Construction Services in Samoa Inc. v. American Samoa Government

10 Am. Samoa 3d 315
CourtHigh Court of American Samoa
DecidedNovember 23, 2005
DocketCA No. 41-03
StatusPublished

This text of 10 Am. Samoa 3d 315 (Construction Services in Samoa Inc. v. American Samoa Government) is published on Counsel Stack Legal Research, covering High Court of American Samoa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction Services in Samoa Inc. v. American Samoa Government, 10 Am. Samoa 3d 315 (amsamoa 2005).

Opinion

OPINION AND ORDER

Introduction

On March 16, 2001, plaintiff Construction Services In Samoa ("CSS") entered into a construction contract with defendant American Samoa Government, Department of Port Administration ("ASG"). In short, the contract required CSS to complete the third and final phase ("Phase III") of a dock rehabilitation project ("the project") in the Pago Pago Harbor.1 Although Phase III involved erecting a small guardhouse, a fence, and some drainage causeways, the vast majority of work (roughly 70-80%) involved pouring and finishing a concrete dock in the Pago Pago port.

The contract provided that all work would be "substantially completed" 335 calendar days from the date ASG issued CSS a Notice to Proceed. The contract also stated that the "[cjontractor shall be considered in default. . . and default shall be considered as cause for termination" if, among other things, CSS: 1) "failed to perform the work ... in accordance with the terms of the contract" or 2), "failed "to carry on the work in an acceptable manner."

The Notice to Proceed, which started the clock running on CSS's time to complete the contract, was issued on May 7, 2001. Shortly thereafter, CSS began to fall seriously behind schedule. According to weekly site meeting minutes, on July 21, 2001, some 77 days into the contract, CSS [317]*317had completed exactly 5% of the total work required by the contract. By August 23, 2001, one-third of the time allotted to finish the project had elapsed; CSS had completed only 6% of the total work. On January 31, 2002, ASG issued a notice stating its intent to terminate the contract for failure to perform the work. At that time CSS had completed just 8% percent of the total contract work, while approximately 77% of the allocated time to complete Phase III had elapsed.

There is no hiding the fact that as of the termination date, CSS was seriously, if not fatally, behind schedule.2 The alleged reasons for the delay, however, form the backbone of this dispute. CSS argues that defects in the project plans caused unneeded delay, and further that Defendant exhibited a lack of good faith in carrying out the agreement.

Briefly on the design flaw issue, CSS claims that the project plans were defective; namely, that the concrete-which amounted to approximately 75% of the total work — would crack after it was poured under the current design.3 CSS argues that because the concrete associated with Phase II showed considerable cracking, and because the concrete specifications for Phases II and III were the same, then the Phase HI concrete would likely crack if they poured the concrete according to the existing plans.4 They argue, without any citation to legal authority, that because Defendant issued them defective plans, Defendant breached the implied warranty of adequacy of plans and specifications, thus entitling CSS to contract damages.

After discovering the alleged design flaw, CSS sent a series of Request for Information ("RFI") letters to GMP & Associates, Inc. ("GMP"), an engineering group who ASG authorized to act in its shoes as project manager. The first RFI on the design defect issue, drafted and sent in late September 2001, asked GMP or the project designer to clarify the alleged concrete defect issue before CSS continued work. Given that CSS was already seriously behind schedule, GMP responded by telling CSS to continue the work despite the alleged design flaw. Although the contract terms expressly provide that the contractor is not liable for [318]*318design defects, CSS requested indemnification for any defects in the concrete resulting from the allegedly defective design.5 On October 31, 2001, GMP acquiesced and indemnified CSS for any concrete cracking or concrete failure associated with the Phase III project. After issuing the indemnification, GMP told CSS to get to work. Instead, CSS requested indemnity directly from ASG, arguing that GMP lacked the authority to authorize indemnity on its own.6

Throughout this dialogue, CSS made no significant progress on the dock project. Accordingly, on December 10, 2001, GMP sent a letter to CSS expressing its intent to terminate the contract based on CSS's failure to perform the work in a timely or otherwise acceptable manner. CSS responded five days later arguing that much of the delay was rooted in GMP's refusal to clarify the design defect issue. The parties' positions remained virtually unchanged over the next two months, and on February 5,2002, ASG formally terminated the contract.

