Construction Lender, Inc. v. Sutter

491 S.E.2d 853, 228 Ga. App. 405, 97 Fulton County D. Rep. 3327, 1997 Ga. App. LEXIS 1147
CourtCourt of Appeals of Georgia
DecidedSeptember 8, 1997
DocketA97A1611
StatusPublished
Cited by25 cases

This text of 491 S.E.2d 853 (Construction Lender, Inc. v. Sutter) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction Lender, Inc. v. Sutter, 491 S.E.2d 853, 228 Ga. App. 405, 97 Fulton County D. Rep. 3327, 1997 Ga. App. LEXIS 1147 (Ga. Ct. App. 1997).

Opinion

Ruffin, Judge.

The Construction Lender, Inc. (“TCL”) and its president, Joe Ray, appeal from a $111,727.21 jury verdict and judgment in favor of Robert and Sandra Sutter, who borrowed money from TCL to finance the construction of their Hall County home. The jury’s verdict was based on the Sutters’ negligence claims, in which they alleged TCL and Ray had improperly disbursed $47,500 to the builder, Joe Mus-tin, who then abandoned the job and left the house uncompleted. We find the evidence supports the jury’s finding on one theory of negligence, but we reverse the judgment and remand for a new trial because the Sutters cannot sustain a second negligence theory and failed to prove that certain damages were proximately caused by any action of TCL or Ray.

We review the evidence, as we must, construing it strongly in favor of the jury’s verdict. See Southeastern Security Ins. Co. v. Hotle, 222 Ga. App. 161, 162 (1) (473 SE2d 256) (1996). Viewed in this light, the evidence shows that in April 1994, the Sutters and builder Joe Mustin agreed in writing that Mustin would construct the Sutters’ home for a total contract price of $235,000. That contract specified the Sutters would give Mustin a ten percent advance, and Mustin would receive additional payments based on the “Lender’s Draw schedule.”

The Sutters then entered a loan agreement with TCL to finance the construction and to pay off the purchase price for the underlying land. That agreement specified TCL would make “advances” up to the “total principal amount” of the note, provided that, among other things, “[a]t the time of each advance, [TCL] is fully satisfied with the timeliness, progress, and quality of development and/or construction and, in the sole opinion of [TCL], the estimated cost of development and/or construction in accordance with the plans and specifications does not exceed the balance of the loan to be advanced.” The contract further specified, however, that “[TCL] has had no control over, will have no control over, has not supervised, and will not supervise the construction of improvements on the property. [TCL] has not, does not, and will not make any representations, warranties, guarantees or promises concerning the construction, workmanship, materials, or design employed in, to be used in, or constituting the improvements on the property. [TCL’s) relationship to the construction ... is solely that of a mortgage lender, and all periodic inspections and any appraisals made by [TCL] are for the sole purpose of protecting [TCL’s] security interest in the real estate and determining that progress has been made for the disbursement of construction *406 loan funds as work has been completed.” At the bottom of the loan agreement, the Sutters signed a clause directing TCL to “make all advances under the foregoing agreement directly to the contractor” and authorizing Mustin “to apply for and receive all advances under the foregoing agreement for the purpose of paying all bills for labor and material employed in the construction. . . .”

At the closing, the Sutters learned that the ten percent advance to Mustin ($23,500) could not come from loan funds. A TCL employee told the Sutters that if they paid that advance, the $23,500 would be reimbursed to them from loan funds once the house was complete. Therefore, so long as no “change orders” were made, the Sutters alleged, TCL should have disbursed to Mustin a total of $211,500 in exchange for Mustin’s completion of the house. Mr. Sutter testified no such change orders were made.

After construction began, the Sutters had problems with Mus-tin’s work, including his incorrect placement of a driveway. In September, the Sutters asked Ray that he and TCL not make any further disbursements to Mustin without first obtaining their approval. Ray complied, and before allowing Mustin the next three draws, he called one of the Sutters and obtained authorization to make these advances. In December, however, Mustin requested an additional draw in excess of $60,000. Ray^inspected the construction, decided the work completed warranted an-advance of $47,500, and on December 15, 1994, disbursed those funds to Mustin without first contacting the Sutters. This unauthorized advance brought the total amount paid by TCL to Mustin to $211,564, or $64 in excess of what TCL should have paid the builder assuming no increases were made in the $235,000 fixed contract price. On December 19, 1994, Mustin abandoned the job and soon thereafter declared bankruptcy.

