OPINION BY
Judge PELLEGRINI.
ConocoPhillips, formerly Tosco Oil (Employer), appeals an order of the Workers’ Compensation Appeal Board (Board) denying its Application for Supersedeas Fund Reimbursement (Application) because it made a payment on award of benefits which was later reduced to Thomas Logan (Claimant) before there was a denial of the request for supersedeas as required by Section 443(a) of the Workers’ Compensation Act (Act).1
On September 14, 1999, Claimant filed a claim petition alleging that he suffered occupational hearing loss while in the course of his employment with Employer. Workers’ Compensation Judge Joseph Stokes (WCJ Stokes) ordered Employer to pay Claimant 80.86 weeks of hearing loss benefits in a decision circulated March 7, 2001. On March 27, 2001, the Employer appealed and requested supersedeas, the last day to request a supersedeas under the Board’s regulations (Special Rules).2 [1162]*1162Those Special Rules provide that a request for supersedeas must be made within 20 days of the WCJ’s order, and the responding party’s answer is due within 10 days after service of its request. The Board’s decision must be issued within 20 days of receipt of the answer to the request for supersedeas or it is deemed denied. If all the parties and the Board take all of the time allotted by the Special Rules, the Board’s decision, affirmatively or deemed, can be rendered as late as 50 days after the WCJ’ order.
On April 19, 2001, well within the 50 days provided by the Special Rules, Employer’s supersedeas request was granted pending oral argument on the appeal scheduled for June 2001. Unfortunately, unaware that the Board had granted a supersedeas, Employer on the same day paid to Claimant a lump sum hearing loss award of $52,139.96. Through an unexplained delay, the Board did not decide the appeal of the award of the lump sum payment order until January 13, 2003.3 The Board, reversing in part, reduced the amount of Claimant’s award proportionate to the amount of hearing loss attributable to his employment with Employer, netting a reduction in the amount that was due to Claimant of $36,414.84.
Seeking reimbursement of $36,414.84, Employer then filed the Application asserting that although its supersedeas request of March 27, 2001, was granted, not denied by the Board because the award was reduced, it was still entitled to reimbursement from the Supersedeas Fund (Fund) for the overpayment. Acting in its capacity as conservator of the Fund, the Bureau of Workers’ Compensation (Bureau) filed an answer on September 12, 2003, asserting that Employer was not entitled to reimbursement from the Fund because the request for supersedeas was granted rather than denied, and that under Section 443(a) of the Act, Employer had failed to present grounds on which relief could be granted.
The matter was then assigned to Workers’ Compensation Judge Robert Simmons (WCJ Simmons) who denied Employer’s Application in a decision circulated on February 13, 2004. Relying on our then-recent decision in Snizaski v. Workers’ Compensation Appeal Board (Rox Coal Co.), 847 A.2d 139 (Pa.Cmwlth.2004), holding that it was an abuse of discretion for a WCJ to impose penalties on an employer who had delayed payment before the 50 days had passed and the request was deemed denied, WCJ Simmons found that the supersedeas request could not have been deemed denied because the Board had granted the request within 50 days of WCJ Stokes’ decision. Because Employer failed to meet the requirement under Section 443 that the payment was made “as a result” of a denial of its request for a supersedeas, WCJ Simmons held that it was ineligible to receive reimbursement from the Fund. Employer appealed to the Board which affirmed and this appeal followed.4
[1163]*1163The sole issue on appeal is whether Employer is entitled to reimbursement from the Fund where it made payment of compensation before the Board formally denied its request for supersedeas. Notwithstanding the Board’s Special Rules that provide for a deemed denial 50 days after the WCJ’s decision, Employer contends that because it is required to make payment within 30 days of the award or be subject to penalties under Section 431(b) of the Act, 77 P.S. § 971(b), if the Board does not act on the supersedeas request within that 30 days, the request for supersedeas should be “deemed denied” as matter of law for purposes of Section 443(a) of the Act, and it is entitled to reimbursement from the Fund.
