Connecticut Properties Tri-Town Plaza, LLC v. Seymour Cinema, Inc.

854 A.2d 756, 84 Conn. App. 569, 2004 Conn. App. LEXIS 358
CourtConnecticut Appellate Court
DecidedAugust 17, 2004
DocketAC 24264
StatusPublished
Cited by2 cases

This text of 854 A.2d 756 (Connecticut Properties Tri-Town Plaza, LLC v. Seymour Cinema, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connecticut Properties Tri-Town Plaza, LLC v. Seymour Cinema, Inc., 854 A.2d 756, 84 Conn. App. 569, 2004 Conn. App. LEXIS 358 (Colo. Ct. App. 2004).

Opinion

Opinion

PETERS, J.

This appeal arises out of a contractual dispute between the owner of a shopping center and one of its tenants about costs associated with the construction of a retaining wall to the rear of the tenant’s movie theater. The owner maintains that the tenant bore this obligation because of two provisions in the lease, one requiring the tenant to comply with local land use regulations and another requiring the tenant to pay all costs of construction associated with the *571 movie theater. The tenant maintains that the lease required the owner to assume the costs of the retaining wall required by the town as well as of an earlier smaller retaining wall constructed by the tenant. The trial court held that neither party had a valid claim against the other. Both parties have appealed. We affirm the judgment of the court.

The plaintiff, Connecticut Properties Tri-Town Plaza, LLC, filed a three count complaint 1 in which it sought damages from the defendant, Seymour Cinema, Inc., for breach of a lease that allegedly required the defendant to pay for the construction of a retaining wall in conformity with land use regulations of the town of Seymour (town). The defendant denied liability and filed a counterclaim for the cost of constructing a smaller, prior retaining wall.

The trial court held that the lease did not require the defendant to erect or to pay for a retaining wall at any time. Accordingly, the plaintiff was not entitled to damages, and the defendant, having acted as a volunteer in building the prior retaining wall, was not entitled to reimbursement. On appeal to this court, each of the parties asks us to overturn some part of the judgment of the trial court.

The underlying facts are largely stipulated. On April 16, 1997, the plaintiff and the defendant executed a letter of intent for a ground lease of approximately 29,300 square feet of space on which the defendant was to construct a movie theater. Thereafter, the town planning and zoning commission (commission) approved a site development plan for this construction. On July 2, 1997, the plaintiff and the defendant entered into the ground lease. The lease subjected the demised *572 premises to all town laws, ordinances, rules and regulations.

Although the site development plan did not call for the construction of a retaining wall to the rear of the movie theater, the defendant constructed a retaining wall (initial retaining wall) in order to bring a fire access road into compliance with the town fire code. After receiving approval from the town fire inspector, the movie theater opened for business on or about May 20, 1998.

Some time later, the town became dissatisfied with the initial retaining wall. It so informed both the plaintiff and the defendant. Although the town did not pursue any enforcement action against the defendant, it required the plaintiff to build a new, higher retaining wall (higher retaining wall) as a condition for obtaining approval for the construction of a new building at the shopping center. The plaintiff constructed the higher retaining wall and, in the present litigation, appeals from the trial court’s rejection of its claim that the defendant must pay the costs associated with this construction.

I

The issues raised by the plaintiffs appeal are twofold. The plaintiff maintains that the trial court improperly decided that (1) the defendant had fulfilled its lease obligation to comply with town planning and zoning regulations and (2) the lease did not obligate the defendant to build the higher retaining wall required by the town. We are not persuaded.

A

The trial court rejected the plaintiffs claim that the defendant was obligated to pay for the construction of the higher retaining wall because the defendant, allegedly in breach of its contract, had failed to comply with *573 the unambiguous terms of the lease requiring the movie theater to comply with all ordinances, laws, rules and regulations of the town. Although the town permitted the movie theater to operate without the higher retaining wall, the plaintiff maintains that the defendant had a continuing obligation to undertake the construction once the town insisted that it be done. The court found, however, that the higher retaining wall “was solely a precondition and requirement of the plaintiffs obtaining approval for the expansion of retail space” at the shopping center. Accordingly, the trial court found, by a preponderance of the evidence, that “the defendant, in constructing the [movie theater], met all of the requirements of the town . . . .”

The plaintiff disagrees with the trial court’s ruling. Its disagreement does not turn on a question of contract interpretation, because the court did not question the defendant’s contractual obligation to comply with applicable land use regulations. Instead, the plaintiff disagrees with the court’s finding of fact that the defendant had fulfilled this obligation. We review such a finding of fact by applying the clearly erroneous standard. Practice Book § 60-5; see also Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980).

The crux of the plaintiffs disagreement with the court’s finding is its claim that the defendant bore responsibility for constructing the higher retaining wall to conform with town regulations even though the town chose not to enforce this obligation. In the plaintiffs view, it is irrelevant that the town did not insist on the required construction until the plaintiff sought approval for the construction of an additional building.

The record at trial, however, supports the findings of the trial court. The commission originally approved a site development plan for the construction of the *574 movie theater without requiring construction of a retaining wall to the rear of the theater. The defendant constructed the initial retaining wall to facilitate the construction of a fire access road required by the town fire code.

It was only after the opening of the movie theater that the town became dissatisfied with the initial retaining wall. Although the town so informed both the plaintiff and the defendant, it never pursued any enforcement action against the defendant. Instead, the town threatened not to issue a permanent certificate of occupancy for the movie theater unless the initial retaining wall was replaced with a higher one. The town did not act on this threat. 2 It did, however, withhold approval for a new building at the shopping center until the plaintiff agreed to build the new, higher retaining wall. 3 The trial court found that the higher retaining wall “was solely a precondition and requirement of the plaintiffs obtaining approval for the expansion of retail space” at the shopping center. The plaintiff constructed the higher retaining wall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips v. Phillips
922 A.2d 1100 (Connecticut Appellate Court, 2007)
Jo-Ann Stores, Inc. v. Property Operating Co.
880 A.2d 945 (Connecticut Appellate Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
854 A.2d 756, 84 Conn. App. 569, 2004 Conn. App. LEXIS 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connecticut-properties-tri-town-plaza-llc-v-seymour-cinema-inc-connappct-2004.