Concrete Recovery, L.L.C. v. Nestle Purina Petcare Co.

2026 Ohio 692
Ohio Court of Appeals·Decided March 2, 2026·No. CA2025-05-042·Published

Opinion

IN THE COURT OF APPEALS

TWELFTH APPELLATE DISTRICT OF OHIO CLERMONT COUNTY

CONCRETE RECOVERY LLC, :

CASE NO. CA2025-05-042

Appellant, :

OPINION AND

vs. : JUDGMENT ENTRY 3/2/2026

NESTLE PURINA PETCARE : COMPANY, et al., :

Appellees.

:

CIVIL APPEAL FROM CLERMONT COUNTY COURT OF COMMON PLEAS Case No. 2025 CVH 00268

Sebaly Shillito + Dyer, and Toby K. Henderson and Kaitlyn C. Meeks, for appellant.

Stites & Harbison PLLC, and William G. Geisen and Cassandra L. Welch, for appellee Nestle Purina Petcare Company.

UB Greensfelder LLP, and Jesse R. Lipcius and Kyle D. Greene, for appellee Lithko Contracting, LLC

OPINION

SIEBERT, J.

{¶ 1} Concrete Recovery LLC appeals the trial court's dismissal of Concrete Recovery's declaratory judgment, breach of contract, and promissory estoppel claims

against Nestle Purina Petcare Company ("Nestle").1 The trial court determined that Concrete Recovery failed to state a claim for which it could recover against Nestle. Concrete Recovery argues the trial court erred because Nestle allegedly accepted Concrete Recovery's bid for concrete pouring work and, among other things, gave Concrete Recovery "formal notice to proceed" with that work. Assuming the allegations of its amended complaint (as well as attached exhibits) are true, we agree that Concrete Recovery set forth actionable claims against Nestle.

Background

{¶ 2} In October 2024, Nestle issued a request for bids (entitled the "Scope of Work") for concrete work in connection with construction of Nestle's petfood factory in Batavia, Clermont County (the "Project"). Generally speaking, the 28-page Scope of Work described the services and labor needed as well as the responsibilities of any contractor whose bid Nestle accepted. Among other provisions, the Scope of Work stated:

1.3.1 CONTRACT DOCUMENTS

The Contract Documents, together with all documents incorporated by reference therein . . . including any drawings, specifications, 3D Model, Addenda, Document Releases, Document Supplement Information (DSI's), Request for lamination (RFI's), Submittals, or other General Documents that are issued by [Nestle], will be distributed via electronic distribution . . . Contractor shall be responsible to determine, extrapolate, and refer to all applicable drawing and specifications to determine the complete contract scope of work.

1. Concrete Recovery also asserted claims for tortious interference with a contract and business relationship against Lithko Contracting, LLC, alleging that Lithko ultimately performed the work Nestle initially awarded to Concrete Recovery. The fact that these claims against Lithko remains unresolved "is irrelevant" and does not bar the instant appeal for lack of a final and appealable order because "at this point [Concrete Recovery] cannot recover from [Lithko]." Wisintainer v. Elcen Power Strut Co., 67 Ohio St.3d 352, 355 (1993). Stated differently, because the trial court found Concrete Recovery did not have a contract with Nestle and did not reasonably or foreseeably rely on any promises made by Nestle, Lithko cannot be found to have interfered with Concrete Recovery and Nestle's alleged contract or business relationship. We therefore conclude this appeal is properly before us.

(Emphasis deleted.). The Scope of Work further stated that the selected contractor would have to use Nestle's "project management and collaboration system . . . for all project documentation" and required "Contractor to regularly check and review updated documents as they are added." To facilitate this, the Scope of Work stated "[a]pplicable team members of the Contractor are required to complete a free, one-hour Contractor training certification course . . . within TWO (2) weeks following contract execution." (Emphasis deleted.). Finally, as relevant to this opinion, the Scope of Work noted that "[a]ny discrepancies between [the Scope of Work] and the Contract shall be brought to the attention of [Nestle] prior to signing the contract and [Nestle] shall provide guidance on the controlling terms."

{¶ 3} That same month, Concrete Recovery submitted an estimate to perform the Project for $471,277 (the "Bid"). The Bid provided that it may be accepted by telephone or email. The Bid further stated, "We do require half of the estimate prior to day or day of starting the job, the remaining balance is due upon completion of the job" and "We do offer a one year warranty on anything over a hairline fracture." Concrete Recovery alleged that "[o]n or about October 14, 2024 . . . [Nestle] informed Concrete Recovery of acceptance [of the Bid] by phone call." Nestle does not contest the phone call occurred on this date, but asserts it was "to inform Concrete Recovery it had been selected as the preferred bidder" for the Project.

