Commonwealth Edison Co. v. Illinois Commerce Comm'n

2014 IL App (1st) 130211
Procedural entryThis page is a short order in Commonwealth Edison Co. v. Illinois Commerce Comm'n. Read the opinion of the Court — 2014 IL App (1st) 132011
Appellate Court of Illinois·Decided August 5, 2014·No. 1-13-2011, 1-13-2012 cons.·Unpublished

Opinion

2014 IL App (1st) 132011

FOURTH DIVISION

July 31, 2014

Nos. 1-13-2011 & 1-13-2012 (Cons.)

COMMONWEALTH EDISON COMPANY, )

)

Petitioner, )

)

v. ) Petition for Review of Orders ) of the Illinois Commerce ) Commission in

ILLINOIS COMMERCE COMMISSION; ) Docket Nos. CITIZENS UTILITY BOARD; THE CITY OF ) 11-0588 and 11-0662 CHICAGO; and THE PEOPLE OF THE STATE ) OF ILLINOIS, )

)

Respondents. )

JUSTICE EPSTEIN delivered the judgment of the court, with opinion.

Presiding Justice Howse and Justice Lavin concurred in the judgment and opinion.

OPINION

¶1 In this consolidated appeal, petitioner Commonwealth Edison (ComEd), challenges two orders of respondent, the Illinois Commerce Commission (the Commission) interpreting and applying section 16-125(e) of the Public Utilities Act (220 ILCS 5/16-125(e) (West 2010)) (the Act) to power interruptions that resulted from a series of severe storm systems that hit northern Illinois in 2011 and caused damage to ComEd's electric delivery system. The Commission concluded that, pursuant to the language of section 16-125(e), ComEd was liable for damages to the affected consumers. However, with the exception of the storm that occurred on July 11, 2011, the Commission granted ComEd a waiver of liability under section 16-125(e)(1) of the Act

where the power interruption resulted from "[u]npreventable damage due to weather events or conditions." 220 ILCS 5/16-125(e)(1) (West 2010). ¶2 ComEd now contends that the statute only applies where there is a continuous power outage caused by a single event that interrupts power to over 30,000 of the same customers for the same four-hour period and that the Commission erred in deciding that section 16-125(e)(1) applied to the "numerous dispersed and discrete interruptions at different times, in different places, and for different reasons." ComEd further contends that it is entitled to a full waiver of liability for the July 11, 2011 storm. ComEd also argues that the Commission unlawfully precluded ComEd from recovering its cost of providing notice to the customers. For the reasons that follow, we dismiss appeal No. 1-13-2012 and affirm the Commission's decision in appeal No. 1-13-2011. ¶3 BACKGROUND ¶4 Several storm systems struck northern Illinois in 2011 causing significant damage to thousands of ComEd's customers. One of the storms occurred on February 1, 2011 (Winter 2011 Storm). Six storms occurred in the summer of 2011 (Summer 2011 Storms), specifically on June 8, June 21, June 30, July 11, July 22, and July 27, 2011. More than 2 million of ComEd's customers experienced a power interruption. After some customers made claims for damages resulting from the power outages, ComEd filed two verified petitions before the Commission. Docket No. 11-0588 was filed on August 18, 2011 and involved the Summer 2011 Storms. Docket No. 11-0662 was filed on September 29, 2011 and involved the Winter 2011 Storm. ComEd sought a determination of the applicability of section 16-125(e) of the Act, which provided, in pertinent part:

“(e) In the event that more than *** 30,000 *** customers *** of an electric utility are subjected to a continuous power interruption of 4 hours or more that results in the transmission of power at less than 50% of the standard voltage, or that results in the total loss of power transmission, the utility shall be responsible for compensating customers affected by that interruption for 4 hours or more for all actual damages, which shall not include consequential damages, suffered as a result of the power interruption. *** A waiver of the requirements of this subsection may be granted by the Commission in instances in which the utility can show that the power interruption was a result of any one or more of the following causes:

(1) Unpreventable damage due to weather events or conditions." 220 ILCS 5/16-125(e) (West 2010).

ComEd sought a ruling that section 16-125(e) did not apply to the outages at issue because no one single interruption left 30,000 customers without electricity at the same time. In the alternative, ComEd argued that, even if the statute applies, any liability should be waived pursuant to subsection 16-125(e)(1) because the interruptions were "[u]npreventable damage due to weather events or conditions." ¶5 An administrative law judge (ALJ) held evidentiary hearings in July 2012. ComEd, the Commission's staff, and the office of the Illinois Attorney General (Attorney General) presented evidence. Respondents, City of Chicago and Citizens Utility Board, also appeared at the hearings.

Free access — add to your briefcase to read the full text and ask questions with AI

Commonwealth Edison Co. v. Illinois Commerce Comm'n, 2014 IL App (1st) 130211 (Ill. Ct. App. 2014).

2014 IL App (1st) 130211 (Commonwealth Edison Co. v. Illinois Commerce Comm'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Duquesne Light Co. v. Barasch
488 U.S. 299 (Supreme Court, 1989)
Crittenden v. The Cook County Comm'n on Human Rights
2013 IL 114876 (Illinois Supreme Court, 2013)
Illinois Bell Telephone Co. v. Illinois Commerce Commission
840 N.E.2d 704 (Appellate Court of Illinois, 2005)
Geer v. Kadera
671 N.E.2d 692 (Illinois Supreme Court, 1996)
Pajic v. Old Republic Insurance
917 N.E.2d 564 (Appellate Court of Illinois, 2009)
Golden Rule Insurance v. Schwartz
786 N.E.2d 1010 (Illinois Supreme Court, 2003)
Schweickart v. Powers
613 N.E.2d 403 (Appellate Court of Illinois, 1993)
Illinois Bell Telephone Co. v. Illinois Commerce Commission
797 N.E.2d 716 (Appellate Court of Illinois, 2003)
Abruzzo v. City of Park Ridge
898 N.E.2d 631 (Illinois Supreme Court, 2008)
Commonwealth Edison Co. v. Illinois Commerce Commission
924 N.E.2d 1065 (Appellate Court of Illinois, 2009)
Landis v. Marc Realty, L.L.C.
919 N.E.2d 300 (Illinois Supreme Court, 2009)
People Ex Rel. Birkett v. Dockery
919 N.E.2d 311 (Illinois Supreme Court, 2009)
People v. Purcell
778 N.E.2d 695 (Illinois Supreme Court, 2002)
Condon v. American Telephone & Telegraph Co.
554 N.E.2d 206 (Illinois Supreme Court, 1990)
Krohe v. City of Bloomington
789 N.E.2d 1211 (Illinois Supreme Court, 2003)
Monarch Gas Co. v. Illinois Commerce Commission
633 N.E.2d 1260 (Appellate Court of Illinois, 1994)
Cates v. Cates
619 N.E.2d 715 (Illinois Supreme Court, 1993)
Illinois Bell Telephone Co. v. IlliNois Commerce Commission
111 N.E.2d 329 (Illinois Supreme Court, 1953)
Hyatt Corp. v. Sweet
594 N.E.2d 1243 (Appellate Court of Illinois, 1992)