The Sutters presented evidence of their damages, including the amounts disbursed without authority and in excess of the contract price. They also sought the $50,000 cost of completing the house and other damages that resulted from the delays in completion caused when Mustin abandoned the job. Because the house was not complete, the Sutters were required to pay continuing interest on the construction loan and had to refinance the loan to pay the additional completion costs. They introduced evidence showing approximately $42,000 in additional unpaid materialmen’s liens that Mustin’s subcontractors had placed on the property. In addition to those amounts, the Sutters sought recovery for rent they paid from December 1994 through July 1995, moving expenses, damages resulting from deterioration to the house as it sat vacant and uncompleted for many months, and the cost of an insurance policy they maintained on the house from December 1994 until its completion.

At the close of evidence, but before the case was submitted to the *407 jury, the Sutters dropped all their contract-based claims and proceeded only on two tort theories. First, they asserted that TCL and Ray had a tort duty to ensure that payments made on the loan were timely and for work actually done. Second, they argued that Ray and TCL negligently failed to discharge the duty they voluntarily undertook to obtain the Sutters’ approval before disbursing the final $47,500 to Mustin.

On appeal, Ray and TCL claim the trial court erred by denying their motions for directed verdict and judgment notwithstanding the verdict (“j.n.o.v.”). They claim neither defendant had any tort-based duty to the Sutters and, if they did, no proximate causal connection existed between the violation of any duty and the damages the Sutters sought. Having construed the evidence strongly in favor of the jury’s verdict, we must determine whether the Sutters produced any evidence to support their claims. Southeastern Security, supra.

1. (a) Voluntary Undertaking. We find the court properly allowed the jury to determine whether TCL and Ray negligently breached their duty to obtain authorization before disbursing funds. The Sutters correctly state the principle that “[wjhere one undertakes an act which he has no duty to perform and another reasonably relies upon that undertaking, the act must generally be performed with ordinary or reasonable care. [Cit.]” Stelts v. Epperson, 201 Ga. App. 405, 407 (411 SE2d 281) (1991). The evidence supports a finding that Ray, on behalf of TCL, voluntarily undertook the duty to obtain approval from the Sutters before disbursing the $47,500 and breached that duty. An officer of a corporation who personally takes part in a tort committed by the corporation may be held personally liable. See Cherry v. Ward, 204 Ga. App. 833, 834 (1) (a) (420 SE2d 763) (1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhonda May Dixon v. Richard Alan Dixon
Court of Appeals of Georgia, 2019
Paramount Contracting Co. v. DPS Industries, Inc.
709 S.E.2d 288 (Court of Appeals of Georgia, 2011)
Goldsmith v. Peterson
703 S.E.2d 694 (Court of Appeals of Georgia, 2010)
Brock Built, LLC v. Blake
686 S.E.2d 425 (Court of Appeals of Georgia, 2009)
J. Kinson Cook of Georgia, Inc. v. Heery/Mitchell
644 S.E.2d 440 (Court of Appeals of Georgia, 2007)
Walton v. UCC X, Inc.
640 S.E.2d 325 (Court of Appeals of Georgia, 2006)
Mau, Inc. v. Human Technologies, Inc.
619 S.E.2d 394 (Court of Appeals of Georgia, 2005)
Baker v. Campbell
565 S.E.2d 855 (Court of Appeals of Georgia, 2002)
White v. City of Atlanta
545 S.E.2d 625 (Court of Appeals of Georgia, 2001)
Wallace v. State Farm Fire & Casualty Co.
539 S.E.2d 509 (Court of Appeals of Georgia, 2000)
Wynn v. Arias
531 S.E.2d 126 (Court of Appeals of Georgia, 2000)
Traina Enterprises, Inc. v. Racetrac Petroleum, Inc.
525 S.E.2d 712 (Court of Appeals of Georgia, 1999)
Cooley v. Gulf Bank, Inc.
773 So. 2d 1039 (Court of Civil Appeals of Alabama, 1999)
Bibb Distributing Co. v. Stewart
519 S.E.2d 455 (Court of Appeals of Georgia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
491 S.E.2d 853, 228 Ga. App. 405, 97 Fulton County D. Rep. 3327, 1997 Ga. App. LEXIS 1147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-lender-inc-v-sutter-gactapp-1997.