Consolidated Edison Co. v. Commission

676 F.2d 763, 219 U.S. App. D.C. 165, 1982 U.S. App. LEXIS 19967
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 20, 1982
DocketNo. 81-1082
StatusPublished
Cited by1 cases

This text of 676 F.2d 763 (Consolidated Edison Co. v. Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Edison Co. v. Commission, 676 F.2d 763, 219 U.S. App. D.C. 165, 1982 U.S. App. LEXIS 19967 (D.C. Cir. 1982).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

Petitioner, Consolidated Edison (“Con Ed”) challenges the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) approval of an end use curtailment plan for natural gas that does not require customers who undergo below average curtailment to compensate those who are curtailed more than the average customer.1 [167]*167Con Ed argues that FERC’s action constitutes a taking of property without just compensation, and is thus in violation of the fifth amendment. It also argues that FERC’s rejection of a compensation scheme was not a product of reasoned decisionmaking and was arbitrary and capricious. For the reasons set forth below, we affirm the Commission.

I. BACKGROUND

A. History of Curtailment Plans

Following natural gas shortages on a number of pipelines in 1970, the Commission 2 issued Order No. 431, 45 F.P.C. 570 (1971), directing each interstate pipeline company to report to the Commission stating whether it expected to experience natural gas shortages. Those companies that anticipated shortages were required to submit a revised tariff outlining their plans for allocating short supplies. Pipeline companies filed two types of curtailment plans: “pro-rata” plans and “end use” plans. Under a pro-rata plan, all customers would receive the same proportion of the natural gas they contracted for. The worse the shortage, the smaller that proportion would be; but no customer would receive a greater percentage of his contract than any other customer. In contrast, an end use plan would allocate gas according to the use to which that gas would ultimately be put. Under an end use plan, the contracts providing gas to the highest priority end users must be performed before any gas is allocated to the next highest user.3

Two years after it first solicited curtailment plans, the Commission issued a policy statement stating its preference for end use curtailment plans. Order No. 467,49 F.P.C. 85 (1973). As modified by a subsequent order,4 this policy statement established nine priority rankings for end users. These rankings are:

(1) Residential, small commercial (less than 50 Mcf on a peak day).

(2) Large commercial requirements (50 Mcf or more on a peak day), firm industrial requirements for plant protection, feedstock and process needs, and pipeline customer storage injection requirements.

(3) All industrial requirements not specified in (2), (4), (5), (6), (7), (8), or (9).

(4) Firm industrial requirements for boiler fuel use at less than 3,000 Mcf per day, but more than 1,500 Mcf per day, where alternate fuel capabilities can meet such requirements.

(5) Firm industrial requirements for large volume (3,000 Mcf or more per day) boiler fuel use where alternate fuel capabilities can meet such requirements.

(6) Interruptible requirements of more than 300 Mcf per day, but less than 1,500 Mcf per day, where alternate fuel capabilities can meet such requirements.

(7) Interruptible requirements of intermediate volumes (from 1,500 Mcf per day through 3,000 Mcf per day), where alternate fuel capabilities can meet such requirements.

(8) Interruptible requirements of more than 3,000 Mcf per day, but less than 10,000 Mcf per day, where alternate fuel capabilities can meet such requirements.

(9) Interruptible requirements of more than 10,000 Mcf per day where alternate fuel capabilities can meet such requirements.

[168]*168The Commission explained its priority scheme both on efficiency grounds and on an assessment of the comparative hardship suffered by different end users should they be required to reduce their consumption of natural gas. Generally, the Commission found an end use scheme preferable to a pro-rata scheme “because contracts do not necessarily serve the public interest requirement of efficient allocation of this wasting resource.” 49 F.P.C. at 86. By employing an end use plan, natural gas could be directed to those who could burn it most efficiently or for whom it would be most expensive to convert to other fuels. Turning to its own priority scheme, the Commission reasoned that it is least efficient to allocate gas to interruptible customers because “[i]nterruptible service . . . envisions interruption. And accordingly, interruptible customers can most reasonably be expected to have alternate fuel facilities already operational.” 49 F.P.C. at 86 (quoting Arkansas-Louisiana Gas Co., 49 F.P.C. 53, 66 (1973)). The Commission also labelled those in the next lowest priority group — boiler fuel users — as “inferior” users of natural gas for the following reasons:

Aside from the established physical fact that combustion of natural gas for raising steam in boilers and its subsequent conversion into electricity or mechanical energy results in a loss of roughly two-thirds of the heating value of the gas used — which we regard as unacceptably inefficient in time of shortage — we note also that those who use gas as boiler fuel generally can substitute other fuels more readily and at lower overall cost than other gas users; additionally, pollution control is more practical because of the large size of individual installations. Other fuels generally can be phsyically [sic] substituted in large boiler fuel applications with less inconvenience and less possible adverse consequences than in other industrial applications, such as direct fired uses, and other uses demanding precise temperature control, flame characteristics, instantaneous response and atmosphere quality.

Id. In addition to these efficiency concerns, the Commission found that its priority scheme would best protect “residential and small volume consumers who cannot be safely curtailed on a daily basis.” See 49 F.P.C. at 86.5

End use plans were not without their critics. In a petition to this court, pipeline customers receiving below average percentages of their contracts argued that end use plans illegally reallocated natural gas among pipeline customers and were thus in violation of section 7(a) of the Natural Gas Act, 15 U.S.C. § 717f(a). We rejected this argument, ruling that section 7(a) only prohibits the Commission from ordering sales to new customers when to do so would impair service to existing customers. Since curtailment plans govern pipeline sales during retractions of service, rather than expansions of service, we held that section 7(a) is inapplicable to curtailment plans. See American Smelting & Refining Co. v. FPC, 494 F.2d 925, 936 (D.C.Cir.), cert. denied, 419 U.S. 882, 95 S.Ct. 148, 42 L.Ed.2d 122 (1974). Subsequently, in North Carolina v. FERC, 584 F.2d 1003, 1011 (D.C.Cir.1978), we discussed at greater length the scope of the Commission’s curtailment authority, explaining that discriminatory treatment of distributors is only justified to the extent that a curtailment plan reasonably reflects the actual impact that plan will have on ultimate consumers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
676 F.2d 763, 219 U.S. App. D.C. 165, 1982 U.S. App. LEXIS 19967, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-edison-co-v-commission-cadc-1982.