{¶ 4} After this call, Concrete Recovery completed forms and paperwork required by Nestle and cooperated with being added to Nestle's vendor management system. Concrete Recovery workers also completed online orientation/safety training with Nestle and provided Nestle with a certificate of liability insurance as required by the Scope of Work. In late October, Nestle sent Concrete Recovery an "Amended Notice of Commencement" which included an exhibit listing "all contractors contracting directly with

[Nestle]." The list included "Concrete Restorations, 150E Forest Ave, South Lebanon, Ohio 45065." Although its name was not correct, the listed address was that of Concrete Recovery's office.

{¶ 5} On November 1, 2024, Nestle emailed a "Letter of Intent" to Concrete Recovery which stated Nestle's "intention to engage in a direct agreement with [Concrete Recovery] for work associated with the [the Project]." The letter further invited Concrete Recovery to advise Nestle "if there are other critical path items to be addressed while we finalize this agreement" and that Nestle "sincerely appreciate[s] the opportunity to work with you as we continue to develop our pending agreement." In another email sent later that day, Nestle stated, "work is slated to start on Monday [November 4, 2024]. We won't have the contract in hand by then. Attached is our formal notice to proceed. Please let me know if this will work for you guys to move forward with the work."

{¶ 6} However, on November 4, 2024, Nestle emailed Concrete Recovery advising that "[Nestle] will not be able to comply with the request for downpayment within the 14-day period . . . Given the current schedule demands and financial considerations, [Nestle] will not be proceeding with this contract at this time."

{¶ 7} Concrete Recovery subsequently filed suit. Concrete Recovery's amended complaint (the operative complaint on appeal) sought a declaratory judgment that the parties entered into a binding contract. Concrete Recovery also claimed Nestle breached the parties' contract. Finally, Concrete Recovery pled a claim for promissory estoppel, asserting that if no contract between the parties existed, Nestle's selection of the Bid and its later directive to "move forward with the work" were promises that reasonably and foreseeably induced Concrete Recovery to incur time and expense to get ready for the project.

{¶ 8} Nestle filed a motion to dismiss the amended complaint. The trial court

granted Nestle's motion, concluding that there was no valid and enforceable contract between Nestle and Concrete Recovery. The trial court found the "Scope of Work itself is not a contract and anticipates that important matters such as discrepancies must be addressed prior to the execution of a formal, written contract." The decision also rested on the Letter of Intent, its reference of Nestle's "intention to engage in a direct agreement" with Concrete Recovery, and its inquiry into whether Concrete Recovery "has other critical path items to be addressed while we finalize this agreement." (Emphasis deleted.).

Free access — add to your briefcase to read the full text and ask questions with AI

Concrete Recovery, L.L.C. v. Nestle Purina Petcare Co., 2026 Ohio 692 (Ohio Ct. App. 2026).

2026 Ohio 692 (Concrete Recovery, L.L.C. v. Nestle Purina Petcare Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sterling Constr., Inc. v. Alkire
2014 Ohio 2897 (Ohio Court of Appeals, 2014)
Buckner v. Bank of New York
2014 Ohio 568 (Ohio Court of Appeals, 2014)
White Hat Management, L.L.C. v. Ohio Farmers Insurance
856 N.E.2d 991 (Ohio Court of Appeals, 2006)
Holloway v. Moritz
2019 Ohio 83 (Ohio Court of Appeals, 2019)
N. Side Bank & Trust Co. v. Trinity Aviation, L.L.C.
2020 Ohio 1470 (Ohio Court of Appeals, 2020)
Conaway v. Mt. Orab
2021 Ohio 4041 (Ohio Court of Appeals, 2021)
Byrd v. Faber
565 N.E.2d 584 (Ohio Supreme Court, 1991)
York v. Ohio State Highway Patrol
573 N.E.2d 1063 (Ohio Supreme Court, 1991)
Wisintainer v. Elcen Power Strut Co.
617 N.E.2d 1136 (Ohio Supreme Court, 1993)
Smith-Knabb v. Vesper
2023 Ohio 259 (Ohio Court of Appeals, 2023)