and (3) respondent failed to follow the contract’s termination procedure. We affirm.

FACTS

On April 30, 2008, the parties entered into a contract for the construction of a wastewater-treatment facility. The contract price for the project was $509,610. Pursuant to Minnesota law and article 5 of the contract, appellant entered into an indemnity agreement (indemnity agreement) with performance and payment bonds from a surety (performance bond), North American Specialty Insurance Company (NAS). See Minn. Stat. § 574.26, subd. 2 (2014) (requiring contractors to obtain performance and payment bonds for public-works projects). Appellant agreed to indemnify NAS for any losses NAS might suffer as a result of issuing bonds for appellant.

The contract originally called for work to be substantially completed by November 30, 2008. However, unexpected weather conditions caused delays, and the parties mutually agreed to extend the substantial completion date to June 30, 2009.

On June 9, 2009, the project’s engineer, Ayres Associates (Ayres), informed appellant that appellant was unlikely to achieve substantial progress by the June 30 deadline. Ayres did not issue a certificate of substantial completion until July 15, 2009. Attached to the certificate was a punch list of 265 items that, by the terms of the contract, were required to be fixed or completed by appellant within 30 days. They were not completed on time. On August 15, 2009, respondent’s town board, along with Ayres, met with appellant to discuss outstanding punch-list items and a possible date for the

project’s final completion. Appellant could not provide a final completion date at that time.

On August 26, 2009, appellant submitted an application for the project’s sixth progress payment in the amount of $151,001. The terms of the contract require appellant to submit an application for payment to Ayres to receive a progress payment. Ayres would then review the application and either make a written recommendation for payment to respondent, or return the application to appellant with reasons why it was refusing to recommend payment. If a payment application was returned, appellant was to correct and resubmit the application. Payment would then be due 20 days after respondent received a payment application with Ayres’s recommendation.

On September 10, 2009, respondent sent a letter to NAS and appellant notifying them that it was considering declaring appellant to be in default after its failure to timely complete its work.

On September 15, 2009, Ayres sent a memorandum to appellant informing them that the amount approved on their August 26 application for the sixth progress payment was reduced to $117,253. Ayres sent a follow-up memorandum on September 18, 2009, which further reduced the approved payment price to $105,121.49. Appellant did not resubmit a payment application and was unresponsive to Ayres’s letters.

In accordance with the performance bond, the parties held a conference on September 18, 2009. At that time, appellant agreed to complete the remaining punch-list items within one week of September 21, 2009. On October 2, 2009, the punch-list items were still incomplete and respondent sent another letter to appellant proposing that they

would not declare appellant to be in default if appellant agreed to pay for the additional engineering and legal fees incurred as a result of the delay. In addition to the delay, appellant failed to pay its subcontractors, resulting in mechanic’s liens on the property, and appellant failed to complete closeout and warranty work as required by the contract. Finally, on July 13, 2010, after a number of subsequent communications, conferences, and failed mediation sessions, respondent terminated the contract pursuant to the terms of the indemnity agreement. Following the termination procedures of the performance bond, respondent notified appellant and NAS that it was declaring appellant to be in default.

NAS filed suit against appellant to recoup losses that it incurred as a result of acting as a surety for appellant and, in July 2011, was awarded default judgment against appellant for $69,241.17. In September 2011, NAS sought to recover from respondent any remaining contract funds due to appellant as a secured creditor pursuant to the indemnity agreement. In March 2012, respondent paid NAS $4,928.37 in net contract funds in accordance with NAS’s assertion of its right under the indemnity agreement. In September 2013, appellant filed this lawsuit against respondent seeking to recover funds it believes it was owed under the contract.1 Both parties filed motions for summary judgment, and a motion hearing took place on March 11, 2014. The district court denied appellant’s summary judgment motion, granted respondent’s motion, and summary

1 Appellant asserted four causes of action: (1) breach of contract; (2) unjust enrichment; (3) quantum merit; and (4) failure to promptly pay. On appeal, appellant only argues that it was entitled to summary judgment on its breach-of-contract theory and has accordingly waived its other claims. See Melina v. Chaplin, 327 N.W.2d 19, 20 (Minn. 1982) (stating that issues not briefed on appeal are waived).

judgment was entered. The district court concluded that appellant’s assignment of its rights to NAS barred the relief it sought from respondent. This appeal follows.

DECISION

“Summary judgment is appropriate when the evidence, viewed in the light most favorable to the nonmoving party, establishes that no genuine issue of material fact exists and that the moving party is entitled to judgment as a matter of law.” Citizens State Bank Norwood Young Am. v. Brown, 849 N.W.2d 55, 61 (Minn. 2014); see also Minn. R. Civ. P. 56.03. “No genuine issue of material fact exists when the record taken as a whole could not lead a rational trier of fact to find for the nonmoving party.” Frieler v. Carlson Mktg. Grp., Inc., 751 N.W.2d 558, 564 (Minn. 2008) (quotations omitted). A district court’s grant of summary judgment is reviewed de novo. Dukowitz v. Hannon Sec. Servs., 841 N.W.2d 147, 150 (Minn. 2014).

The district court concluded that summary judgment in favor of respondent was appropriate because appellant had assigned any right to recovery to NAS in the event of default. To determine whether the award of summary judgment was made in error, we must decide if there is a genuine issue of material fact as to whether appellant defaulted on the contract such that appellant’s indemnity agreement with NAS was triggered. “The plain and ordinary meaning of the contract language controls, unless the language is ambiguous.” Bus. Bank v. Hanson, 769 N.W.2d 285, 288 (Minn. 2009). The indemnity agreement between appellant and NAS provides that appellant agrees to

assign, transfer, pledge and convey to [NAS] (effective as of the date of each such bond, but only in the event of default, breach or failure as referred to in preceding Section 4(c))

Free access — add to your briefcase to read the full text and ask questions with AI

Construction Services, Inc. of Duluth v. Town of Alborn, (Mich. Ct. App. 2015).

Construction Services, Inc. of Duluth v. Town of Alborn (Construction Services, Inc. of Duluth v. Town of Alborn) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Valspar Refinish, Inc. v. Gaylord's, Inc.
764 N.W.2d 359 (Supreme Court of Minnesota, 2009)
Anderson v. State, Department of Natural Resources
693 N.W.2d 181 (Supreme Court of Minnesota, 2005)
Melina v. Chaplin
327 N.W.2d 19 (Supreme Court of Minnesota, 1982)
Frieler v. Carlson Marketing Group, Inc.
751 N.W.2d 558 (Supreme Court of Minnesota, 2008)
Business Bank v. Hanson
769 N.W.2d 285 (Supreme Court of Minnesota, 2009)
Minnwest Bank Central v. Flagship Properties LLC
689 N.W.2d 295 (Court of Appeals of Minnesota, 2004)
Schoepke v. Alexander Smith & Sons Carpet Co.
187 N.W.2d 133 (Supreme Court of Minnesota, 1971)
Citizens State Bank Norwood Young America v. Gordon Brown
849 N.W.2d 55 (Supreme Court of Minnesota, 2014)
Bob Acres, LLC v. Schumacher Farms, LLC
797 N.W.2d 723 (Court of Appeals of Minnesota, 2011)
Dukowitz v. Hannon Security Services
841 N.W.2d 147 (Supreme Court of Minnesota, 2014)