With respect to the good faith issue, CSS maintains that ASG and its representatives dragged their feet in approving materials and responding to CSS's RFI's. CSS argues that the contract required ASG to approve materials before CSS could order them from suppliers. CSS contends that since ASG did not approve materials — particularly the concrete — in a timely manner, then CSS could not order the materials.7 Because CSS did not have materials, they could not perform any work on the project.

For its part, ASG contests each of the reasons and submits that CSS's failure to timely perform the contract had nothing to do with ASG's actions or inaction. First, regarding the design defect issue, ASG maintains that under both accepted law and the contract's own terms, CSS would not have been liable for construction defects caused by a defective design. Because neither the contract nor case law requires CSS to indemnify ASG for design defects, CSS's concerns over its own [319]*319liability were unfounded. Thus, CSS should have continued working, especially after GMP clarified the issue. Moreover, ASG maintains that even if CSS was originally liable under the contract (which it clearly was not under the contract's express terms) for design defects, GMP relieved them of liability by indemnifying CSS in October 2001. Regardless, ASG maintains that CSS cannot unilaterally cease work on the project and still recover the contract price.

With respect to the good faith issue, ASG argues that any alleged failure to approve material submittals or respond to RFI's is simply untrue and does not excuse CSS's inability to perform. Regarding the RFIs, ASG maintains that it responded quickly, first telling CSS not to worry about the design issue and then indemnifying CSS from liability. Thus, ASG contends it timely addressed CSS's concerns. As to the material submittals, ASG points out that while concrete comprised 74% of the total contract work, CSS did not even make a concrete submittal until late October 2001, or more than five months after ASG issued the Notice to Proceed. Accordingly, ASG argues, whatever delay CSS faced in obtaining the concrete and beginning the concrete work was not caused by ASG's failure to approve the submittals.8 In sum, ASG maintains that it timely responded to CSS's material submittals and RFI's, and therefore did not breach its duty to act in good faith.

Discussion

CSS raised two issues at trial: first, whether ASG breached "the implied warranty of adequacy of plans and specifications," and second, whether [320]*320ASG breached its duty to deal with CSS in good faith. If ASG breached neither duty, then CSS's claims fail.

I. The Implied Warranty Claim

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Pancoast v. Russell
307 P.2d 719 (California Court of Appeal, 1957)
Montrose Contracting Co. v. County of Westchester
80 F.2d 841 (Second Circuit, 1936)
Allied Properties v. John A. Blume & Associates
25 Cal. App. 3d 848 (California Court of Appeal, 1972)
Roberts v. Karr
178 Cal. App. 2d 535 (California Court of Appeal, 1960)
Gautier v. General Telephone Co.
234 Cal. App. 2d 302 (California Court of Appeal, 1965)
Lindner v. Barlow, Davis & Wood
210 Cal. App. 2d 660 (California Court of Appeal, 1962)
Bonadiman-McCain, Inc. v. Snow
183 Cal. App. 2d 58 (California Court of Appeal, 1960)
Northern Crossarm Co. v. Chemical Specialities, Inc.
318 F. Supp. 2d 752 (W.D. Wisconsin, 2004)
Souza & McCue Construction Co. v. Superior Court
370 P.2d 338 (California Supreme Court, 1962)
APAC Carolina, Inc. v. Town of Allendale
41 F.3d 157 (Fourth Circuit, 1994)
De La Concha of Hartford, Inc. v. Aetna Life Insurance
849 A.2d 382 (Supreme Court of Connecticut, 2004)
Elm Street Builders, Inc. v. Enterprise Park Condominium Ass'n
778 A.2d 237 (Connecticut Appellate Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
10 Am. Samoa 3d 315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-services-in-samoa-inc-v-american-samoa-government-amsamoa-2005.