Combustion Engineering Caribe, Inc. v. Geo P. Reintjes Co.

298 F. Supp. 2d 215, 2003 U.S. Dist. LEXIS 23382, 2003 WL 23112380
CourtDistrict Court, D. Puerto Rico
DecidedDecember 23, 2003
DocketCIV. 02-2466(RLA)
StatusPublished
Cited by5 cases

This text of 298 F. Supp. 2d 215 (Combustion Engineering Caribe, Inc. v. Geo P. Reintjes Co.) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Combustion Engineering Caribe, Inc. v. Geo P. Reintjes Co., 298 F. Supp. 2d 215, 2003 U.S. Dist. LEXIS 23382, 2003 WL 23112380 (prd 2003).

Opinion

ORDER DENYING MOTION FOR DISQUALIFICATION OF COUNSEL

ACOSTA, District Judge.

Plaintiffs have moved the court to disqualify SEIGFRIED, BINGHAM, LEVY, SELZER & GEE, P.C., the law firm representing codefendant GEO P. REINTJES CO., INC. (“REINTJES”) in this case due to an alleged conflict of interest originated by DUANE J. FOX, ESQ., one of its members, in having also acted as counsel for J.R. INSULATION SALES & SERVICE (“JRISS”), a non-party, during the taking of the deposition of two of its officers by plaintiffs herein. Additionally, movants have requested the imposition of *217 sanctions based on objections raised by MR. FOX during the aforementioned depositions regarding inquiries into his attorney-client relationship with JRISS.

FACTUAL BACKGROUND

Plaintiffs’ claims arise from a contract for the design and construction of portions of a coal burning “co-generation” power plant located in Guayama, Puerto Rico owned by AES PUERTO RICO, L.P. (“AES”). 1

AES contracted with DUKE/FLUOR DANIEL CARIBBEAN, S.E. (“DUKE/ FLUOR DANIEL”) as its prime contractor to design and build the project.

Subsequently, plaintiff ALSTOM POWER, INC. (“ALSTOM”) became a first-tier subcontractor for DUKE/FLUOR DANIEL and with its consent, plaintiff COMBUSTION ENGINEERING CARIBE, INC. (“CE-CARIBE”) was assigned part of ALSTOM’s subcontract.

Thereafter, both plaintiffs entered into separate second-tier subcontracts with co-defendant REINTJES. Pursuant to its agreement with ALSTOM codefendant REINTJES was responsible for designing the refractory insulation for the plant as well as supplying the materials necessary for that work, i.e., the “Design and Materials Contract”.

On the other hand, through its contract with CE-CARIBE eodefendant REINTJES agreed to perform the labor necessary to install the refractory insulation, i.e., “Labor Contract”. According to plaintiffs, codefendant’s obligations under the Labor Contract were guaranteed by two separate bonds issued by ST. PAUL FIRE AND MARINE INSURANCE CO. (“ST.PAUL”). A Performance Bond sought to protect CE-CARIBE in the event that REINTJES failed to comply with its contract and warranty obligations whereas a Payment Bond was intended to protect codefendant’s unpaid subcontractors as well as safeguard CE-CARIBE from claims or liens by such subcontractors.

Plaintiffs further contend that codefen-dant REINTJES entered into an Indemnity Agreement with ST. PAUL for any *218 damages or costs incurred under the bonds.

REINTJES in turn entered into third-tier subcontracts for both the Material as well as the Design and Material Contracts. Codefendant REINTJES subcontracted the majority of its installation labor to JRISS, a Puerto Rico corporation dedicated primarily to insulation work, and with RHI/HARBISON WALKER to design the refractory work and supply the installation material.

Both JRISS and RHI/HARBISON WALKER are currently under the bankruptcy court’s jurisdiction. 2

THE PLEADINGS

The outstanding complaint was filed by CE-CARIBE and ALSTOM against REINTJES and ST. PAUL. 3

Plaintiff CE-CARIBE seeks damages from REINTJES purportedly caused by a breach of contract, delays in completion of work, as well as defective installation of refractory materials. CE-CARIBE further calls for a declaratory judgment determining the validity of the bonds issued by ST. PAUL as well as the surety’s obligation to pay thereunder.

Plaintiff ALSTOM on the other hand demands REINTJES payment for damages caused by alleged failures in refractory materials and defective design.

REINTJES counter-claimed 4 against both plaintiffs for failure to pay invoiced payments and for extra labor charges and overtime purportedly resulting from delays and disruptions in the refractor work.

ST. PAUL also filed a counter-claim 5 against plaintiff challenging the validity of the bonds.

JRISS’ INTERESTS

According to plaintiffs’ motion, the project work carried out by REINTJES and JRISS concluded in April 2002 and approximately two to three months thereafter REINTJES “submitted a series of invoices to CE-Caribe for millions of dollars in alleged extra labor costs” caused by delays in construction. Plaintiffs’ Motion for Disqualification (docket No. 70 ¶ 11(a) p.7). Plaintiffs further note that “Recording to Reintjes’ original claim, its local subcontractor JRISS planned to work only 94,000 man-hours but actually worked 179,068 man-hours from October 2000 through April 2002. It is largely those extra hours that are in dispute and form the basis of Reintjes’ claim.” Id., ¶ 11(b) p. 8 (emphasis ours).

Pursuant to the documents submitted together with plaintiffs’ motion, JRISS, which is not a party to this case, has an outstanding claim against REINTJES for over one million dollars for refractory work performed under the contract. On two separate occasions JRISS requested *219 AES, DUKE/FLOUR DANIEL as well as plaintiffs herein to withhold payment of any monies due REINTJES until codefen-dant had satisfied JRISS’s debt. Additionally, JRISS sought payment of its outstanding claim from ST. PAUL.

Plaintiffs also note that according to the evidence on record JRISS owes REINTJES approximately $35,761.00 in back charges for material purchased by REINTJES on behalf of JRISS. Further, REINTJES acknowledged that it will seek reimbursement from JRISS for any damages assessed against codefendant REINTJES in these proceedings for defective insulation work.

EVENTS TRIGGERING THE CONFLICT OF INTEREST

The depositions of FELIX CAMACHO and JOSE ORTIZ, JRISS’ project manager and president respectively, were taken by plaintiffs on May 19, 20 and 21, 2003. During these depositions MR. FOX mentioned for the first time that he was also appearing on behalf of JRISS. Plaintiffs argue this dual representation of entities whose interests are directly adverse to each other triggered a conflict of interest which warrants disqualification of both MR. FOX and his law firm.

DISQUALIFICATION — STANDING AND APPLICABLE STANDARD

REINTJES questions plaintiffs’ standing to bring this matter to the court’s attention. Even though some jurisdictions have sided with REINTJES’s position, 6 in our jurisdiction non-parties to the attorney-client relationship have been found suitable to alert the court as to possible ethical violations including conflict of interests via motions to disqualify opposing counsel. Kevlik v. Goldstein, 724 F.2d 844, 848 (1st Cir.1984). See also, Reyes Cañada v. Rey-Hernandez,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
298 F. Supp. 2d 215, 2003 U.S. Dist. LEXIS 23382, 2003 WL 23112380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/combustion-engineering-caribe-inc-v-geo-p-reintjes-co-prd-2003.