Committee for a Progressive Gilroy v. State Water Resouces Control Board

192 Cal. App. 3d 847, 237 Cal. Rptr. 723, 1987 Cal. App. LEXIS 1819
CourtCalifornia Court of Appeal
DecidedJune 15, 1987
DocketC000501
StatusPublished
Cited by39 cases

This text of 192 Cal. App. 3d 847 (Committee for a Progressive Gilroy v. State Water Resouces Control Board) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Committee for a Progressive Gilroy v. State Water Resouces Control Board, 192 Cal. App. 3d 847, 237 Cal. Rptr. 723, 1987 Cal. App. LEXIS 1819 (Cal. Ct. App. 1987).

Opinion

Opinion

SPARKS, J.

In this environmental case we are called upon to decide whether judicial review of a decision of the State Water Resources Control Board concerning waste discharge levels for a municipal sewage treatment facility is governed by the limitation period of the California Environmental *852 Quality Act (CEQA) or the Porter-Cologne Water Quality Control Act. We hold that CEQA claims are governed by the CEQA statute of limitations.

Plaintiff Committee for a Progressive Gilroy petitioned for a writ of mandate to compel defendants Regional Water Control Board, Central Coast Region (Regional Board) and State Water Resources Control Board (State Board) to set aside certain orders and decisions relating to a wastewater treatment plant operated by the real parties in interest City of Gilroy and City of Morgan Hill. The trial court denied the petition on the ground that it was barred by the statute of limitations contained in the Porter-Cologne Water Quality Control Act. Plaintiff appeals, contending that the CEQA limitation applies instead and that its petition was timely under that act. Although we agree on that point, we nevertheless conclude that the trial court’s decision was legally correct on other grounds and therefore affirm it.

Factual and Procedural Background

The cities of Gilroy and Morgan Hill jointly operate a municipal sewage wastewater treatment plant in south Santa Clara County. Wastewater is treated in aeration ponds in the facility and then discharged into 230 acres of evaporation-percolation ponds. The treated wastewater is eventually discharged into Llagas Creek, a tributary to Pajaro River. The facility was built to its current capacity as the result of a project to replace an antiquated plant in the mid-1970’s. In connection with the original project the City of Gilroy acted as the “lead agency” under CEQA (Pub. Resources Code, § 21000 et seq.), and caused to be prepared a final environmental impact report (EIR) for a projected capacity of 6.4 million gallons per day (mgd) on an average daily dry weather flow basis. 1 That final EIR was not judicially challenged.

Under the Porter-Cologne Act, the Regional Board was required to set discharge requirements for the revamped wastewater treatment facilities. (See Wat. Code, § 13263.) In 1981, after completion of the Gilroy-Morgan Hill facility expansion project, the Regional Board issued order number 81-02 setting requirements for the facility. Among other things, the order set a maximum flow of 6.1 mgd for the facility.

In 1982 and 1983, the cities encountered aeration and percolation problems in the operation of the facility. These problems resulted in excessive *853 odors and in the unauthorized discharge of wastewater into Llagas Creek. In response to these difficulties the Regional Board issued a cease and desist order against the cities in 1983. As part of the enforcement action, and pursuant to a stipulation in a legal action, the Regional Board issued an order temporarily prohibiting the City of Gilroy from permitting new connections to its sewer system. In January 1984, the Regional Board adopted order number 84-06 prescribing requirements for discharge from the facility. Among the requirements was a reduction of the permitted daily flow to a maximum of 5.15 mgd.

The cities then undertook remedial action. They purchased and developed an additional 163 acres for percolation ponds. In connection with the pond development, the cities adopted a negative declaration under CEQA. 2 (See Pub. Resources Code, §§ 21064, 21080, subd. (c).) Once again, no judicial challenge was made to this negative declaration. The cities also replaced the aeration system which had malfunctioned with a new, conventional system. In addition, the cities replaced the city officials responsible for the management of the plant, and contracted with a qualified consulting firm to manage the plant.

In November 1984, after a hearing at the request of the cities, the Regional Board issued the first of the two orders challenged here, order number 84-97. Among other things, this order permitted an increase in plant capacity to 5.30 mgd. At that time the Regional Board also rescinded the connection ban against the City of Gilroy. In May 1985, after further hearings, the Regional Board adopted the second order, number 85-83, which permitted the cities to operate the facility at the originally approved level of 6.1 mgd.

