This text of 62 Colo. 470 (Consolidated Juchem Ditch & Reservoir Co. v. Old) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Juchem Ditch & Reservoir Co. v. Old, 62 Colo. 470 (Colo. 1917).

Opinion

Mr. Justice Scott

delivered the opinion of the court.

This is an action by the defendants in error, plaintiffs below, for mandatory injunctive relief, under a contract by and between Evan E. Reno, grantor of Robert O. Old, deceased, whose heirs are the defendants in error, and The Juchem Extension Ditch & Reservoir Company, original defendant below, and for which the plaintiff in error, was substituted as party defendant, pending proceedings on the trial court. This contract was as follows:

“State of Colorado, County of Arapahoe,. April 16, 1892.

[471]*471This agreement entered into this day by and between The Jnchem Extension Ditch & Reservoir Company, party of the first part, and Evan E. Reno, party of the second part, to-wit:

For and in consideration of 35 inches of water, which - party of the first part agrees to deliver to party of the second part on the West One-half (y2) of the Southeast Quarter of Section 9, Township 3 South, Range 69 West, County of Jefferson, at such place or places, but not to exceed two boxes, as might be agreed upon between both parties to this agreement, party of the second part agrees to execute and deliver to the party of the first part a quit claim deed, quitclaiming unto said party all claims of any nature whatsoever which he may hold against parties of the first part, as well as the right of way now being used by the company, 16 ft.

Party of the second part further agree with first party to pay to said first party the sum of $2.00 per inch for water and to pro rate in all cases with the members of the company as provided by the by-laws.

The Juchem Extension Ditch & Reservoir Co.
By its officers,
Chas. Ecker, President, James Stickle, Secretary,
A. S. Lang, Treasurer,
Evan E. Reno.”

The complaint alleged in substance, the ownership by plaintiff of the lands described in the contract, at the time of the execution of that instrument, and long prior thereto, by the said Reno; a conveyance of said premises with the water rights, under said contract to Robert O. Old; the ownership thereof by said Old at the time of his death, and that plaintiffs are the sole heirs and legatees of said Old; that the said Juchem Extension Ditch and Reservoir Company, in the year 1887, without right- [472]*472and wrongfully, entered upon said lands and constructed an irrigation ditch over and across the southern portion of said lands, and proceeded to use the same as an extension of its irrigation ditch. That a controversy thus arose between the said Reno and the said ditch company, which continued until 1892, when the same was adjusted and settled by the execution of the said contract.

It was further alleged that said lands are improved agricultural lands, and without value for agricultural purposes, without the right to use the water stipulated in the contract; that said ditch so remains and is in use across said premises; willingness upon the part of the plaintiffs to pay the agreed price for the delivery of water; that there is no other source of water supply for said land, and that plaintiffs are now and have at all times been willing to comply with their obligations under the said agreement.

The prayer of the complaint was as follows:

“Wherefore, plaintiffs pray judgment that the defendant be compelled, by order of this court, to turn out annually to the plaintiffs, for use upon the said west half of the southeast quarter of section 9, township 3 south of range 69 west, in Jefferson county, Colorado, thirty-five inches of water, upon the payment, to-wit: of the sum of seventy dollars. That a peremptory order be entered against the defendant, either by way of mandamus or mandatory injunction, requiring the said defendant to specifically perform the’said contract. For two thousand dollars damages; for costs of this action; and for such other and further relief as to the court shall seem meet and proper in the premises.”

The answer was a general denial of the allegations of the complaint. The court found specifically as to all matters of fact, in favor of the plaintiff and it was ordered :

[473]*473“That the plaintiffs are hereby required to execute and deliver to the clerk of this court a deed, conveying to the defendant a right of way for its said ditch, sixteen (16) feet in width, being eight (8) feet each way from the center of said ditch, over and across the south end of the West Half (Wy2) of the Southeast Quarter (SE%) of Section (9) Nine, Township Three (3) South, Bange Sixty-nine (69) West, in Jefferson county, State of Colorado, being the strip of land now, and for the past twenty years, occupied by said ditch;

And It Is Further Ordered, Adjudged and Decreed that the defendant be and it is hereby required to deliver to the plaintiffs and their grantees, or their heirs or assigns, thirty-five (35) inches of water every year, during the irrigation season, or so much thereof as may be necessary to irrigate said eighty (80) acres of land, for which the plaintiffs shall pay to the defendant the sum of Two Dollars ($2) per inch per annum; that the water shall be delivered from said ditch of the defendant company in not to exceed two (2) boxes, upon the eighty (80) acres of land, at points to be selected by the plaintiffs; and in case of shortage of water, the right of the plaintiffs to water from said ditch shall be the same, and are hereby declared to be the same, with respect to the prorating and division of water, as the right of a stockholder in said ditch as defined by the articles of incorporation, by-laws, and rules and regulations of The Juchem Extension Ditch & Beservoir Company, to observe and carry out the terms of this decree.”

The court made certain findings of fact which seem important to recite, as follows:

“The court further finds that the water under the above contract was used upon the land in the year 1895, and was paid for at the rate of Two Dollars ($2) per inch; that A. B. Cole, who is the present secretary of the [474]*474defendant company, and has been such secretary since 1901, was a tenant of the grantee of said Evan E. Reno, to-wit, Robert 0.' Old, and was asserting at that time that this contract was in existence, and was entitled to the water; that the secretary of the company, in 1895, conceded the right of the owners of this eighty acres to the water, and water was turned in upon the land, and a bill was rendered by the company to the owners of the land, and. they paid therefor; that since said time there has been constant controversy with reference to this contract, the same being denied by the company both, verbally and in their pleadings; that in 1906 a formal demand was again made upon the ditch company for this water, and a tender made of $2.00 per inch, which was refused, whereupon this suit was brought. * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tovrea v. Umphress
556 P.2d 814 (Court of Appeals of Arizona, 1976)
Hall v. Bankers Trust Co.
74 P.2d 720 (Supreme Court of Colorado, 1937)
Cortella v. Salt Lake City
72 P.2d 630 (Utah Supreme Court, 1937)
Skinner v. Jordan Valley Irrigation District
3 P.2d 534 (Oregon Supreme Court, 1931)
Devine v. Western Slope Fruit Growers Ass'n
196 P. 329 (Supreme Court of Colorado, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
62 Colo. 470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-juchem-ditch-reservoir-co-v-old-colo-1917.