Company of Kingston v. Latona Trucking, Inc.

159 F.3d 80, 1998 U.S. App. LEXIS 26788
CourtCourt of Appeals for the Second Circuit
DecidedOctober 21, 1998
Docket97-9236
StatusPublished
Cited by3 cases

This text of 159 F.3d 80 (Company of Kingston v. Latona Trucking, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Company of Kingston v. Latona Trucking, Inc., 159 F.3d 80, 1998 U.S. App. LEXIS 26788 (2d Cir. 1998).

Opinion

159 F.3d 80

In the Matter of the Application to Compel Arbitration
Between S & R COMPANY OF KINGSTON, a New York
General Partnership, and Hartford Fire
Insurance Company,
Petitioners-Appellants,
v.
LATONA TRUCKING, INC., Respondent-Appellee.

Docket No. 97-9236.

United States Court of Appeals,
Second Circuit.

Argued April 24, 1998.
Decided Oct. 21, 1998.

Mark T. Walsh, Gleason, Dunn, Walsh & O'Shea, Albany, N.Y., for Petitioners-Appellants.

J. Scott Greer, Lewis & Greer, P.C., Poughkeepsie, N.Y., for Respondent-Appellee.

Before: WALKER and CALABRESI, Circuit Judges, and RESTANI,* Judge.

JOHN M. WALKER, JR., Circuit Judge:

Petitioners-appellants S & R Company of Kingston ("S & R") and Hartford Fire Insurance Company ("Hartford") appeal from the September 8, 1997, judgment of the United States District Court for the Northern District of New York (Thomas A. McAvoy, Chief Judge ) denying their petition to compel arbitration under Section 4 of the Federal Arbitration Act, 9 U.S.C. § 4, on the ground that they waived their right to arbitration by engaging in extensive pre-trial litigation to the prejudice of respondent-appellee Latona Trucking, Inc. ("Latona").

AFFIRMED.

BACKGROUND

In July 1995, Latona entered into a contract with S & R,1 the owner and developer of a construction project at the Hudson Valley Plaza in Kingston, New York. Latona was to perform site work on the construction project. The contract between S & R and Latona contained an arbitration clause that provided:

In the event any dispute arises between the Parties relative to this contract which cannot be resolved by the Parties within thirty (30) days from the date first noticed, the Parties agree to refer the dispute to an arbitrator in accordance with the rules of the American Arbitration Association.

Hartford was the surety on a payment bond obtained by S & R to secure payment of the contract price to Latona. The payment bond included a clause incorporating the contract into the bond, which read as follows:

WHEREAS, PRINCIPAL [S & R] has entered into a contract with OBLIGEE [Latona] dated July 12, 1995, designated as Phase 1+ Site Work ... which is made a part hereof as fully as if copied verbatim herein.

Disputes arose between the parties regarding work completion and payments. On February 20, 1996, Latona commenced an action in the district court to collect $650,000 from Hartford under the payment bond as a result of S & R's alleged failure to make payments due under the contract. In answering the complaint, Hartford did not include "arbitration and award" as an affirmative defense.

On June 28, 1996, a stipulation and consent order was filed allowing S & R to intervene as a defendant. Latona thereafter served an amended complaint seeking to recover attorney's fees from S & R, pursuant to New York General Obligations Law § 5-322.3, for failure to file the payment bond with the County Clerk. In answering the amended complaint, neither Hartford nor S & R pleaded "arbitration and award" as an affirmative defense. Moreover, S & R counterclaimed against Latona alleging breach of contract.

The action continued with all parties actively participating in the discovery process, which included extensive document production, numerous interrogatories, and several depositions. The parties also negotiated and filed a Joint Civil Case Management Plan, resorted to the court to resolve discovery disputes, and participated in two settlement conferences. On June 5, 1997, the assigned magistrate judge held a telephone conference regarding petitioners' request to substitute counsel. During the course of that conference, petitioners' new attorneys moved for an order to extend the May 15, 1997 deadline for filing pre-trial motions. Specifically, petitioners intended, inter alia, to apply for a stay of the proceedings pending enforcement of the arbitration clause contained in the contract. By an order dated June 6, 1997, the magistrate judge granted petitioners' request for substitution of counsel, but denied their request for leave to file pre-trial motions, and the action was scheduled for trial on October 20, 1997.

Petitioners appealed the magistrate judge's order to the district court and also filed an independent petition, pursuant to 9 U.S.C. § 4, to compel arbitration of the pending action. In its Memorandum Decision and Order dated September 8, 1997, denying the petition to compel arbitration, the district court held that S & R and Hartford had waived their right to arbitration by actively participating for 15 months in pre-trial litigation, including extensive discovery, to the prejudice of Latona. See S & R Co. v. Latona Trucking, Inc., 984 F.Supp. 95, 101-03 (N.D.N.Y.1997).

Petitioners raise three arguments on appeal to this court: (1) that the district court erred in not referring the issue of waiver to the arbitrator; (2) that petitioners did not engage in sufficient litigation or sufficiently prejudice Latona to warrant a finding of waiver; and (3) that the "no waiver" clause found in the arbitration rules precludes a finding of waiver. For the following reasons, we affirm the district court's denial of petitioners' motion to compel arbitration.

DISCUSSION

I. Propriety of District Court Deciding Issue of Waiver

At the outset, petitioners argue that the district court should not have decided the issue of waiver itself, but rather should have referred the matter to the arbitrator. The district court, relying on Doctor's Assocs., Inc. v. Distajo, 66 F.3d 438 (2d Cir.1995), and other cases, held that it could decide the waiver issue in light of petitioners' active participation in the litigation for 15 months. In Distajo, the court reviewed the existing case law and determined that, although ordinarily a defense of waiver brought in opposition to a motion to compel arbitration under § 4 is a matter to be decided by the arbitrator, the district court could properly decide the question when the party seeking arbitration had already participated in litigation on the dispute.

Petitioners rely on the Distajo court's statement that it was "bound ... by our most recent precedent" to allow a district court to decide the issue of waiver, 66 F.3d at 456, to argue that Distajo is not binding precedent because in so holding it misinterpreted the prior cases. This argument is without merit. Even assuming the Distajo court was not required to decide the way it did, once it did so, its decision became binding precedent. See Jones v. Coughlin, 45 F.3d 677, 679 (2d Cir.1995) (per curiam ) ("A decision of a panel of this Court is binding unless and until it is overruled by the Court en banc or by the Supreme Court."). Distajo has not been overturned (indeed, it has been followed in recent cases, see, e.g., PPG Indus., Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jock v. Sterling Jewelers, Inc.
564 F. Supp. 2d 307 (S.D. New York, 2008)
Republic Insurance v. Paico Receivables, LLC
383 F.3d 341 (Fifth Circuit, 2004)
Eastern Fish Co. v. South Pacific Shipping Co., Ltd.
105 F. Supp. 2d 234 (S.D. New York, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
159 F.3d 80, 1998 U.S. App. LEXIS 26788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/company-of-kingston-v-latona-trucking-inc-ca2-1998.