Plaintiff sought review of the Regional Board’s orders by the State Board. Among other grounds, plaintiff contended that the Regional Board was required to prepare a new EIR before permitting an increase in the capacity at which the cities could operate the facility. The State Board rejected that argument, ruling that the Regional Board was not required to prepare an EIR when setting requirements for an existing facility. The State Board reasoned that the “regulations implementing CEQA make clear that a new EIR need not be prepared where an agency is approving an existing facility. (Cal. Admin. Code, tit. 14, § 15301.) In fact, an EIR or negative declaration prepared by a lead agency (in this case, the Cities) is conclusively presumed to comply with CEQA for purposes of use by responsible agencies, such as the Regional Board. (Cal. Admin. Code, tit. 14, § 15231.) The only excep *854 tions to this rule are where the environmental document is determined to be invalid in court proceedings (§ 15231(a)) and where a subsequent EIR is necessary (§ 15231(b)). There has been no such court ruling in this case, and none of the criteria requiring preparation of a subsequent EIR has been met. (Cal. Admin. Code, tit. 14, § 15162(a).)” The decision of the State Board upholding the orders of the Regional Board was adopted on August 22, 1985, and was served on plaintiff on September 3, 1985.

On January 30, 1986, plaintiff filed its petition for a writ of mandate against the two boards, naming the cities as real parties in interest. Plaintiff sought a writ compelling the boards to rescind their orders and decisions and to require the Regional Board to prepare an EIR prior to authorizing any increase in capacity for the Gilroy-Morgan Hill wastewater treatment facility. Plaintiff alleged that the Regional Board abused its discretion and failed to proceed in the manner required by law when it adopted the orders increasing the permitted flows first to 5.3 mgd and then to 6.1 mgd because it did not prepare an EIR for either order. The trial court denied the petition on the ground that it was untimely under Water Code section 13330, subdivision (a). This appeal followed.

Discussion

Plaintiff launches its appellate attack by asserting that the CEQA limitation period applies to this writ proceeding and not the Water Code statute of limitations. The Water Code limitation, it contends, applies only to litigation concerning duties imposed by the Porter-Cologne Water Quality Control Act (Wat. Code., § 13000 et seq.) and not to cases such as this one relating only to CEQA duties. This follows, it claims, by virtue of the rules of statutory construction and for reasons of public policy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midler v. City of San Diego CA4/1
California Court of Appeal, 2024
Save Lafayette Trees v. City of Lafayette
243 Cal. Rptr. 3d 636 (California Court of Appeals, 5th District, 2019)
Save Lafayette Trees v. City of Lafayette
California Court of Appeal, 2018
Trees v. City of Lafayette
239 Cal. Rptr. 3d 222 (California Court of Appeals, 5th District, 2018)
Lopez v. Sony Electronics, Inc.
420 P.3d 767 (California Supreme Court, 2018)
Pesticide Action Network N. Am. v. Cal. Dep't of Pesticide Regulation
224 Cal. Rptr. 3d 591 (California Court of Appeals, 5th District, 2017)
Wilson v. Douglas CA2/6
California Court of Appeal, 2014
Ogawa v. City of Palo Alto CA6
California Court of Appeal, 2013
May v. City of Milpitas
217 Cal. App. 4th 1307 (California Court of Appeal, 2013)
Van de Kamps Coalition v. Board of Trustees of Los Angeles Community College District
206 Cal. App. 4th 1036 (California Court of Appeal, 2012)
Vafi v. McCloskey
193 Cal. App. 4th 874 (California Court of Appeal, 2011)
Strother v. California Coastal Commission
173 Cal. App. 4th 873 (California Court of Appeal, 2009)
Cardinal Health 301, Inc. v. Tyco Electronics Corp.
169 Cal. App. 4th 116 (California Court of Appeal, 2008)
Moss v. County of Humboldt
76 Cal. Rptr. 3d 428 (California Court of Appeal, 2008)
Com. for Green Foothills v. Santa Clara Cty. Bd. of Sup'rs
75 Cal. Rptr. 3d 112 (California Court of Appeal, 2008)
Communities for Better Env. v. Scaqmd
71 Cal. Rptr. 3d 7 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
192 Cal. App. 3d 847, 237 Cal. Rptr. 723, 1987 Cal. App. LEXIS 1819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/committee-for-a-progressive-gilroy-v-state-water-resouces-control-board-calctapp-1987.