Commissioners of Saline Branch Drainage District v. Pilcher

310 N.E.2d 454, 19 Ill. App. 3d 125, 1974 Ill. App. LEXIS 2586
CourtAppellate Court of Illinois
DecidedApril 25, 1974
Docket12217
StatusPublished
Cited by7 cases

This text of 310 N.E.2d 454 (Commissioners of Saline Branch Drainage District v. Pilcher) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commissioners of Saline Branch Drainage District v. Pilcher, 310 N.E.2d 454, 19 Ill. App. 3d 125, 1974 Ill. App. LEXIS 2586 (Ill. Ct. App. 1974).

Opinions

Mr. JUSTICE CRAVEN

delivered the opinion of the court:

This appeal is from a proceeding under the Illinois Drainage Code in which the commissioners of the Saline Branch Drainage District sought to levy assessments for annual maintenance work and additional drainage work. Following a hearing on the matter, the trial court found the proposed improvements were necessary and the court entered a judgment on the assessment roles of the drainage district. The objectors at the hearing appealed.

The issues on appeal are: whether the trial court erroneously restricted evidence of and gave too little consideration to esthetic, ecological and environmental consideration in passing upon the necessity and advisability of the proposed drainage work; and whether the trial court erroneously ruled that the drainage district had recorded title to an easement that amounted to a right-of-way in the land adjacent to the drainage ditch involved in the project.

The commissioners of the Saline Branch Drainage District filed a petition to levy additional assessment and to establish and levy annual maintenance assessment. The petition recites that the drainage district is comprised of approximately 11,320 acres and is adjacent to 981 subdivision lots; that the last assessment in the district was levied in 1935 with all assessments on the role then filed having been paid. The petition noted that it was necessary for the proper preservation of the drainage system that additional work be done on the drainage ditch at this time and that such annual maintenance as required in the future be done. The commissioners recited as reasons for the need for the work the alleged fact that the ditch was now “obstructed by debris, silt, broken tiles, aquatic growth, stumps and dead fall to such an extent that the hydraulic capacity and efficiency are greatly reduced * * *.” The petition stated that in order to remedy the mentioned condition, the ditch in question should be cleared, and certain trees and vegetation growing next to the ditch should be removed. The petitioners estimated the cost of this work and the annual maintenance to be approximately $125,000 and $5,000, respectively.

Objections were formally filed opposing the petition. The objectors contended that the proposed plans were vague and uncertain in nature and extent concerning the work to be done on the ditch, and that it was questionable whether the benefits, if any, would exceed the cost of such work. The objectors alleged that the petition failed to contain sufficient information to ascertain if there were viable alternative plans that could be implemented in the renovation of the drainage ditch. The objectors stated that the proposed plan failed to consider such factors as a natural beauty and recreational potential of the area; and that the destruction of one of the last wooded stream areas in Champaign County is a substantial factor in determining whether the proposed work is necessary or desirable. The objectors contended that the proposed plan would not solve the existing problem and that among other things it would result in additional erosion and landslides due to the deepening of the drainage ditch, thereby posing a threat to the property of abutting objectors.

On July 14, 1970, the hearing on the petition was commenced. The petitioners established that they had conducted a recent investigation of the condition of the drainage ditch. The results of this investigation showed that at some points the flow capacity of the ditch was only two-thirds of its 1937 capacity; but other portions of the ditch were free of debris. All petitioners’ experts agreed that the ditch should be cleared of all trees and brush that were growing in the bed of the ditch, and that the bank areas within the right-of-way of the ditch should also be cleared; and that herbicides should be used to discourage regrowth of certain undesirable forms of vegetation.

It was also elicited through petitioners’ witnesses that the present condition of the drainage ditch was such that an ordinary rainfall occasionally resulted in flooding over a portion of the district, including valuable farmlands. Also, the Champaign-Urbana Sanitary District’s main treatment plant, which is located on the bank of the ditch, has been flooded several times when the drainage ditch overflowed its banks. As a direct consequence of this flooding, raw sewage flowed directly into the ditch. An engineer of the sanitary district contended that once the ditch was cleared of its debris the overflow problem would be abated. If the debris was not cleared from the ditch, it would be necessary for the sanitary district to build dikes and install diesel pumps or a storm sewer in order to avoid serious health hazards resulting from the dumping of raw sewage into the ditch. The sanitary district’s engineer stated that the district agreed to pay approximately $60,000 of the cost of clearing the ditch.

The objectors called Professor Donald L. Walker, Jr., to testify. He stated that he was a professor of landscaping architecture at the University of Illinois, and that he had prepared an alternative plan for clearing the ditch which would entafl the actual clearing of the bed of the ditch and the thinning of trees on the bank by the process of selective removal. He contended that his plan would increase the flow of the ditch and have the advantages of minimizing the erosion and eliminate excessive brush growth, yet preserve the natural habitat for wildlife and retain the physical visual beauty as well as the potential economical value of the trees. He admitted that his plans would eliminate the use of a dragline as proposed by the petitioners because of the remaining trees on the bank would make such an operation impossible. His plan also eliminated the use of herbicides because he contended that they were pollutants. However, he admitted that if properly used, the herbicides were not injurious to man or animal.

Mr. John Goodell, a registered civil engineer, testified for the objectors that he had worked on farm drainage problems for a number of years and was a principal engineer for several drainage districts, including the Beaver Lake Dam District immediately upstream from Saline. He testified that he was familiar with both the Walker and the petitioners’ proposals. He believed that the best plan would include elements of both of these proposals. He contended that a selective clearing as postulated by Professor Walker was probably more desirable than a total clearing as proposed by the petitioners. He did admit that the Walker plan would unduly restrict a contractor’s right of access and that this particular facet of the plan should be changed. Also, he stated that a dragline should be used to drag debris out of the ditch, a consideration that was specifically rejected by the Walker proposal.

The objectors also called a Mr. Willett Wandell whose testimony concerned the esthetic and erosion control value of the trees along the drainage ditch. He did testify that he believed the use of herbicides was not dangerous and that it was necessary to control the regrowth of brush once it was removed.

The objectors then attempted to call certain witnesses who would testify concerning the ornamental and recreational value of the trees in question. The testimony was objected to and an offer of proof was made over the objection. The trial court excluded the testimony.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meeks v. Dissanayake
2021 IL App (1st) 191420-U (Appellate Court of Illinois, 2021)
Upper Salt Fork Drainage District v. DiNovo
Appellate Court of Illinois, 2008
Commissioners of Sny Island Levee Drainage District v. Utterback
474 N.E.2d 859 (Appellate Court of Illinois, 1985)
Rockville Drainage District No. 2 v. Mougin
466 N.E.2d 402 (Appellate Court of Illinois, 1984)
Hamming v. Murphy
404 N.E.2d 1026 (Appellate Court of Illinois, 1980)
Commissioners of Saline Branch Drainage District v. Pilcher
310 N.E.2d 454 (Appellate Court of Illinois, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
310 N.E.2d 454, 19 Ill. App. 3d 125, 1974 Ill. App. LEXIS 2586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commissioners-of-saline-branch-drainage-district-v-pilcher-illappct-1974.