Combustion Engineering, Inc. v. Miller Hydro Group

812 F. Supp. 260, 1992 WL 438339, 1992 U.S. Dist. LEXIS 20792
CourtDistrict Court, D. Maine
DecidedOctober 6, 1992
DocketCiv. 89-0168-P-C
StatusPublished
Cited by6 cases

This text of 812 F. Supp. 260 (Combustion Engineering, Inc. v. Miller Hydro Group) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Combustion Engineering, Inc. v. Miller Hydro Group, 812 F. Supp. 260, 1992 WL 438339, 1992 U.S. Dist. LEXIS 20792 (D. Me. 1992).

Opinion

MEMORANDUM AND ORDER GRANTING DEFENDANT’S MOTION FOR JUDGMENT AS A MATTER OF LAW

GENE CARTER, Chief Judge.

After entering into a turnkey construction contract with Defendant for a hydroelectric facility in Lisbon Falls, Maine, Plaintiff designed, constructed, and tested the facility. In 1989 Plaintiff brought this suit for breach of contract, alleging that Defendant had failed to pay certain amounts due under the contract including the retainage and bonus amounts for power generated in excess of the contract minimums. The complaint was amended to include equitable claims for unjust enrichment and equitable estoppel. Defendant counterclaimed for breach of contract, fraud, and misrepresentation. Trial was held in this matter in January, 1992, on Plaintiffs contract claim and on Defendant’s counterclaims. The Court left the parties’ claims for equitable relief for later resolution.

At trial the parties stipulated to both the existence and the validity of the turnkey contract. At the end of Plaintiff’s case, the Court granted the Defendant’s and the Party-in-Interest’s motions for judgment on Plaintiff’s contract claims as a matter of law, finding that Plaintiff had breached the turnkey contract. The Court determined that Plaintiff had not fulfilled a condition precedent to the contract by failing to test the facility as contemplated in the contract and by failing to achieve final acceptance.

The jury considered Defendant’s counterclaims, finding that Plaintiff had committed fraud by means of both affirmative misrepresentations and omissions concerning the facility. The jury also found that Plaintiff had breached the turnkey contract in several respects. Specifically, it concluded that Plaintiff had designed the turbines with a flow in excess of that specified by the contract, had installed equipment with an electrical capacity in excess of that prescribed by the contract, and had construct *262 ed a facility which was not in accordance with the federal license incorporated in the contract. Plaintiff’s breaches consisted of designing and building the facility with a greater ability to generate electricity than was contemplated under the contract. Despite the breaches, the jury concluded that Defendant was entitled to no damages on its counterclaims.

Now asserting its equitable claims, Plaintiff argues that even though it breached the contract, it should be allowed to recover in quantum merit or on a theory of promissory estoppel for the benefit conferred on Defendant. Defendant argues that Plaintiff cannot obtain equitable relief when a valid written agreement covers the construction work at issue. Although other states have established such a principle, see e.g., Commerce, Crowdus & Canton, Ltd. v. DKS Construction, Inc., 776 S.W.2d 615, 620 (Tex.App.1989); First National Bank v. Burton, Parsons & Co., 57 Md.App. 437, 451, 470 A.2d 822 (1984), the Maine Law Court has not set forth such an absolute rule. 1

Defendant relies on Aroostook Valley R. Co. v. Bangor & Aroostook R. Co., 455 A.2d 431, 433 (Me.1983), in which the Law Court stated that

when two parties have agreed upon specific and unambiguous terms of compensation for specified services by means of an express contract, ... the law should be most hesitant to imply a second contract, which covers the same subject matter, if the evidence does not compel an inference that the parties intended to make one.

(Emphasis added). Clearly, however, alternative remedies are not entirely prohibited, and Maine law contains a smattering of cases from which can be gleaned the instances in which recovery might be permitted.

In Loyal Erectors, Inc. v. Hamilton & Son, Inc., 312 A.2d 748, 755 (Me.1973), another case relied on by Defendant, the Law Court was called upon to determine whether a debt was due absolutely or contingently for purposes of a Maine trustee process statute. The case concerned a building contract which included a requirement that an architect give a certificate of approval before the retainage could be paid. Having found that the architect’s certificate of approval was a condition precedent which had not been fulfilled, the court addressed the issue of an action in quantum meruit despite the failure to fulfill the contract:

The mere fact that an action based on “quantum meruit” concepts could possibly be entertained in the instant case, notwithstanding the failure to obtain the architect’s certificate of approval, on which we intimate no opinion, does not ipso facto convert what was an intended conditional potential liability for the re-tainage fund to a debt “due absolutely and not on any contingency.”

Id. Assuming that such an action was maintainable, however, the court examined the equities of the situation, finding they favored the person for whose protection the retainage clause was inserted in the contract. Id. at 756. The legal issue presented in this case is different from that presented in Loyal Erectors. The factual situation is similar in certain respects, however, and considering the equities, as did the court there, the Court finds no reason in the context of this construction contract to depart from the intended purpose of the parties under the contract. See id. at 757.

Plaintiff cites Maine cases in which, despite a breach of an express construction contract by the builder, a buyer has been required to pay in quantum meruit for the value of the goods and services received. In Gosselin v. Better Homes, Inc., 256 A.2d 629 (Me.1969), the Law Court permitted recovery when an express construction contract has not been fulfilled, but the buyer had received the benefit of the construction, accepted it, and used it.

Just as Maine has no absolute rule barring equitable recovery in the presence of a valid contract, there is no absolute rule *263 requiring equitable recovery for partial performance when the person seeking restitution has breached an express contract. Analysis of the precedents underlying Gosselin and those subsequent to it demonstrate that the Law Court looks to the equities of the situation, specifically to the good faith of the breaching party, to determine whether restitution should be awarded. In 1863, the court enunciated the principle:

When there has been no intentional departure from the contract, or failure to perform it, but the party has acted in good faith, endeavoring to fulfill it according to its terms in case of failure, he may recover what his services are worth, less the damage caused by such failure ....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
812 F. Supp. 260, 1992 WL 438339, 1992 U.S. Dist. LEXIS 20792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/combustion-engineering-inc-v-miller-hydro-group-med-1992.