Conrad Shipyard, LLC

CourtArmed Services Board of Contract Appeals
DecidedMarch 24, 2025
Docket63869
StatusPublished

This text of Conrad Shipyard, LLC (Conrad Shipyard, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conrad Shipyard, LLC, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Conrad Shipyard, LLC ) ASBCA No. 63869 ) Under Contract No. 000000-00-0-0000 )

APPEARANCES FOR THE APPELLANT: Michael H. Payne, Esq Cohen Seglias Pallas Greenhall & Furman, PC Philadelphia, PA

Casey J. McKinnon, Esq. Cohen Seglias Pallas Greenhall & Furman, PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Scott C. Seufert, Esq. Jacqueline Kelly, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Philadelphia

OPINION BY ADMINISTRATIVE JUDGE MELNICK ON THE GOVERNMENT’S MOTION TO DISMISS OR FOR SUMMARY JUDGMENT AND ON APPELLANT’S PARTIAL CROSS-MOTION FOR SUMMARY JUDGMENT

Conrad Shipyard, LLC (Conrad), contends the Army Corps of Engineers (government) breached an implied-in-fact contract to pay it a $1,000,000 stipend to compete for a contract to design and construct a new dredging vessel. In the first count of its complaint, Conrad essentially argues that it performed the contract and the government refused to pay. In the second count, it maintains the government interfered with its performance, breaching the implied duty of good faith and fair dealing. After considering dispositive motions by the parties, we conclude Conrad did not complete performance so is not entitled to recover under Count I. Also, Conrad did not submit a claim to the contracting officer for breach of the duty of good faith and fair dealing. Count II is therefore dismissed for lack of jurisdiction.

STATEMENT OF THE FACTS (SOF) FOR PURPOSES OF THE MOTIONS

1. On December 18, 2020, the government issued a solicitation to procure the design and construction of a dredging vessel. Nobody submitted a proposal. (Compl. ¶ 5; gov’t mot. at 3) The government inquired of the industry and discovered that the engineering and related supplier consultations required to properly develop a proposal cost an estimated $600,000, with no guarantee of a return for offerors. The government officially determined that it was necessary to pay a stipend to cover those associated costs to make the procurement more attractive, generate adequate competition, and provide a level of engineering and pricing that would reduce the government’s risk of unsuccessful contract performance. (R4, tab 20)

2. On May 26, 2022, the government issued another solicitation for design and construction of the dredge (R4, tab 4). This time the solicitation included provision for a stipend. It stated the following:

PURPOSE: The purpose of authorizing a Stipend in Medium Class Hopper Dredge (MCHD) procurement is to stimulate competition and innovation within the dredging shipyard industry. Each Offer, except the contract awardee, who meets the conditions listed below is eligible for an award of a firm fixed price stipend.

1. The Offeror competed in the MCHD solicitation evaluation process and was unsuccessful in receiving the contract award.

2. The Offeror’s proposal is otherwise rated acceptable in the source selection process. To receive consideration for a stipend, a rating of no less than “Acceptable” must be achieved for all non-price factors except past performance which must be rated other than “No Confidence.”

3. The amount authorized for each stipend award is a firm fixed price of less than or equal to $1,000,000.00.

4. Unsuccessful Offerors eligible to receive the stipend, shall be notified within 30 calendar days of contract award to invoice for stipend.

5. Only one stipend will be provided to each offeror regardless if the offeror submitted more than one proposal for evaluation.

2 6. Maximum stipend pool is $3 Million to allow for up to 3 potential $1,000,000.00 stipends. In the unlikely event more than 4 acceptable proposals are received (1-Contract Awardee, 3-Acceptable Proposals), each eligible offeror shall receive an equal per capita share of the stipend pool ($3 Million).

(R4, Tab 4 at 426) Essentially, the solicitation offered to pay a stipend to all offerors competing in the solicitation process whose proposals were acceptable but who did not receive the award.

3. Offers were due January 5, 2023 (R4, tab 15 at 1-2, 12). The solicitation also contained FAR 52.212-1, INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021) (R4, tab 4 at 437). As amended, subsection (c) of that clause identified the “[p]eriod for acceptance of offers.” It dictated that “[t]he offeror agrees to hold the prices firm for 120 calendar days from the date specified for receipt, unless another time period is specified in an addendum to the solicitation” (R4, tab 4 at 438, 440).

4. On January 5, 2023, Conrad submitted a proposal (gov’t mot. at 4; app. opp’n & mot. at 23). Accordingly, its price was to remain firm for 120 days, until May 5, 2023.

5. On March 2, 2023, the government informed Conrad its proposal was in the competitive range and the government was prepared to enter discussions. During discussions, all offerors would be allowed to revise their pricing. (R4, tab 1 at 13) Conrad submitted an updated proposal on March 15, 2023. There is no indication it altered its price. After the government reviewed the second submission, it reported on April 7, 2023, that Conrad remained in the competitive range, it had no further questions, and discussions could continue. Again, the government granted Conrad the opportunity to revise its prices, but it required the final pricing to remain valid through August 1, 2023, beyond the initial 120-day mandate. (R4, tab 33) By letter dated April 21, 2023, Conrad forwarded revised prices and expressly agreed they would remain valid until August 1, 2023 (R4, tab 34; gov’t mot. at 4; app. opp’n & mot. at 5-6). The government concedes Conrad’s proposal was acceptable for establishing the competitive range (gov’t reply at 6).

6. On June 22, 2023, Conrad withdrew its consent to extend the validity of its proposal, which it acknowledges constituted a withdrawal of the proposal (R4, tab 36 at5; app. opp’n & mot. at 6). Conrad explained that inflationary impacts, supply chain issues, other commitments, and, perhaps most significantly, the refusal of its surety to issue performance and payment bonds, caused it to withdraw (R4, tab 38 at 3). On

3 July 24, 2023, the government issued the award to another contractor (gov’t mot at 5; app. opp’n & mot. at 6).

7. On August 3, 2023, Conrad inquired into the process for payment of the stipend. The contracting officer responded on September 15, 2023, that Conrad was ineligible because it had withdrawn from the competition prior to contract award (R4, tabs 39-40).

8. On September 28, 2023, Conrad submitted a certified claim to the contracting officer demanding the $1,000,000 stipend. Conrad characterized the solicitation provisions as a contract and contended it had complied with its terms. (R4, tab 1 at 29-30). The government denied the claim on January 3, 2024 (R4, tab 3). Conrad now appeals.

9. Count I of Conrad’s complaint alleges that the parties formed an implied-in- fact contract where Conrad would compete for the procurement and be eligible for the stipend. It contends Conrad performed as specified and the government breached by failing to pay. It seeks the $1,000,000 stipend and an additional recovery on a quantum meruit theory for the value it bestowed on the government for participating in the competition. (Compl. ¶¶ 31-43)

10. Count II alleges breach of the implied duty of good faith and fair dealing. The purported support for that assertion is that the government unreasonably delayed contract award by 200 days from the date offers were due, unreasonably required offerors to extend their offers an additional 88 days, and failed to inform Conrad, after Conrad stated its offer could no longer be extended, the award was imminent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
New Era Construction v. The United States
890 F.2d 1152 (Federal Circuit, 1990)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
City of Cincinnati v. United States
153 F.3d 1375 (Federal Circuit, 1998)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Labatte v. United States
899 F.3d 1373 (Federal Circuit, 2018)
The Tolliver Group, Inc. v. United States
20 F.4th 771 (Federal Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Conrad Shipyard, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conrad-shipyard-llc-asbca-2025.