Commonwealth v. Semanderes

531 A.2d 815, 109 Pa. Commw. 505, 1987 Pa. Commw. LEXIS 2485
CourtCommonwealth Court of Pennsylvania
DecidedSeptember 24, 1987
DocketAppeals, 1735 C.D. 1986 and 1876 C.D. 1986
StatusPublished
Cited by9 cases

This text of 531 A.2d 815 (Commonwealth v. Semanderes) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth v. Semanderes, 531 A.2d 815, 109 Pa. Commw. 505, 1987 Pa. Commw. LEXIS 2485 (Pa. Ct. App. 1987).

Opinion

Opinion by

Judge Doyle,

The Commonwealth of Pennsylvania, Department of Transportation (DOT) and Stavro N. Semanderes, t/a Odyssey Contracting Company (Odyssey), cross-appeal from an order of the Board of Claims (Board) awarding Odyssey $30,615.77 for bridge repairs. We affirm the decision of the Board.

The underlying facts found by the Board in this case are not in dispute. In June 1982, DOT and Odyssey entered into a contract for repair work to the Memorial Bridge in Connellsville, Pennsylvania. The initial total contract price was $294,392.50, which amount included $86,355 for Item 2090-0502 (Item) entitled “Concrete Bridge Deck Repair, Special.” Under this Item, Odyssey was to repair 4,545 square feet of the bridge at a cost of $19 per square foot by removing existing con *507 Crete from areas outlined by DOT inspectors, cleaning the holes with compressed air, and filling them with a quick setting material.

Paragraph 3(b) of the Item provided in full:

(b) Preparation of Surface.
The limits of repair areas will be determined and delineated by the engineer. The contractor shall outline the delineated areas with a % inch deep saw cut.
During the removal of deteriorated concrete should it be found that the area of deteriorated concrete extends beyond the initial saw-cut peripheries, new saw-cuts for repair limits shall be made.
The concrete shall be removed to a depth sufficient to provide a minimum %-inch clearance around all reinforcement bars in the top mat.
During the removal of deteriorated concrete the sound concrete surrounding the perimeter of the repair area shall be slightly undercut as shown in the attached sketch.
Exposed reinforcement bars shall be sandblasted or wire brushed to remove rust and/or corrosion. All portions of damaged or heavily corroded reinforcement bars shall be removed and replaced in kind by satisfactorily splicing to the remaining reinforcement bars.
All removal areas shall be blown clear with oil-free compressed air and protected against any contaminates detrimental to the bond of the patching material. (Emphasis added).

Odyssey began working on the bridge deck on September 27, 1982. In accordance with DOTs interpretation of the contract at that time, Odyssey, removed concrete to a minimum depth of %-inch below the top mat *508 of reinforcement bars (rebars) 1 in every instance, regardless of whether the concrete below the top mat of rebars was sound or deteriorated. On September 30, however, after consultation with DOTs inspector in charge of the bridge contract, Odyssey began to remove concrete only down to the top mat of rebars, and would remove it to a minimum depth of %-inch below the top mat of the rebars only if the bond between the top bar and concrete was broken or if the concrete was deteriorated below the bar. This continued until October 14.

On October 15, however, a different DOT representative informed Odyssey that the contract required Odyssey to remove all concrete to a minimum depth of %- inch below the top mat of rebars, regardless of deterioration, and if deterioration extended to a depth greater than %-inch, then the deteriorated concrete also had to be removed. For the remainder of all repair work performed, Odyssey complied with DOTs interpretation of the contract.

Between October 1 and October 14, Odyssey performed 1,049.2 square feet of bridge repair work consistent with its interpretation of the contract. From October 15 until November 9, it completed the remaining bid quantity of 3,495.8 square feet in accordance with DOTs interpretation. In addition, at DOT’s request, Odyssey performed 2,109.9 square feet of repair work in excess of bid quantity in a manner consistent with DOT’s interpretation of the contract, and it sent a letter to DOT on November 15 requesting an increase of $6.57 per square foot for the additional work, making the unit price $25.57 per square foot for that segment of the work. On February 18, 1983, approximately two *509 months after all bridge deck repair work was completed, DOT authorized payment of $25.57 per square foot on all repair work in excess of the contract quantity of 4,545 square feet.

DOT ultimately paid Odyssey the following amounts: 1) $11.18 per square foot for 1000.4 square feet of work performed prior to October 15, 1982; 2 2) $19 per square foot for the remaining 3,495.8 square feet under the contract; and 3) $25.57 per square foot for the 2,109.9 square feet of work in excess of the contract quantity.

Odyssey commenced this suit before the Board, seeking to recover costs for what it contends was excessive concrete removal from September 27 through September 30 and from October 15 through November 23, 1982, the periods during which it performed the repairs in accordance with DOT’s interpretation of the contract. The Board concluded that the contract language as to depth of removal was ambiguous, and applied the contra proferentem rule of construction against DOT, the drafter of the contract. Construing the contract under Odysseys interpretation, the Board held that DOT modified its terms by requiring Odyssey to remove all concrete to a minimum depth of %-inch below the top mat of rebars, irrespective of deterioration, instead of to the top mat of rebars, and awarded Odyssey $30,615.77 plus interest. DOT appeals to this Court, and Odyssey cross-appeals as to damages only.

In reviewing orders of the Board of Claims, this Courts scope of review is limited to determining whether an order of the Board is in accordance with law and *510 whether its findings of fact are supported by substantial evidence. Larry Armbruster and Sons, Inc. v. State Public School Building Authority, 95 Pa. Commonwealth Ct. 310, 505 A.2d 395 (1986). Contract interpretation and construction is a question of law uniquely within the province of the court. Department of Transportation v. Bracken Construction Co., 72 Pa. Commonwealth Ct. 620, 457 A.2d 995 (1983).

DOT argues that since the contract was clear and unambiguous as to removal of concrete, the Board erred by construing the contract under Odysseys interpretation. We cannot agree.

It is axiomatic that when the words of a contract are clear and free from ambiguity, the intent of the parties is to be determined solely from the express language of the agreement. Robert F. Felte, Inc. v. White, 451 Pa. 137, 302 A.2d 347 (1973).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nazareth Mutual Ins. Co. v. PA Ins. Dept.
Commonwealth Court of Pennsylvania, 2023
C.M. Erb v. City of Lancaster
Commonwealth Court of Pennsylvania, 2018
Twp. of Lower Yoder v. Borough of Westmont
Commonwealth Court of Pennsylvania, 2017
Public School Bldg. Auth. v. Quandel
585 A.2d 1136 (Commonwealth Court of Pennsylvania, 1991)
Shannopin Mining Co. v. Commonwealth
556 A.2d 488 (Commonwealth Court of Pennsylvania, 1989)
Commonwealth, Department of Transportation v. Manor Mines, Inc.
544 A.2d 538 (Commonwealth Court of Pennsylvania, 1988)
McGinley Maintenance, Inc. v. Commonwealth
542 A.2d 618 (Commonwealth Court of Pennsylvania, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
531 A.2d 815, 109 Pa. Commw. 505, 1987 Pa. Commw. LEXIS 2485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-v-semanderes-pacommwct-1987.