Deemed denials or, for that matter, deemed approvals, not created by the legislature or the entity’s own regulations or rules, are not favored because they take away the discretion vested in that entity that is charged with making the decision. In several cases in the past, though, dealing with the imposition of penalties and concerned with the possibility that a claimant would not receive the compensation that he or she was due, we have considered applications for a supersedeas deemed denied where the Board took an inordinate amount of time in acting on the request. See, e.g., Cunningham v. Workmen’s Compensation Appeal Board, (Inglis House), 156 Pa.Cmwlth.241, 627 A.2d 218 (1993) (four-month delay in Board’s ruling on a supersedeas request operates as a deemed denial); M.D.S. Laboratories v. Workmen’s Compensation Appeal Board (Munchinski), 125 Pa.Cmwlth.460, 558 A.2d 148 (1989) (10-month delay is tantamount to a deemed denial). Not only is the 43-day delay not the inordinate delay required by those cases, but additionally, all of those cases involved events occurring before the Board issued the Special Rule in 1989 that stated there was a deemed denial if the Board did not act on the request within 50 days from the date of the award. For us to do as Claimant suggests and create a 30 day instead of the 50-day period deemed denial the Board decided that was needed to have the losing party decide whether to appeal, request a supersedeas, to have the prevailing party answer the request and for the Board to decide the request, would be an abuse of discretion on our part.
We recognize, though, that because there is a requirement to pay compensation under the Act within 30 days but no corresponding duty imposed on the Board to act on a supersedeas request within 30 days,5 employers would have been in a quandary in that they may have well had to make the choice of not paying the award and being subject to a penalty or paying the award before the supersedeas request was acted upon and foregoing supersedeas fund reimbursement. While dealing with penalties, Snizaski, which Employer calls [1164]*1164an aberrant decision, resolves that quandary. In that case, we held that it was an abuse of discretion for a WCJ to impose penalties on an employer for not paying an award of benefits within the 30-day period while a supersedeas request was still pending, reasoning that the Board’s Special Rules operated as a stay of an employer’s obligation to pay under the Act while the supersedeas request was being processed or 50 days had past, whichever occurred first. Snizaski, 847 A.2d at 143.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION BY
Judge PELLEGRINI.
ConocoPhillips, formerly Tosco Oil (Employer), appeals an order of the Workers’ Compensation Appeal Board (Board) denying its Application for Supersedeas Fund Reimbursement (Application) because it made a payment on award of benefits which was later reduced to Thomas Logan (Claimant) before there was a denial of the request for supersedeas as required by Section 443(a) of the Workers’ Compensation Act (Act).1
On September 14, 1999, Claimant filed a claim petition alleging that he suffered occupational hearing loss while in the course of his employment with Employer. Workers’ Compensation Judge Joseph Stokes (WCJ Stokes) ordered Employer to pay Claimant 80.86 weeks of hearing loss benefits in a decision circulated March 7, 2001. On March 27, 2001, the Employer appealed and requested supersedeas, the last day to request a supersedeas under the Board’s regulations (Special Rules).2 [1162]*1162Those Special Rules provide that a request for supersedeas must be made within 20 days of the WCJ’s order, and the responding party’s answer is due within 10 days after service of its request. The Board’s decision must be issued within 20 days of receipt of the answer to the request for supersedeas or it is deemed denied. If all the parties and the Board take all of the time allotted by the Special Rules, the Board’s decision, affirmatively or deemed, can be rendered as late as 50 days after the WCJ’ order.
On April 19, 2001, well within the 50 days provided by the Special Rules, Employer’s supersedeas request was granted pending oral argument on the appeal scheduled for June 2001. Unfortunately, unaware that the Board had granted a supersedeas, Employer on the same day paid to Claimant a lump sum hearing loss award of $52,139.96. Through an unexplained delay, the Board did not decide the appeal of the award of the lump sum payment order until January 13, 2003.3 The Board, reversing in part, reduced the amount of Claimant’s award proportionate to the amount of hearing loss attributable to his employment with Employer, netting a reduction in the amount that was due to Claimant of $36,414.84.
Seeking reimbursement of $36,414.84, Employer then filed the Application asserting that although its supersedeas request of March 27, 2001, was granted, not denied by the Board because the award was reduced, it was still entitled to reimbursement from the Supersedeas Fund (Fund) for the overpayment. Acting in its capacity as conservator of the Fund, the Bureau of Workers’ Compensation (Bureau) filed an answer on September 12, 2003, asserting that Employer was not entitled to reimbursement from the Fund because the request for supersedeas was granted rather than denied, and that under Section 443(a) of the Act, Employer had failed to present grounds on which relief could be granted.
