Commonwealth Edison Co. v. Illinois Commerce Comm'n

2014 IL App (1st) 130211
Procedural entryThis page is a short order in Commonwealth Edison Co. v. Illinois Commerce Comm'n. Read the opinion of the Court — 2014 IL App (1st) 132011
Appellate Court of Illinois·Decided August 5, 2014·No. 1-13-2011, 1-13-2012 cons.·Unpublished

Opinion

2014 IL App (1st) 132011

FOURTH DIVISION July 31, 2014

Nos. 1-13-2011 & 1-13-2012 (Cons.)

COMMONWEALTH EDISON COMPANY, ) ) Petitioner, ) ) v. ) Petition for Review of Orders ) of the Illinois Commerce ) Commission in ILLINOIS COMMERCE COMMISSION; ) Docket Nos. CITIZENS UTILITY BOARD; THE CITY OF ) 11-0588 and 11-0662 CHICAGO; and THE PEOPLE OF THE STATE ) OF ILLINOIS, ) ) Respondents. )

JUSTICE EPSTEIN delivered the judgment of the court, with opinion. Presiding Justice Howse and Justice Lavin concurred in the judgment and opinion.

OPINION

¶1 In this consolidated appeal, petitioner Commonwealth Edison (ComEd), challenges two

orders of respondent, the Illinois Commerce Commission (the Commission) interpreting and

applying section 16-125(e) of the Public Utilities Act (220 ILCS 5/16-125(e) (West 2010)) (the

Act) to power interruptions that resulted from a series of severe storm systems that hit northern

Illinois in 2011 and caused damage to ComEd's electric delivery system. The Commission

concluded that, pursuant to the language of section 16-125(e), ComEd was liable for damages to

the affected consumers. However, with the exception of the storm that occurred on July 11,

2011, the Commission granted ComEd a waiver of liability under section 16-125(e)(1) of the Act Nos. 1-13-2011 & 1-13-2012 (Cons.)

where the power interruption resulted from "[u]npreventable damage due to weather events or

conditions." 220 ILCS 5/16-125(e)(1) (West 2010).

¶2 ComEd now contends that the statute only applies where there is a continuous power

outage caused by a single event that interrupts power to over 30,000 of the same customers for

the same four-hour period and that the Commission erred in deciding that section 16-125(e)(1)

applied to the "numerous dispersed and discrete interruptions at different times, in different

places, and for different reasons." ComEd further contends that it is entitled to a full waiver of

liability for the July 11, 2011 storm. ComEd also argues that the Commission unlawfully

precluded ComEd from recovering its cost of providing notice to the customers. For the reasons

that follow, we dismiss appeal No. 1-13-2012 and affirm the Commission's decision in appeal

No. 1-13-2011.

¶3 BACKGROUND

¶4 Several storm systems struck northern Illinois in 2011 causing significant damage to

thousands of ComEd's customers. One of the storms occurred on February 1, 2011 (Winter 2011

Storm). Six storms occurred in the summer of 2011 (Summer 2011 Storms), specifically on June

8, June 21, June 30, July 11, July 22, and July 27, 2011. More than 2 million of ComEd's

customers experienced a power interruption. After some customers made claims for damages

resulting from the power outages, ComEd filed two verified petitions before the Commission.

Docket No. 11-0588 was filed on August 18, 2011 and involved the Summer 2011 Storms.

Docket No. 11-0662 was filed on September 29, 2011 and involved the Winter 2011 Storm.

ComEd sought a determination of the applicability of section 16-125(e) of the Act, which

provided, in pertinent part:

-2- Nos. 1-13-2011 & 1-13-2012 (Cons.)

“(e) In the event that more than *** 30,000 *** customers

*** of an electric utility are subjected to a continuous power

interruption of 4 hours or more that results in the transmission of

power at less than 50% of the standard voltage, or that results in

the total loss of power transmission, the utility shall be responsible

for compensating customers affected by that interruption for 4

hours or more for all actual damages, which shall not include

consequential damages, suffered as a result of the power

interruption. *** A waiver of the requirements of this subsection

may be granted by the Commission in instances in which the utility

can show that the power interruption was a result of any one or

more of the following causes:

(1) Unpreventable damage due to weather events or

conditions." 220 ILCS 5/16-125(e) (West 2010).

ComEd sought a ruling that section 16-125(e) did not apply to the outages at issue because no

one single interruption left 30,000 customers without electricity at the same time. In the

alternative, ComEd argued that, even if the statute applies, any liability should be waived

pursuant to subsection 16-125(e)(1) because the interruptions were "[u]npreventable damage due

to weather events or conditions."

¶5 An administrative law judge (ALJ) held evidentiary hearings in July 2012. ComEd, the

Commission's staff, and the office of the Illinois Attorney General (Attorney General) presented

evidence. Respondents, City of Chicago and Citizens Utility Board, also appeared at the

hearings.

