This text of Combat Support Associates (Combat Support Associates) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Combat Support Associates, (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Combat Support Associates ) ASBCA Nos. 58945, 58946 ) Under Contract No. DASA02-99-C-1234 )

APPEARANCES FOR THE APPELLANT: Karen L. Manos, Esq. Owen E. Whitehurst, Esq. Gibson, Dunn & Crutcher LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Douglas R. Jacobson, Esq. Trial Attorney Defense Contract Management Agency Bloomington, MN

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL ON APPELLANT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

Appellant moves to dismiss these appeals from government claims for lack of jurisdiction, contending that the government's claims are barred by the statute of limitations. The Board denies the motion, without prejudice.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 13 July 1999, the Department of the Army (government) awarded Contract No. DASA02-99-C-1234 to appellant, Combat Support Associates, for the provision of support and security services in Kuwait (R4, tab 1 at 1; app. mot. at 1, ~ 1; gov't opp'n br. at 1).

2. On 30 August 2007, appellant submitted to the government its fiscal year (FY) 2006 incurred cost submission (ICS) (app. mot., ex. 1 at 2).

3. On 10 May 2007, the government requested that appellant submit three additional items: (1) a formal letter confirming the submission of the ICS; (2) a compact disc containing ''the same information"; and (3) a "Schedule T" (app. mot., ex. 2).

4. On 14 May 2007, appellant submitted to the government a formal letter confirming its ICS submission (app. mot., ex. 3). 5. On 20 May 2007, appellant submitted to the government its "Schedule T," and a compact disc with a copy of that schedule (app. mot., ex. 4).

6. On 25 August 2007, appellant submitted to the government revised Schedules A and B of its ICS (app. mot., ex. 5).

7. On 17 June 2013, the Defense Contract Audit Agency (DCAA) issued a report on an audit of the ICS (app. mot., ex. 6).

8. On 23 August 2013, the administrative contracting officer (ACO), having reviewed the DCAA audit report, issued two final decisions, one demanding that appellant pay the government $332,167 in disallowed direct costs (app. mot., ex. 7), and the other disallowing indirect costs and unilaterally determining appellant's indirect cost rates for FY 2006 (app. mot., ex. 8).

9. The ACO's payment demand consists of two categories of disallowed direct costs: (1) $308,889 in equipment costs, and (2) $23,278 in telephone and fax expenses (app. mot., ex. 7 at 1-2). The ACO disallowed and demanded repayment of$164,008 of the equipment costs because it determined that appellant had failed to provide documentation that justified the purchase of Caterpillar equipment from Winner International Trading Company (Winner), as opposed to from whom the ACO identified as the sole authorized distributor of Caterpillar equipment in Kuwait in FY 2006, Mohamed Adulrahman Al-Bahar (id. at 1). The amount disallowed was the difference in price between the two suppliers (app. mot., ex. 6 at 33). The ACO disallowed and demanded repayment of $144,881 of the equipment costs because it determined that appellant had failed to provide documentation that justified "the selection of Volvo Motor Road Grader rather than the lowest bidder supplier" (app. mot., ex. 7 at 1-2).

10. The ACO also disallowed and demanded repayment of $23,278 in telephone and fax expenses "to adjust for personal use of [the] telephones and fax machines by [appellant's] employees" (app. mot., ex. 7 at 2). The ACO explained that "[d]uring DCAA audit, [appellant] acknowledged" that the $108,777 in telephone and fax expenses that appellant had proposed "includes unallowable telephone/fax expenses costs [sic] that were not voluntarily deleted" (id.). Such personal-use telephone and fax expenses also comprise $13 3, 779 (of $625, 13 5 such expenses proposed) of the $1,409,464 in indirect cost disallowances that form the basis of the CO's unilateral determination of appellant's FY 2006 indirect cost rates (app. mot., ex. 8 at 1-3). Including telephone and fax expenses, those indirect cost disallowances consist of seven distinct categories (id. at 1).

11. On 2 October 2013, appellant timely filed an appeal docketed as ASBCA No. 58945 (appealing the CO's final decision demanding payment of disallowed direct costs), and filed an appeal docketed as ASBCA No. 58946 (appealing the CO's final decision disallowing indirect costs and determining indirect cost rates).

2 12. On 20 March 2014, DCAA Supervisory Auditor Kathryn Adamson declared under penalty of perjury that:

I have reviewed the DCAA files related to [appellant's ICS] and, to the best of my knowledge, the supporting data related to those costs identified in the two (2) Government contracting officer final decisions dated August 23, 2013 was not provided to the auditors until after August 23, 2007.

(Gov't opp'n, ex. G-1)

DECISION

Appellant seeks the dismissal of these appeals for lack of jurisdiction, contending that they are time barred pursuant to the Contract Disputes Act, 41 U.S.C. § 7103(a)(4). That section requires a contract claim to be "submitted within 6 years after the accrual of the claim." Id. The government opposes, making it the proponent of the Board's jurisdiction, with the burden of proving that the Board possesses jurisdiction to entertain the appeals. 1 Raytheon Missile Systems, ASBCA No. 58011, 13 BCA if 35,241 at 173,016. The government must establish, by a preponderance of the evidence, facts sufficient to invoke the Board's jurisdiction. See Reynolds v. Army & Air Force Exchange Service, 846 F.2d 746, 748 (Fed. Cir. 1988).

In deciding the motion, the Board has presumed undisputed facts to be true; disputed jurisdictional facts have been subjected to our fact-finding based upon a review of the record. Raytheon Missile Systems, 13 BCA if 35,241at173,016. A claim accrues under the CDA when "all events, that fix the alleged liability ... and permit assertion of the claim, were known or should have been known." Id. at 173,017 (citing FAR 33.201). Given the CDA's six-year limitation, to be timely, the government's 23 August 2013 claims must have accrued on or after 23 August 2007.

The government has met its burden, at least upon the record currently before the Board. Appellant contends that the government's claims accrued no later than 20 May

1 At page 2 of its brief, the government cites Sikorsky Aircraft Corp. v. United States, 105 Fed. Cl. 657 (2012) (the government's citation mistakenly reports that the court issued its opinion in 2013), an opinion that is not binding precedent for the Board. MA. Mortenson Co., ASBCA No. 53346, 05-2 BCA if33,014 at 163,616 n.3. In addition, the government follows that citation with a quotation (at page 3 of its brief) that does not appear in the opinion that begins at 105 Fed. Cl. 657, but in Sikorsky Aircraft Corp. v. United States, 110 Fed. Cl. 210, 220 (2013). The government provides "Sikorsky at 11" as the citation for the quotation. 3 2007 (app. mot. at 4), when (except for revisions to Schedules A and B) appellant completed the submission of its ICS (SOF ifif 5-6). The government contends that it "had no knowledge, and had no reason to know, whether the costs were allowable until [appellant] provided the detailed information (adequate supporting data) showing the costs were allowable" (gov't opp'n br. at 7).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weeks Marine, Inc. v. United States
575 F.3d 1352 (Federal Circuit, 2009)
Sikorsky Aircraft Corporation v. United States 09-844c &
110 Fed. Cl. 210 (Federal Claims, 2013)
Sikorsky Aircraft Corp. v. United States
105 Fed. Cl. 657 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Combat Support Associates, Counsel Stack Legal Research, https://law.counselstack.com/opinion/combat-support-associates-asbca-2014.