The matter was then assigned to Workers’ Compensation Judge Robert Simmons (WCJ Simmons) who denied Employer’s Application in a decision circulated on February 13, 2004. Relying on our then-recent decision in Snizaski v. Workers’ Compensation Appeal Board (Rox Coal Co.), 847 A.2d 139 (Pa.Cmwlth.2004), holding that it was an abuse of discretion for a WCJ to impose penalties on an employer who had delayed payment before the 50 days had passed and the request was deemed denied, WCJ Simmons found that the supersedeas request could not have been deemed denied because the Board had granted the request within 50 days of WCJ Stokes’ decision. Because Employer failed to meet the requirement under Section 443 that the payment was made “as a result” of a denial of its request for a supersedeas, WCJ Simmons held that it was ineligible to receive reimbursement from the Fund. Employer appealed to the Board which affirmed and this appeal followed.4
[1163]*1163The sole issue on appeal is whether Employer is entitled to reimbursement from the Fund where it made payment of compensation before the Board formally denied its request for supersedeas. Notwithstanding the Board’s Special Rules that provide for a deemed denial 50 days after the WCJ’s decision, Employer contends that because it is required to make payment within 30 days of the award or be subject to penalties under Section 431(b) of the Act, 77 P.S. § 971(b), if the Board does not act on the supersedeas request within that 30 days, the request for supersedeas should be “deemed denied” as matter of law for purposes of Section 443(a) of the Act, and it is entitled to reimbursement from the Fund.
Deemed denials or, for that matter, deemed approvals, not created by the legislature or the entity’s own regulations or rules, are not favored because they take away the discretion vested in that entity that is charged with making the decision. In several cases in the past, though, dealing with the imposition of penalties and concerned with the possibility that a claimant would not receive the compensation that he or she was due, we have considered applications for a supersedeas deemed denied where the Board took an inordinate amount of time in acting on the request. See, e.g., Cunningham v. Workmen’s Compensation Appeal Board, (Inglis House), 156 Pa.Cmwlth.241, 627 A.2d 218 (1993) (four-month delay in Board’s ruling on a supersedeas request operates as a deemed denial); M.D.S. Laboratories v. Workmen’s Compensation Appeal Board (Munchinski), 125 Pa.Cmwlth.460, 558 A.2d 148 (1989) (10-month delay is tantamount to a deemed denial). Not only is the 43-day delay not the inordinate delay required by those cases, but additionally, all of those cases involved events occurring before the Board issued the Special Rule in 1989 that stated there was a deemed denial if the Board did not act on the request within 50 days from the date of the award. For us to do as Claimant suggests and create a 30 day instead of the 50-day period deemed denial the Board decided that was needed to have the losing party decide whether to appeal, request a supersedeas, to have the prevailing party answer the request and for the Board to decide the request, would be an abuse of discretion on our part.
We recognize, though, that because there is a requirement to pay compensation under the Act within 30 days but no corresponding duty imposed on the Board to act on a supersedeas request within 30 days,5 employers would have been in a quandary in that they may have well had to make the choice of not paying the award and being subject to a penalty or paying the award before the supersedeas request was acted upon and foregoing supersedeas fund reimbursement. While dealing with penalties, Snizaski, which Employer calls [1164]*1164an aberrant decision, resolves that quandary. In that case, we held that it was an abuse of discretion for a WCJ to impose penalties on an employer for not paying an award of benefits within the 30-day period while a supersedeas request was still pending, reasoning that the Board’s Special Rules operated as a stay of an employer’s obligation to pay under the Act while the supersedeas request was being processed or 50 days had past, whichever occurred first. Snizaski, 847 A.2d at 143. Regarding requests for supersedeas and the needed denial of a supersedeas to obtain reimbursement from the Fund, the Special Rules and Snizaski recognize that once a claimant receives an award of a lump sum payment for retroactive compensation or specific loss benefits and that award is later reversed or modified, the claimant is not required to repay that money. Instead, the employer must resort to repayment from the Fund, which itself is funded by employers and their insurance carriers. If payments are then made to a claimant who was not entitled to those benefits, it drives up workers’ compensation costs and the cost of doing business, not to mention that it takes funds out of the system that could otherwise go to deserving claimants. The Special Rules, as recognized in Sniza-ski give the Board additional time to decide whether there is a substantial possibility of error on the part of the WCJ that would justify the grant of the supersedeas with the attendant effect of protecting the Fund and providing for the definite denial that employers need to obtain reimbursement under Section 443(a) of the Act, with an almost de minimus delay in the claimant receiving compensation.
Because there was no formal or deemed denial at the time payment of compensation was made, Employer failed to meet the prerequisites of Section 443(a) needed to obtain reimbursement from the Fund. Accordingly, the order of the Board is affirmed.
ORDER
AND NOW, this 19th day of January, 2006, the order of the Workers’ Compensation Appeal Board, No. A04-0621, is affirmed.