-3- Nos. 1-13-2011 & 1-13-2012 (Cons.)

¶6 The Commission issued its ruling in both cases on June 5, 2013. In two separate orders,

the Commission determined that, by its plain and unambiguous language, section 16-125(e)

applied to the outages related to the Summer 2011 Storms, as well as the Winter 2011 Storm.

The Commission specifically found that "[s]ection 16-125(e) applies when 30,000 or more of

ComEd's customers have their service interrupted during the same four-hour period."

Commonwealth Edison Company, Ill. Commerce Comm’n Final Order 11-0588 at 16 (June 5,

2013); Commonwealth Edison Company, Ill. Commerce Comm’n Final Order 11-0662 at 18

(June 5, 2013). The Commission rejected ComEd's argument that the General Assembly

intended section 16-125(e) to apply only to single discrete interruptions that continuously

interrupt power to over 30,000 of the same customers for the same four-hour period.

¶7 In the Winter 2011 Storm case, docket No. 11-0662, the Commission further determined

that ComEd was entitled to a waiver of liability under section 16-125(e)(1) where the evidence

demonstrated that the great majority of the power interruptions that occurred were the result of

"unpreventable damage due to weather events or conditions." Commonwealth Edison Company,

Ill. Commerce Comm’n Final Order 11-0662 at 23 (June 5, 2013). The Commission made a

similar determination in the Summer 2011 Storms case, docket No. 11-0588, with the exception

of the July 11, 2011 storm. Further, the Commission found that the 34,559 customers affected

by the July 11, 2011 storm, as well as the municipalities in which the affected customers resided,

were entitled to file for compensation under the Act. ComEd was directed to file a confidential

document with the Commission identifying the customers or areas that would be entitled to file a

claim. The Commission also required ComEd to work with the Commission's consumer services

division in drafting, within 60 days, written notice to the affected customers informing them that

they were entitled to seek damages. The Commission further concluded that the "[c]osts

-4- Nos. 1-13-2011 & 1-13-2012 (Cons.)

incurred in providing such notice, and all associated costs, shall not be included in rate base or

treated as allowable expenses for purposes of determining the rates to be charged by the public

utility."

¶8 On June 27, 2013, the Commission denied ComEd's petitions for rehearing in both cases.

ComEd promptly appealed. ComEd filed an appeal (No.

Free access — add to your briefcase to read the full text and ask questions with AI

Commonwealth Edison Co. v. Illinois Commerce Comm'n, 2014 IL App (1st) 130211 (Ill. Ct. App. 2014).

2014 IL App (1st) 130211 (Commonwealth Edison Co. v. Illinois Commerce Comm'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Duquesne Light Co. v. Barasch
488 U.S. 299 (Supreme Court, 1989)
Crittenden v. The Cook County Comm'n on Human Rights
2013 IL 114876 (Illinois Supreme Court, 2013)
Illinois Bell Telephone Co. v. Illinois Commerce Commission
840 N.E.2d 704 (Appellate Court of Illinois, 2005)
Geer v. Kadera
671 N.E.2d 692 (Illinois Supreme Court, 1996)
Pajic v. Old Republic Insurance
917 N.E.2d 564 (Appellate Court of Illinois, 2009)
Golden Rule Insurance v. Schwartz
786 N.E.2d 1010 (Illinois Supreme Court, 2003)
Schweickart v. Powers
613 N.E.2d 403 (Appellate Court of Illinois, 1993)
Illinois Bell Telephone Co. v. Illinois Commerce Commission
797 N.E.2d 716 (Appellate Court of Illinois, 2003)
Abruzzo v. City of Park Ridge
898 N.E.2d 631 (Illinois Supreme Court, 2008)
Commonwealth Edison Co. v. Illinois Commerce Commission
924 N.E.2d 1065 (Appellate Court of Illinois, 2009)
Landis v. Marc Realty, L.L.C.
919 N.E.2d 300 (Illinois Supreme Court, 2009)
People Ex Rel. Birkett v. Dockery
919 N.E.2d 311 (Illinois Supreme Court, 2009)
People v. Purcell
778 N.E.2d 695 (Illinois Supreme Court, 2002)
Condon v. American Telephone & Telegraph Co.
554 N.E.2d 206 (Illinois Supreme Court, 1990)
Krohe v. City of Bloomington
789 N.E.2d 1211 (Illinois Supreme Court, 2003)
Monarch Gas Co. v. Illinois Commerce Commission
633 N.E.2d 1260 (Appellate Court of Illinois, 1994)
Cates v. Cates
619 N.E.2d 715 (Illinois Supreme Court, 1993)
Illinois Bell Telephone Co. v. IlliNois Commerce Commission
111 N.E.2d 329 (Illinois Supreme Court, 1953)
Hyatt Corp. v. Sweet
594 N.E.2d 1243 (Appellate Court of Illinois, 1992)