Concrete Materials of Georgia, Inc. v. Smith & Plaster Co.

195 S.E.2d 219, 127 Ga. App. 817, 1973 Ga. App. LEXIS 1656
CourtCourt of Appeals of Georgia
DecidedJanuary 5, 1973
Docket47475
StatusPublished
Cited by11 cases

This text of 195 S.E.2d 219 (Concrete Materials of Georgia, Inc. v. Smith & Plaster Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concrete Materials of Georgia, Inc. v. Smith & Plaster Co., 195 S.E.2d 219, 127 Ga. App. 817, 1973 Ga. App. LEXIS 1656 (Ga. Ct. App. 1973).

Opinions

Eberhardt, Presiding Judge.

The lease contract called for and contemplated completion and delivery of the building by Lurlee, the owner, to Scott-Foresman, the lessee, on March 1, 1969, "or as soon thereafter as the building to be constructed by the lessor . . . can, with due diligence on lessor’s part, be completed in accordance with the Plans and Specifications.”

Plaintiff, the prime contractor, asserts that the building was not so completed and delivered until some four months after the date contemplated by the lease and that as a result the owner lost four months of rentals which the owner has back-charged to plaintiff by deducting the amount from its final payment under the construction contract.

The defendant, subcontractor, contends that the deduction of the rentals by the owner-lessor was illegal and cannot be passed on even if defendant was the cause of the delay in completion because of the provision in the prime construction contract that: "The work to be performed under this [820]*820contract shall be commenced within ten days of notice to proceed and completed within 150 days. Work must be completed by March 1, 1969, as tenant must vacate present facilities. Liquidated damages of $4,400 plus costs will be assessed.” Defendant’s position is that the damages for delay could in no event exceed $4,400.

If this were a proper and lawful limitation as to the amount of damages which the owner might recover from the prime contractor, we would agree that he would be thus limited as to recovery against his subcontractor, for otherwise it would enable the prime contractor unjustly to enrich himself by recovering damages which he had not, in fact, suffered.

But, as we view it, this provides a penalty within the contemplation of Code § 20-1403, for the amount of actual damages is readily capable of computation, and, additionally, the provision "plus costs,” whatever that may mean, rendered it uncertain. Consequently, we doubt that it is sustainable under Code § 20-1402. Certainly the damages for loss of rentals are directly dependent upon the element of time. See Florence Wagon Works v. Salmon, 8 Ga. App. 197 (68 SE 866).

The lease provision postpones the time for completion and delivery of the building if it appears that "with due diligence” the contractor was unable to follow the plans and specifications and meet the March 1 schedule. Elements of weather, strikes, inability to secure the necessary materials or labor, etc., are to be considered. Whether there was "due diligence” by the lessor in getting construction completed is a jury issue.

Assuming that the evidence fully authorizes a finding that neither the lessor nor the prime contractor has been responsible for the delay (there is much conflicting evidence on the issue), and that the whole responsibility for the delay is chargeable to the subcontractor (about which there is much conflicting evidence), it appears from the testimony of the manager of Scott-Foresman, the lessee, that the warehouse portion of the building was available to and was used [821]*821by it for the intended placing of books and supplies therein from early May. Scott-Foresman says that it had a security guard there to protect its stored property from May 5. And the manager also testified that the office portion of the building became available and they moved their equipment into it "around June 12.” The specified rental of $4,400 per month included both the office and the warehouse space. Consequently, it appears that the lessee was liable for the reasonable rental of the warehouse from the time it became available, and for the whole rental when both portions became available. Whether the owner-lessor in fact collected from that time or from some other time is of no concern to either the prime contractor or the subcontractor. It is clear that the owner could not hold them as sureties on the lease, and that the only allowable damages for loss of rentals is from the time the building was promised — March 1, 1969, or such later time as may, under the evidence, be an excusably postponed date — until the building or portions of it became available and the lessee entered under the lease. In no event was the warehouse rental loss recoverable beyond the time from March 1 to the early part of May, when Scott-Foresman began its use, and likewise, the loss of rentals for the office portion was, in any event, only from March 1 to June 12. Since the lessee entered at times other than the first of the month, the rentals should be apportioned, and there should be an apportionment as between the warehouse and the office, applying the respective costs to the rental formula in the lease, in order to arrive at a proper amount representing loss of rentals as an item of recoverable damages.

