Commonwealth, Department of Labor & Industry, Bureau of Labor Law Compliance v. Lawson Demolition & Hauling Co.

856 A.2d 860, 2004 Pa. Commw. LEXIS 568
CourtCommonwealth Court of Pennsylvania
DecidedJuly 29, 2004
StatusPublished
Cited by3 cases

This text of 856 A.2d 860 (Commonwealth, Department of Labor & Industry, Bureau of Labor Law Compliance v. Lawson Demolition & Hauling Co.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth, Department of Labor & Industry, Bureau of Labor Law Compliance v. Lawson Demolition & Hauling Co., 856 A.2d 860, 2004 Pa. Commw. LEXIS 568 (Pa. Ct. App. 2004).

Opinion

FLAHERTY, Senior Judge.

The Department of Labor and Industry, Bureau of Labor Law Compliance (Bureau) appeals from an order of the Prevailing Wage Appeals Board (Board) which reversed the decision of the Secretary of Labor and Industry (Secretary) and determined that Lawson Demolition and Hauling Co., and John D. Lawson (collectively, Lawson) did not intentionally violate the Pennsylvania Prevailing Wage Act (Act), Act of August 5, 1961, P.L. 987, as amended, 43 P.S. §§ 165-1 — 165-17. We affirm.

Westra Construction Co. (Westra) was awarded a contract to perform renovation *861 work to the central administrative building of the Pennsylvania Turnpike Commission (the project). Specifications for the project included a predetermination of the prevailing minimum wage rates issued for the job. Westra entered into a subcontract agreement with Lawson to perform demolition work on the project.

On April 6, 2001 an order to show cause was filed against Lawson asserting that he intentionally faded to pay the prevailing minimum wage to its employees. A hearing was conducted before a hearing examiner.

The Secretary issued findings and determined that the subcontract agreement between Lawson and Westra included a 5% retainage of money from Lawson until the Turnpike Commission made final payment to Westra. The money was to be paid no sooner than 35 days after the prime contract had been completed. Lawson was aware of the retainage and had previously entered into other public work contracts where there had been a 10% retainage. Lawson did not have capital or resources to meet its financial obligations except if paid by Westra. Westra stopped payments to Lawson because Lawson’s suppliers were not being paid and the amount of money needed to complete the project was greater than that owed by Lawson.

The Secretary also determined that Lawson did not pay its workers for over a month at the beginning of the project and throughout the project were paid irregularly due to the lack of money. For a two month period at the end of the project from June 3, 2000 through July 29, 2000, workers were not paid until August 2001, when the Bureau paid them with money retained by Westra. When the payroll was not being met, Lawson informed employees that it did not have the money but that it would be forthcoming. Lawson also admitted that it under budgeted the project.

During its investigation, Bureau requested certified payroll receipts from Lawson. Lawson gave certified payroll reports to the Bureau for the period ending June 3, 2000 through July 29, 2000. Those payroll reports differed from those that Lawson had submitted to Westra.

The Secretary concluded that Lawson intentionally failed to pay its workers the prevailing wage in violation of the Act. Workers were not paid for a period of two months totaling $29,777.26. Even though the workers were eventually paid, subsequent compliance is not a valid defense or mitigating factor when considering an intentional Act violation. The Secretary also concluded that Lawson submitted falsified certified payrolls. Specifically, Lawson submitted payroll reports showing that the employees had been paid when in fact they had not. Due to the intentional violations of the Act, the Secretary barred Lawson from public works for a period of three years.

On appeal, the Board reversed the decision of the Secretary concluding that substantial evidence did not exist to support the Secretary’s determination that Lawson intentionally violated the Act. Specifically, with regard to payment of the prevailing wage, the Board found that Lawson made numerous attempts to ensure that its workers were paid from funds withheld by Westra. In May 2000, the project supervisor prepared a list of items which needed to be finished in order to complete the contract. Although Lawson completed these items, Westra did not release the money but instead a new project manager prepared an additional list for Lawson to complete. Upon completion of these items, Westra again refused to release funds in the amount of $41,000.00 owed to Lawson.

*862 As a result of the Bureau’s audit in August, 2000, it requested that Westra retain $29,777.26 of the amount due and payable to Lawson on the project, which reflected sums not paid to Lawson’s workers. Despite requests from Lawson for his workers to be paid from the retainage fund which had been sent to the Bureau, the Bureau refused to make payment of the withheld funds until August, 2001. “In fact, funds were available and in the Bureau’s hands for payment to Lawson’s workers for almost eleven months before they were agreed to be released to Lawson’s workers.” (Board’s decision at p. 7.)

The Board concluded that Lawson unintentionally violated the Act by failing to make payment of prevailing wages. Lawson reasonably anticipated payment from Westra so that it could pay its workers and such funds should have been available to it. Although Lawson finished the work requested by Westra, Westra refused to pay over any of the retainage it held for Lawson. Moreover, even though the re-tainage funds had been forwarded to the Bureau, the Bureau held the funds for almost eleven months until August 2001 before it finally distributed it to Lawson’s workers. Lawson completed the work required and it was Westra and the Bureau which prevented Lawson from paying its workers because they held the retained funds. As such, the Board reversed the decision of the Secretary.

On appeal, our review is limited to determining whether constitutional rights were violated, an error of law was committed and whether necessary findings are supported by substantial evidence. Boss Insulation & Roofing v. Department of Labor and Industry, 722 A.2d 778 (Pa. Cmwlth.1999).

The first issue we address is whether Lawson violated the Act by intentionally failing to pay the prevailing wage. The Act states that substantial evidence of an intentional failure to pay prevailing wage rates includes “[a]ny acts of omission or commission done willfully or with a knowing disregard of the rights of the workmen resulting in payment of less than prevailing wage rates.” Section 11(h)(1) of the Act, 43 P.S. § 165-11(h)(1). “Therefore, all that is required is evidence that the contractor performed or failed to perform any act which it knew to be in disregard to workmen’s rights.” Leonard S. Fiore, Inc. v. Department of Labor and Industry, Prevailing Wage Appeals Board, 526 Pa. 282, 289, 585 A.2d 994, 998 (1991).

Bureau argues that subcontractors have an unconditional obligation to pay prevailing wages regardless of financial ability to do so. In Di Lucente Corp. v. Pennsylvania Prevailing Wage Appeals Board, 692 A.2d 295, 298 (Pa.Cmwlth.1997) this court stated:

A contractor’s statutory obligation to pay the prevailing wage is not contingent on ability to pay. This obligation is unconditional, 34 Pa.Code § 9.106(a) and one that arises weekly, 34 Pa.Code § 9.103(f).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.L. Insulation Co. v. Prevailing Wage Appeals Board
923 A.2d 550 (Commonwealth Court of Pennsylvania, 2007)
Allied Mechanical & Electrical, Inc. v. Pennsylvania Prevailing Wage Appeals Board
923 A.2d 1220 (Commonwealth Court of Pennsylvania, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
856 A.2d 860, 2004 Pa. Commw. LEXIS 568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-department-of-labor-industry-bureau-of-labor-law-pacommwct-2004.