Conservation Commission of Brockton v. Department of Environmental Protection

966 N.E.2d 228, 81 Mass. App. Ct. 601, 2012 WL 1320214, 2012 Mass. App. LEXIS 173
CourtMassachusetts Appeals Court
DecidedApril 19, 2012
DocketNo. 11-P-766
StatusPublished
Cited by2 cases

This text of 966 N.E.2d 228 (Conservation Commission of Brockton v. Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conservation Commission of Brockton v. Department of Environmental Protection, 966 N.E.2d 228, 81 Mass. App. Ct. 601, 2012 WL 1320214, 2012 Mass. App. LEXIS 173 (Mass. Ct. App. 2012).

Opinion

Sullivan, J.

This is an appeal pursuant to the Administrative Procedures Act, G. L. c. 30A, § 14, from a decision of the Department of Environmental Protection (DEP) authorizing the construction of a 350 megawatt power plant (the plant) near the [602]*602Salisbury Plain River. The conservation commission of Brockton (commission) appeals from a judgment entered by a judge of the Superior Court upholding the final decision and order of the DEP on two grounds. First, the commission claims that the judge erred in affirming the DEP’s determination that the project proponent, Brockton Power Company, LLC (Brockton Power), did not have to include in its permit application information concerning the impact of its purchase of water from the Brockton advanced waste water reclamation facility (Brockton Water) on the river’s water levels and on the wetlands bordering the river. Second, the commission claims that the judge erred in upholding the DEP’s determination that Brockton Power’s application for exemption from local zoning under G. L. c. 40A, § 3, satisfied the Wetlands Protection Act (WPA) requirement that applicants seek all obtainable local permits and approvals when filing a notice of intent with the local conservation commission. See G. L. c. 131, § 40. We affirm.2

Background. Brockton Power proposes to build the project partially within 100 feet of vegetated wetlands bordering the Salisbury Plain River, a protected wetland area. The plant would not take water directly from the river. Rather, the plant’s cooling towers are projected to use approximately 1.9 million gallons per day of treated effluent from the adjacent Brockton Water facility &emdash; water that would otherwise be discharged into the river under the terms of an existing NPDES/MA3 surface water discharge permit. The proposed plant is projected to return .3 million gallons of water per day to the river, and to disperse the remaining 1.6 million gallons per day by evaporation as steam. Brockton Power’s consumption of treated effluent may result in discharge into the Salisbury Plain River of approximately 1.6 million fewer gallons per day. Thus, Brockton Water’s sale of water to Brock-ton Power will reduce the existing addition to the river’s flow.

[603]*603The WPA prohibits certain activities that would alter wetlands in the absence of a wetlands permit. G. L. c. 131, § 40. A person who desires to perform “work” within the 100 foot area surrounding wetlands (buffer zone) that would alter the wetlands may be required to obtain a permit, known as an order of conditions, and file a notice of intent (NOI)4 with the local conservation commission. See G. L. c. 131, § 40; 310 Code Mass. Regs. § 10.02(2)(b) (2007).

Brockton Power is located at a distance from the wetlands, but a portion of the project would fall within the buffer zone. Brockton Power filed an NOI with the commission on June 27, 2008. The NOI contained a detailed discussion of the impact of the construction of the project on the wetlands and the buffer zone, as well as remediation measures. The NOI did not address the impact of the purchase of the water (and concomitant reduction in discharge) on water levels or the wetlands.

On July 12, 2007, Brockton Power applied to the Department of Public Utilities (DPU) for an exemption from Brockton’s relevant zoning restrictions pursuant to G. L. c. 40A, § 3, but the commission deemed the application for exemption insufficient. On October 23, 2008, the commission denied Brockton Power’s request for approval of the project, finding that (1) the NOI contained insufficient information because it did not describe the impact of the project’s use of Brockton Water’s treated effluent on the water levels of the Sudbury Plains River, and (2) Brockton Power had failed to apply for local zoning approvals as required by 310 Code Mass. Regs. § 10.05(4)(e)-(f) (2008).

In early November, 2008, Brockton Power appealed the commission’s decision to the DEP Bureau of Resource Protection (DEP Bureau), requesting a superseding order of conditions. A [604]*604superseding order of conditions approving the project issued on September 3, 2009. The DEP Bureau concluded that “Brockton Power Company’s use of the effluent as cooling water would not be an alteration of a wetland resource area provided that [Brockton Water’s] discharge remains within the limits of the NPDES permits and any permits issued by the MassDEP.” The DEP Bureau reasoned that Brockton Water, not Brockton Power, “would have the responsibility for complying with the permitted effluent discharge requirements or amending the permits and addressing any potential impacts to the wetland resources areas.”

The commission appealed from the superseding order of conditions, and both the commission and Brockton Power filed motions for summary decision under DEP adjudicatory procedures. The DEP upheld the superseding order of conditions in a final order. The DEP found that Brockton Power did not have to include the purchase of water in its NOI, because it was the customer in that transaction and not the supplier, the latter being the party that was responsible for the discharge.5 The DEP also found that Brockton Power was not required to apply for or obtain site plan approval from the local boards before filing an NOI with the commission. The commission appealed from that final order to the Superior Court.

The Superior Court judge heard and decided the matter on the administrative record on a motion for judgment on the pleadings. See Mass.R.Civ.P. 12(c), 365 Mass. 754 (1974). The judge affirmed the final decision of the DEP in all respects, reasoning that the word “alter” in the WPA was intended to cover only that work which had a “direct” rather than an “indirect” impact on [605]*605wetlands. The judge also found that the exemption process relieved Brockton Power of the obligation to apply for or obtain local zoning approval. While we do not adopt the broad “direct” versus “indirect” distinction relied on by the Superior Court judge, we affirm for the reasons stated below.

Discussion. We review an order allowing a motion for judgment on the pleadings de nova. See Wheatley v. Massachusetts Insurers Insolvency Fund, 456 Mass. 594, 600 (2010).

1. “Work” and the WPA. Because the DEP has not decided whether Brockton Water has an obligation to file an NOI, and because there was no challenge to the determination that the wetlands issues may be resolved by monitoring the NPDES/ Surface Water Discharge Permit, the issue before the Superior Court judge was whether Brockton Power’s purchase of the water was “work” that required inclusion in the NOI. Our review is similarly limited to that issue.

The commission carries the “formidable burden” of showing that the agency’s interpretation of its own rules is not rational. Northbridge v. Natick, 394 Mass. 70, 74 (1985), quoting from Greenleaf Fin. Co. v. Small Loans Regulatory Bd., 377 Mass. 282, 293 (1979). “[W]e review an agency’s decision to determine whether it was not supported by substantial evidence, was arbitrary or capricious, or was otherwise based on an error of law.” Ten Local Citizen Group v. New England Wind, LLC, 457 Mass. 222, 228 (2010).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mostyn v. Department of Environmental Protection
989 N.E.2d 926 (Massachusetts Appeals Court, 2013)
Brockton Power LLC v. City of Brockton
948 F. Supp. 2d 48 (D. Massachusetts, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
966 N.E.2d 228, 81 Mass. App. Ct. 601, 2012 WL 1320214, 2012 Mass. App. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conservation-commission-of-brockton-v-department-of-environmental-massappct-2012.