"Where a builder agrees to erect a building within a certain time, knowing that it has been leased from the time named for its completion, and breaks the stipulation as to time, he is ordinarily liable to the owner for loss of rent, but not for loss of interest on the capital invested in the building, nor for damages paid by the owner to a lessee in accordance with a stipulation in the lease contract, as to which the builder had no knowledge.” Albany Phosphate [822]*822Co. v. Hugger Bros., 4 Ga. App. 771 (3a) (62 SE 533).

It is clear that the defendant knew that the building was being constructed for leasing to Scott-Foresman, for in communications from it to plaintiff, beginning September 30, 1968, and continuing until the work of the subcontractor was completed it is referred to as the "Scott-Foresman Warehouse job.” It is not contended that the $4,400 per month rental is unreasonable. Thus, we conclude that plaintiff is entitled to recover an amount equivalent to the rentals actually lost due to delay on the part of the defendant in completing its work on the building. If the delays are attributable to other causes, but in part to the delay of the defendant, the loss should be properly apportioned. In no event should the plaintiff recover damages for delay attributable to it. Enumerations of error 1 and 3 are without merit.

Enumerations of error 2 and 4 raise the issue of whether the expenses of Scott-Foresman incurred because the premises were not ready at the agreed time were too remote for recovery by the prime contractor against his subcontractor. The law is clearly stated in Albany Phosphate Co. v. Hugger Bros., 4 Ga. App. 771 (3a), supra, where it is held that the contractor was not liable "for loss of interest on the capital invested in the building, nor for damages paid by the owner to a lessee in accordance with a stipulation of the lease contract, as to which the builder had no knowledge.” (Emphasis supplied.) Accord: Brockman v. Rhodes, 33 Ga. App. 435, 436 (127 SE 153), where we held that the expenses of paying a manager and clerks whom the tenant had employed to begin work on the date the building was to be completed and delivered to it are too remote and not recoverable. See also Sanford-Brown Co. v. Patent Scaffolding Co., 199 Ga. 41 (33 SE2d 422), where there was a similar ruling.

We have read carefully the lease between the owner, Lurlee, Inc., and the lessee, Scott-Foresman, and we can find no provision in it under which the owner could be held for or charged with the items of damage on which the lessee [823]*823made claim against the lessor and for which the owner-lessor backcharged Smith & Plaster, Co., and which Smith & Plaster, Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Legacy Academy, Inc. v. Doles-Smith Enterprises, Inc.
812 S.E.2d 72 (Court of Appeals of Georgia, 2018)
Dixie Roof Decks, Inc. v. Borggren/Dickson Construction, Inc.
395 S.E.2d 19 (Court of Appeals of Georgia, 1990)
Powers Ferry Construction, Inc. v. Commerce Builders, Inc.
381 S.E.2d 755 (Court of Appeals of Georgia, 1989)
Pottinger v. Cross
317 S.E.2d 850 (Court of Appeals of Georgia, 1984)
United California Bank v. Prudential Insurance Co. of America
681 P.2d 390 (Court of Appeals of Arizona, 1983)
Barbush v. Oiler
281 S.E.2d 359 (Court of Appeals of Georgia, 1981)
Szabo Associates, Inc. v. Peachtree-Piedmont Associates
234 S.E.2d 119 (Court of Appeals of Georgia, 1977)
Szabo Assoc. v. PEACHTREE &C. ASSOC.
234 S.E.2d 119 (Court of Appeals of Georgia, 1977)
White Repair & Contracting Co. v. Krasnoff
227 S.E.2d 82 (Court of Appeals of Georgia, 1976)
Corr v. Aaron Rents, Inc.
222 S.E.2d 150 (Court of Appeals of Georgia, 1975)
Concrete Materials of Georgia, Inc. v. Smith & Plaster Co.
195 S.E.2d 219 (Court of Appeals of Georgia, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
195 S.E.2d 219, 127 Ga. App. 817, 1973 Ga. App. LEXIS 1656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concrete-materials-of-georgia-inc-v-smith-plaster-co-gactapp-1973.